PARTIDA:02.

02 MONTAJE DE TORRES TON


CUADRILLA:10.0 HOMBRES DIA RENDIMIENT: 70.0 AVANCE: 1.14 TON/DIA

ITEM DESCRIPCION UND CANTIDAD unitario Total

MANO DE OBRA 1.0 H-H


MOD0501 CAPATAZ 1.0 H-H 6.9986 S/. 28.45 S/. 199.11
MOD1012 OPERARIO MANIOBRISTA 8.0 H-H 6.9987 S/. 22.78 S/. 159.43
MOD2010 AYUDANTE 10.0 55.9898 S/. 13.70 S/. 767.06
S/. 1,125.60
CHOFERES YOPERADORES
CHO3040 CHOFER DE GRUA HIAB 0.120 H-H 0.8387 S/. 20.95 S/. 17.57
CHO3001 CHOFER CAMION 0.210 H-H 1.4114 S/. 9.26 S/. 13.07
CHO0108 TOPOGRAFO 0.143 H-H 1.0000 S/. 0.01 S/. 0.01
S/. 30.65
EQUIPOS
EQ65001 CAMION CON GRUA HIAB 5 TON 0.142 H-H 0.9932 S/. 32.50 S/. 32.28
EQ65700 CAMION D-300 0.249 H-H 1.7500 S/. 10.10 S/. 17.68
EQ75110 TEODOLITO 0.176 H-H 1.2325 S/. 4.00 S/. 4.93
EQ80400 PLUMAS DE IZADO 0.140 H-H 8.0000 S/. 1.70 S/. 13.60
ME00001 Equipos menores S/. 68.48
HE00001 Herramientas( % MOD) % 5.0000 S/. 5.00
S/. 141.97

TOTAL DEL COSTO UNITARIO S/. 1,298.22