PROGRES FISIK & KEUANGAN

Pekerjaan : Pembangunan Kawasan Pariwisata Labuan Bajo Provinsi NTT TA. 2017/2018 RC total
Lokasi : Kawasan Permukiman Penunjang Pariwisata Labuan Bajo 36,690,753,000.00

Selesai Kontrak : 31 Agustus 2018


Hari/ Tanggal : Minggu, 20/05/2018 s.d. Jam 17.00 WITA

NILAI PADA SHOP/ REALISASI BIAYA STATUS BOBOT


NO URAIAN PEKERJAAN PANJANG (M') ASBUILT DRAWING KETERANGAN
(Rp.) Opname' (Rp.') (B/P/S) FISIK (%)

PEK. SALURAN TUNGGAL PASANGAN BATU RUAS 363.01 329,530,000.00 329,530,000.00 Selesai 0.90 Back-up Data tersedia 0.90
I A sd. F

II PEKERJAAN U-DITCH JALAN LINGKUNGAN


1 Ruas 1 108.00 89,887,000.00 89,887,000.00 Selesai 0.24 Back-up Data tersedia
2 Ruas 2 88.60 75,759,000.00 75,759,000.00 Selesai 0.21 Back-up Data tersedia
3 Ruas 3 124.00 105,154,000.00 105,154,000.00 Selesai 0.29 Back-up Data tersedia
4 Ruas 6 87.40 73,821,000.00 73,821,000.00 Selesai 0.20 Back-up Data tersedia
5 Ruas 7 54.60 47,229,000.00 47,229,000.00 Selesai 0.13 Back-up Data tersedia
6 Ruas 8 355.30 631,640,000.00 631,640,000.00 Selesai 1.72 Back-up Data tersedia
7 Ruas 12 548.50 951,997,000.00 951,997,000.00 Selesai 2.59 Back-up Data tersedia
8 Ruas 14 260.00 239,074,000.00 239,074,000.00 Selesai 0.65 Back-up Data tersedia
9 Ruas 17a 31.80 26,315,000.00 26,315,000.00 Selesai 0.07 Back-up Data tersedia
10 Ruas 18 293.00 232,297,000.00 232,297,000.00 Selesai 0.63 Back-up Data tersedia
Jumlah 1,951.20 2,240,876,000.00 ### 6.74 6.11

III RIGID PAVEMENT JALAN LINGKUNGAN


1 Ruas 1 113.00 269,000,000.00 185,284,000.00 Improve 0.50 (Back-up Data tersedia: sementara)
2 Ruas 2 88.60 120,000,000.00 92,000,000.00 Improve 0.25
3 Ruas 3 235.00 215,000,000.00 187,000,000.00 Improve 0.51
4 Ruas 7 68.60 64,532,000.00 64,532,000.00 Selesai 0.18 Back-up Data tersedia
5 Ruas 8 190.00 630,356,000.00 630,356,000.00 Selesai 1.72 Back-up Data tersedia
6 Ruas 12 702.00 5,284,732,000.00 ### Selesai 14.40 Back-up Data tersedia
7 Ruas 14 143.00 788,371,000.00 788,371,000.00 Selesai 2.15 Back-up Data tersedia
8 Ruas 17a 38.50 35,997,000.00 35,997,000.00 Selesai 0.10 Back-up Data tersedia
9 Ruas 17b 49.74 174,271,000.00 174,271,000.00 Selesai 0.47 Back-up Data tersedia
10 Ruas 18 239.00 960,140,000.00 960,014,000.00 Selesai 2.62 Back-up Data tersedia
Jumlah 1,628.44 8,542,399,000.00 ### 22.90 23.28

IV PEKERJAAN U-DITCH D.80 DI PEDESTRIAN 1,470.00 2,464,604,000.00 ### Selesai 6.52 6.72

V PEKERJAAN PEDESTRIAN (Kiri)


aSection I (Sta. 0+06 sd 200) 194.00 552,000,000.00 441,600,000.00 Proses 1.20 1.50
b Section II (Sta. 0+200 sd 0+430) 230.00 392,216,201.25 351,716,201.25 Proses 0.96 1.07
c Section III (Sta. 0+440 sd 0+799.5) 359.50 445,918,975.39 138,569,715.39 Proses 0.38 1.22
d Section IV (Sta. 0+808.5 sd 1+360) 552.00 676,391,236.20 477,221,236.20 Proses 1.30 1.84
eSection V (Sta. 1+372 sd 1+624) 252.00 298,906,868.70 291,031,868.70 Proses 0.79 0.81 6.45
f PJU 42 Unit 1,725,085,000.00 0.00 Belum 0.00 4.70
Jumlah 1,587.50 4,090,518,281.54 ### 4.63

VI PEKERJAAN JEMBATAN PROMENADE 40.00 3,303,000,000.00 608,078,000.00 Proses 1.66 9.00

VII PEKERJAAN RUANG TERBUKA HIJAU 320.00 3,000,000,000.00 Belum Review Design 8.18

VIII PEKERJAAN PENINGKATAN WISATA KULINER 175.00 4,335,000,000.00 ### Proses 5.62 11.81

IX PEKERJAAN DERMAGA APUNG DLL 4,200,000,000.00 ### Proses 3.53 Fabrikasi (Status PO) 11.45

X PEKERJAAN UMUM
1 Pembersihan Lapangan & Perataan 80,218,800.00 64,175,040.00 Proses 0.17 0.22
2 K3 320,000,000.00 272,000,000.00 Proses 0.74 0.87
3 Pengukuran 51,536,000.00 51,536,000.00 Selesai 0.14 0.14
4 Papan Proyek 2,500,000.00 2,500,000.00 Selesai 0.01 0.01
5 Mobilisasi dan Demobilisasi 450,000,000.00 382,500,000.00 Proses 1.04 1.23
6 Bedeng/ Direksi Keet 120,000,000.00 120,000,000.00 Selesai 0.33 0.33
Jumlah 1,024,254,800.00 892,711,040.00 2.43

Target Rencana Kemajuan Fisik Minggu Ini 69.87


Realisasi Kemajuan Fisik Minggu Ini ### ### 54.94

Deviasi (+,-) Negative 14.93


Total Kemajuan Fisik Minggu Lalu 53.68
Progres Kemajuan Fisik Dari Minggu Lalu 1.26

**** TOTAL REALCOST PADA NILAI KONTRAK (Rp.) 36,690,753,000.00 Konsultan MK


*** NILAI TOTAL PEKERJAAN UMUM (Rp.) 1,024,254,800.00
** TOTAL SEMENTARA REALCOST PADA NILAI SHOP/ASBUILT DRAWING (Rp.) 31,481,672,481.54
* NILAI REALCOST DALAM PROSES REVIEW DESIGN (Rp.) 4,184,825,718.46
Note: Berdasarkan Re-Schedule.2 Ir. Setia Widiantoro, MM.
Team Leader

LUASAN BATU KALI STA. 0+030 (A1)


= 0.68 M2
LUASAN BATU KALI STA. 0+040 (A2)
= 0.68 M2
PANJANG BATU KALI (L)
= 10.00 M'
VOLUME BATU KALI (STA. 0+030 - 0+040)
= (A1+A2)/2 x L
= 6.80 M3

STA. 0+040 - STA. 0+050

LUASAN BATU KALI STA. 0+040 (A1)


= 0.68 M2
LUASAN BATU KALI STA. 0+050 (A2)
= 0.68 M2
PANJANG BATU KALI (L)
= 10.00 M'
VOLUME BATU KALI (STA. 0+040 - 0+050)
= (A1+A2)/2 x L
= 6.80 M3

STA. 0+050 - STA. 0+060

LUASAN BATU KALI STA. 0+050 (A1)


= 0.68 M2
LUASAN BATU KALI STA. 0+060 (A2)
= 0.68 M2
PANJANG BATU KALI (L)
= 10.00 M'
VOLUME BATU KALI (STA. 0+050 - 0+060)
= (A1+A2)/2 x L
= 6.80 M3

STA. 0+060 - STA. 0+070

LUASAN BATU KALI STA. 0+060 (A1)


= 0.68 M2
LUASAN BATU KALI STA. 0+070 (A2)
= 0.68 M2
PANJANG BATU KALI (L)
= 10.00 M'
VOLUME BATU KALI (STA. 0+060 - 0+070)
= (A1+A2)/2 x L
= 6.80 M3

STA. 0+070 - STA. 0+080

LUASAN BATU KALI STA. 0+070 (A1)


= 0.68 M2
LUASAN BATU KALI STA. 0+080 (A2)
= 0.68 M2
PANJANG BATU KALI (L)
= 10.00 M'
VOLUME BATU KALI (STA. 0+070 - 0+080)
= (A1+A2)/2 x L
= 6.80 M3

STA. 0+080 - STA. 0+090

LUASAN BATU KALI STA. 0+080 (A1)


= 0.68 M2
LUASAN BATU KALI STA. 0+090 (A2)
= 0.68 M2
PANJANG BATU KALI (L)
= 10.00 M'
VOLUME BATU KALI (STA. 0+080 - 0+090)
= (A1+A2)/2 x L
= 6.80 M3

STA. 0+090 - STA. 0+100


LUASAN BATU KALI STA. 0+090 (A1)
= 0.68 M2
LUASAN BATU KALI STA. 0+100 (A2)
= 0.68 M2
PANJANG BATU KALI (L)
= 10.00 M'
VOLUME BATU KALI (STA. 0+090 - 0+100)
= (A1+A2)/2 x L
= 6.80 M3

STA. 0+100 - STA. 0+110


KMK Pembangunan Kawasan Pariwisata Labuan Bajo TA. 2017/2018
CATATAN MINGGU-51 terhadap Kontraktor Pelaksana
Minggu, 06 Mei 2018.

1. Beberapa item pekerjaan sedang dilaksanakan secara bersamaan, yaitu :


a. Pusat Kuliner
b. Pedestrian
c. Jembatan, a. Perakitan besi tulangan secara umum selesai 30%
b. Pemancangan minipile dan pengisian beton selesai
c. Pengecoran pondasi sumuran selesai
d. Pengecoran footplate selesai
Yang perlu dipersiapkan segera terkait pelaksanaan Konstruksi
berikutnya ; i. Scaffolding/ Perancah
ii. Begisting balok utama lengkung dan kolom abutmen
iii. Safety Net (Kiri-Kanan)
iv. Concrete Pump
v. Flexible Concrete Pipe ( Min. 50 M'), karena akses tunggal
mobil mixer yang hanya dari Jalan 12.

2. Perlu penambahan tenaga kerja di lapangan


3. Perlu segera didatangkan ke lokasi barang fabrikasi untuk mendukung
progres fisik dalam bentuk Materian on Site (MoS)
a. Canopy Membrant (Rangka sudah terpasang sebagian)
b. Dermaga Apung
4. Sangat perlu perhatian terhadap kewajiban Pelaksana terkait
persyaratan Administrasi Project, antara lain :
a. Request (Kuliner, Pedestrian), belum ada.
b. Asbuilt Drawing dan Back Up Data dari pekerjaan yang sudah selesai
dilaksanakan secara umum sementara ini sudah lengkap, kecuali ;
Pekerjaan Rigid Pavement Ruas Jalan 1, 2, dan 3 yang improve
dengan Pemasangan Batuan Andesit pada jalan anak tangga.

5. Perlu diperhatikan kembali 2 hal sebagai berikut :


a. Berita Acara Percepatan Pelaksanaan Pekerjaan, tertanggal 8 November 2017.
b. Teguran Solutif dari KMK, tertanggal 30 Januari 2018.
c. Teguran Administrasi dan Pelaksanaan dari KMK, tertanggal 25 April 2018.

6. Perlunya peningkatan Manajemen SDM dan Manajemen Keuangan.

7. Perlunya peningkatan komunikasi dan koordinasi multi pihak.