To : Vineyard Construction
Attention : Ms Myrna Bandebas
Project : Sunvida Tower
Location : Cebu City
Email Address : vineyard.pur.myrna@gmail.com
Contact No : 0923-721-2568
Ref # : LAZ-QTN-1803-066
In response to your request, we are pleased to submit to you our proposal for the Supply & Delivery of Plumbing Fixtures of the above-captioned project as
follows:
Total
Qty Model Image Description Unit Price Project Price
(Php)
OPTION 1
9,830.00 5,337,690.00
Amazona pillar tap with hand showerand
543 BF3726PX 1,862.00
push button diverter
OPTION 2
8,790.00 4,772,970.00
Amazona pillar tap with hand showerand
543 BF3726PX 1,862.00
push button diverter
ABOVE PRICES ARE BASED ON CURRENT EXCHANGE RATE. PRICES INDICATED ARE SUBJECT FOR NEGOTIATION UPON RECEIPT OF ACTUAL
QUANTITY/REQUIREMENT.
PAYMENT /PRICE
· We require 50% Down payment upon placement of order. 50% Balance shall be payable prior to delivery.
· Check payment is subject to 3 banking days clearing before delivery.
PRICE VALIDITY
· Price is inclusive of VAT
· Price is valid for 90 days only.
· Unit Price is subject to change without prior notice
· Price offered is for the entire quotation. Any revision, exclusion in the quantity or items quoted will invalidate the price given and will require another
pricing scheme.
· In the event of foreign exchange fluctuation variations up to +/-3% from the date of PO / Signed Agreement, HPC & Customer will share the increase or
decrease in price variations based on the 50-50 sharing. Rate shall be based on prevailing BSP rates.
DELIVERY
· For Delivery accuracy, HPC will follow MATERIALS DELIVERY SCHEDULE. Customer shall inform HPC for any changes in delivery schedule. However, if the
change in the schedule is less than 75days, this may lead to delay of delivery.
· Request for advance delivery is subject to availability of the items and on first come first serve basis.
· 90 days delivery lead time from receipt of down payment
· Free delivery within Metro Manila only.
· Delivery of goods will be on ground level only.
· Changes in Specs, Quantity, & Delivery Address are subject to HPC approval
· Outright Inspection of Items upon delivery is required together with HPC authorized QA representative within 3 working days. Non inspection of goods
within 3 days shall mean all items delivered are IN GOOD CONDITION AND ACCEPTED BY THE CUSTOMER.
· Standard for Quality Inspection shall be in accordance with PNS (Philippine National Standard) guideline and procedure.
· Once goods are accepted, HPC will no longer be liable for damages or lacking of spare parts unless noted on the
Delivery Receipts.
If you have clarifications, you may contact me at 0945-2494969 or email at jvillarosa@lazuli.com.ph. Hope to hear from you soonest.