Ls Memasang 1 m' U-dicth 100x100x120x12

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


A TENAGA
Pekerja OH 0.8000 IDR 66,500.00 IDR 53,200.00
Tukang Batu OH 0.2000 IDR 89,700.00 IDR 17,940.00
Kepala Tukang Batu OH 0.0230 IDR 95,500.00 IDR 2,196.50
Mandor OH 0.2000 IDR 102,950.00 IDR 20,590.00

Jumlah Upah Tenaga Kerja IDR 93,926.50


B BAHAN
U-dicth & Tutupnya Buah 1.2000 IDR 2,000,000.00 IDR 2,400,000.00
Jumlah Harga Bahan IDR 2,400,000.00
C PERALATAN
Alat bantu Ls 1.0000 - IDR -
Mobil Crane Jam 0.1000 IDR 471,000.00 IDR 47,100.00
Jumlah Harga Alat IDR 47,100.00
D JUMLAH (A+B+C) IDR 2,541,026.50
E OVERHEAD & PROFIT (15%xD) IDR 381,153.98
F HARGA SATUAN PEKERJAAN (D+E) IDR 2,922,180.48

Ls Memasang 1 m' Box Culvert 100x100x120x15


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA
Pekerja OH 0.8000 IDR 66,500.00 IDR 53,200.00
Tukang Batu OH 0.2000 IDR 89,720.00 IDR 17,944.00
Kepala Tukang Batu OH 0.0230 IDR 95,600.00 IDR 2,198.80
Mandor OH 0.2000 IDR 102,950.00 IDR 20,590.00

Jumlah Upah Tenaga Kerja IDR 93,932.80


B BAHAN
Box Culvert Buah 1.2000 IDR 3,470,000.00 IDR 4,164,000.00
Jumlah Harga Bahan IDR 4,164,000.00
C PERALATAN
Alat bantu Ls 1.0000 - IDR -
Mobil Crane Jam 0.1000 - IDR -
Jumlah Harga Alat IDR -
D JUMLAH (A+B+C) IDR 4,257,932.80
E OVERHEAD & PROFIT (15%xD) IDR 638,689.92
F HARGA SATUAN PEKERJAAN (D+E) IDR 4,896,622.72