ID Task Name Duration 17 Jun '18 24 Jun '18 01 Jul '18 08 Jul '18 15 Jul '18 22 Jul '

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M
1 DEMOLICIONES 7.12 days? 0%
2 DEMOLICIÓN DE CONCRETO6 EXISTENTE
days? 0%
3 ACARREO DE MATERIAL CONCRETO
3 days? 0%
4 ELIMINACION DE DEMOLICIONES
6 days? 0%
5 TRAZOS, NIVELES Y REPLANTEO 6 days? 0%
6 TRAZO, NIVELACION Y REPLANTEO
2 days? 0%
7 TRAZO Y REPLANTEO DURANTE4 days?
EL PROCESO 0%
8 SEGURIDAD Y SALUD 1 day? 0%
9 ELABORACION, IMPLEMENTACION 0%
1 day?Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO
10 SEÑALIZACION DE SEGURIDAD 0% DE TRAFICO EN OBRA
1 day? Y/O DESVIO
11 PISOS Y PAVIMENTOS 3 days? 0%
12 MOVIMIENTO DE TIERRAS 3 days? 0%
13 PERFILADO Y COMPACTADO
3 days?DE SUB RASANTE EN ZONAS DE CORTE 0%
14 PERFILADO Y COMPACTADO
3 days? DE SUBRASANTE EN ZONAS DE CORTE 0% C/EQUIPO LIVIANO
15 PERFILADO Y COMPACTADO
1 day? DE SUB RASANTE EN ZONA DE 0%
CORTE C/MAQUINARIA
16 PISTAS 27 days? 0%
17 PAVIMENTO RÍGIDO 27 days? 0%
18 PAVIMENTO RIGIDO: CONCRETO
9 days? f´c= 210 KG/CM2 0%
19 PAVIMENTO RIGIDO: ENCOFRADO
13 days? Y DESENCOFRADO 0%
20 PAVIMENTO RIGIDO: CURADO
4 days?DE LOSA 0%
21 PAVIMENTO RIGIDO: JUNTA
5 days?
ASERRADA E=1" 0%
22 PAVIMENTO RIGIDO: JUNTA1 day?
ASERRADA; E=6 mm. 0%
23 CUNETAS 7 days? 0%
24 CUNETA: CONCRETO F´C = 210 1 day?
KG/CM2 0%
25 CUNETA: ENCOFRADO Y DESENCOFRADO
6 days? 0%
26 CUNETA: JUNTA SERRADA E=1" 1 day? 0%
27 TRABAJOS DE CULMINACION DE 1OBRA day? 0%
28 LIMPIEZA FINAL DE OBRA 1 day? 0%

Critical Baseline Project Summary


Critical Split Baseline Split External Tasks

Project: Cronograma Critical Progress Baseline Milestone External Milestone


Date: Fri 15/06/18 Task Milestone Deadline
Split Summary Progress
Task Progress Summary

Page 1