Item Descripción Und. Metrado Precio S/. Parcial S/. Subtotal S/.
02 MOVIMIENTO DE TIERRAS
04 TERRAPLEN 1,338,221.74
04.01 RELLENO CON MATERIAL PROPIO m3 91,195.93 5.58 508,873.29
04.02 RELLENO CON MATERIAL EXCEDENTE DE CORTE (MATERIAL CONSIDERADO EN TRASP.) m3 84,945.00 5.58 473,993.10
04.03 PREPARACION DE TERRENO EN ZONAS DE RELLENO, INVOLUCRANDO SUELO EXISTENTE m2 29,764.78 1.44 42,861.28
04.04 PREPARACION DE TERRENO EN ZONAS DE RELLENO, EMPLEANDO MATERIAL ADICIONADO m3 26,436.99 9.05 239,254.76
04.05 REMOCIÓN DE DERRUMBES (SOLO REFINE) m3 43,594.83 1.68 73,239.31
05 PAVIMENTOS 6,827,681.70
05.01 SUB BASE GRANULAR m3 90,238.57 24.77 2,235,209.38
05.02 BASE GRANULAR m3 54,700.30 38.90 2,127,841.67
05.03 IMPRIMACION BITUMINOSA m2 328,698.64 0.47 154,488.36
05.04 TRATAMIENTO SUPERFICIAL BICAPA m2 327,075.63 2.49 814,418.32
05.05 ASFALTO LIQUIDO RC-250 gln 84,146.85 4.34 365,197.33
05.06 ASFALTO DILUIDO MC-30 gln 215,869.91 4.59 990,842.89
05.07 KEROSENE gln 21,036.71 6.64 139,683.75
Item Descripción Und. Metrado Precio S/. Parcial S/. Subtotal S/.
12.01 EXCAVACION PARA ESTRUCTURAS (MAQUINARIA) m3 367.09 4.55 1,670.26
12.02 EXCAVACION PARA ESTRUCTURAS BAJO AGUA m3 550.64 10.19 5,611.02
12.03 ENCOFRADO Y DESENCOFRADO m2 723.19 30.62 22,144.08
12.04 ENCOFRADO Y DESENCOFRADO BAJO AGUA m2 55.98 55.89 3,128.72
12.05 ACERO DE REFUERZO f'y = 4200 kg/cm2 kg 23,208.66 3.57 82,854.92
12.06 CONCRETO f´c 280 kg/cm2 m3 75.27 341.67 25,717.50
12.07 CONCRETO f´c 210 kg/cm2 m3 113.25 289.75 32,814.19
12.08 CONCRETO f´c 210 kg/cm2 BAJO AGUA m3 92.12 308.00 28,372.96
12.09 CONCRETO f´c 100 kg/cm2 m3 15.58 201.55 3,140.15
12.10 RELLENO DE ESTRUCTURAS m3 709.16 50.40 35,741.66
12.11 JUNTAS DE EXPANSION METALICA m 18.60 761.47 14,163.34
12.12 APOYO DE NEOPRENO und 8.00 1,210.62 9,684.96
12.13 BARANDAS METALICAS m 43.00 506.75 21,790.25
12.14 EXCAVACIÓN EN SECO m3 150.93 4.88 736.54
12.15 EXCAVACIÓN BAJO AGUA m3 2,812.87 10.19 28,663.15
12.16 TERRAPLEN m3 18,572.02 11.33 210,420.99
12.17 ENROCADO m3 4,217.50 35.10 148,034.25
12.18 FILTRO m3 1,513.75 79.70 120,645.88
13 BADENES 1,549,610.65
13.01 EXCAVACION PARA ESTRUCTURAS (MAQUINARIA) m3 5,085.30 4.55 23,138.12
13.02 EXCAVACIÓN PARA ESTRUCTURAS (MANUAL) m3 395.18 21.17 8,365.96
13.03 BASE e=0.20m m3 1,424.94 33.67 47,977.73
13.04 ENCOFRADO Y DESENCOFRADO m2 1,798.90 30.62 55,082.32
13.05 ACERO DE REFUERZO f'y = 4200 kg/cm2 kg 119,982.53 3.57 428,337.63
13.06 CONCRETO f´c 245 kg/cm2 m3 1,713.93 308.15 528,147.53
13.07 JUNTA ASFALTICA LONGITUDINAL m 1,311.50 27.84 36,512.16
13.08 ALIVIADEROS Y EMBOQUILLADO DE PIEDRA (E=0.30M) m2 4,340.00 39.38 170,909.20
13.09 ENROCADO CON MORTERO m3 2,000.00 125.57 251,140.00
17 BAJADAS 45,822.92
17.01 EXCAVACION PARA ESTRUCTURAS m3 360.38 21.17 7,629.24
17.02 MAMPOSTERÍA DE PIEDRA (E=0.15 M) m2 1,369.44 27.89 38,193.68
18 RAPIDAS
18.01 EXCAVACION PARA ESTRUCTURAS m3 141.40 21.17 2,993.44
18.02 CONCRETO CICLOPEO f´c 140 kg/cm2 + 30% PM m3 22.01 191.10 4,206.11
18.03 ENCOFRADO Y DESENCOFRADO m2 90.34 30.62 2,766.21
18.04 MAMPOSTERÍA DE PIEDRA (E=0.15 M) m2 15.00 27.89 418.35
18.05 RELLENO DE ESTRUCTURAS m3 119.19 50.40 6,007.18
19 MUROS 5,250,743.61
19.01 EXCAVACION PARA ESTRUCTURAS (MAQUINARIA) m3 24,009.18 4.55 109,241.77
19.02 EXCAVACIÓN PARA ESTRUCTURAS (MANUAL) m3 79.10 21.17 1,674.55
19.03 ENCOFRADO Y DESENCOFRADO m2 33,458.86 30.62 1,024,510.29
19.04 ACERO DE REFUERZO f'y = 4200 kg/cm2 kg 15,871.41 7.07 112,210.87
19.05 SOLADO DE CONCRETO f´c 100 kg/cm2, E=0.075 M m3 9.45 15.01 141.84
19.06 CONCRETO f´c 210 kg/cm2 m3 276.83 289.75 80,211.49
19.07 CONCRETO CICLOPEO f´c 175 kg/cm2 + 30% PM, PARA MUROS m3 13,785.89 209.09 2,882,491.74
19.08 RELLENO DE ESTRUCTURAS m3 10,909.47 50.40 549,837.29
19.09 FILTRO m3 3,587.36 79.70 285,912.59
19.10 DREN PVC ø 4" m 5,137.05 14.81 76,079.71
19.11 LLORADORES PVC ø 4" m 3,317.70 14.81 49,135.14
19.12 GEOTEXTIL m2 11,467.97 5.11 58,601.33
19.13 MATERIAL IMPERMEABLE m3 366.80 49.72 18,237.30
19.14 ENROCADO m3 70.02 35.10 2,457.70
Presupuesto
Item Descripción Und. Metrado Precio S/. Parcial S/. Subtotal S/.
21 GAVIONES 1,023,408.03
21.01 EXCAVACION PARA GAVIONES m3 32,939.29 5.92 195,000.60
21.02 GAVIONES m3 5,217.00 158.79 828,407.43
22 SEÑALIZACIÓN 187,149.91
22.02 SEÑAL PREVENTIVA (0.75 m x 0.75 m) und 302.00 514.76 155,457.52
22.03 SEÑAL REGLAMENTARIA und 43.00 648.33 27,878.19
25 TRANSPORTES 11,714,699.33
25.01 TRANSPORTE DE MATERIALES GRANULARES PARA D <= 1.00 KM M3K 219,051.26 4.35 952,872.98
25.02 TRANSPORTE DE MATERIALES GRANULARES PARA D > 1.00 KM M3K 3,575,838.21 0.91 3,254,012.77
25.03 TRANSPORTE DE ESCOMBROS PARA D <= 1.00 KM M3K 1,121,706.92 4.35 4,879,425.10
25.04 TRANSPORTE DE ESCOMBROS PARA D > 1.00 KM M3K 730,610.21 0.91 664,855.29
25.05 TRANSPORTE DE MATERIAL PARA RELLENO D <= 1.00 KM M3K 204,157.53 4.35 888,085.26
25.06 TRANSPORTE DE MATERIAL PARA RELLENO D >= 1.00 KM M3K 1,181,810.91 0.91 1,075,447.93
26 VARIOS 614,236.24
26.01 MANTENIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL GLB 1.00 614,236.24 614,236.24
-----------------------
Sub-Total 67,969,334.86
IGV 19.00% 12,914,173.62
-------------------------
SON : OCHENTA MILLONES OCHOCIENTOS OCHENTITRES MIL QUINIENTOS OCHO Y 48/100 NUEVOS SOLES