Predimensionamiento
Predimensionamiento
DATOS:
N° DE PISOS 5
CARGA MUERTA
Aligerado 280 kg/m2
Tabiquería 8.1 kg/m2
Peso propio vigas 100 kg/m2
Peso propio columnas 100 kg/m2
TOTAL 488.1 kg/m2
CARGA VIVA
S/C Hoteles 500 kg/m2
TOTAL 500 kg/m2
CARGA ULTIMA
Peso total por piso 1533.34 Kg/m2
Peso total de los 4 pisos 6133.36 Kg/m2
f'c = 210 Kg/cm2
TIPO DE
LOCALIZACIÓN COLUMNA L1 L2 L3 L4 Area (m)
COLUMNA INTERIOR
C-3 5.25 4.2 4.67 3.93 20.32
EJE C-C C-3 5.11 5.25 6.5 4.67 28.93
C-3 5.25 5.25 6.5 4.67 29.32
C-3 5.25 5.25 6.5 4.67 29.32
C-3 5.25 4.2 6.5 4.67 26.39
EJE D-D C-3 5.11 5.25 3.65 6.5 26.29
C-3 5.25 5.25 3.65 6.5 26.64
C-3 5.25 5.25 3.65 6.5 26.64
C-3 5.25 4.2 3.65 6.5 23.98
RESUMEN
BASE ANCHO
COLUMNAS DE DISEÑO cm cm
C-1 40 30
C-2 40 65
C-3 50 70
UMNAS
asumir
bxD b=D b min
P b (cm) h (cm)
(cm) (cm) (cm)
30792.99 610.97 25 40 40 30 30
23699.30 470.22 22 40 40 30
61899.40 1228.16 35 40 40 30
50876.22 1009.45 32 40 40 30
62429.63 1238.68 35 40 40 30 65
62429.63 1238.68 35 40 40 30
62429.63 1238.68 35 40 40 30
62429.63 1238.68 35 40 40 30
67384.16 1336.99 37 40 40 35
55384.24 1098.89 33 40 40 30
87521.05 1736.53 42 40 40 40
71935.11 1427.28 38 40 40 35
79528.98 1577.96 40 40 40 40
65366.28 1296.95 36 40 40 30
61899.40 1228.16 35 40 40 30
125494.68 2489.97 50 40 40 60
127190.55 2523.62 50 40 40 60
114471.50 2271.26 48 40 40 55
136614.46 2710.60 52 50 50 65 70
138460.60 2747.23 52 50 50 65
138460.60 2747.23 52 50 50 65
124614.54 2472.51 50 50 50 60
177439.94 3520.63 59 50 50 85
179837.78 3568.21 60 50 50 90
179837.78 3568.21 60 50 50 70
161854.00 3211.39 57 50 50 80
161236.83 3199.14 57 50 50 80
163415.71 3242.38 57 50 50 80
163415.71 3242.38 57 50 50 80
147074.14 2918.14 54 50 50 80
PREDIMENSIONAMIENTO DE VIGAS
�=
𝐁/𝟐�
�=
𝐋𝐧/�
Donde:
Ln : luz de la viga
B: Ancho Tributario
VIGAS PRINCIPALES
K= 12 USAR
b h bo ho
TIPO Ln B b (cm) h(cm)
(m) (m) (cm) (cm)
VP-101 4.86 1.78 0.09 0.41 25.00 28.70
A-A
b h b
TRIPOS cm cm cm
ESQUINAS C-1 40 30 VP-101 25
PRINCIPALES
LATERALES C-2 40 65 VP-102 25
INTERIOR C-3 50 70 VP-103 25
VP-104 25
VP-105 25
VS-101 25
Las dimensiones de las vigas secundarias se VS-102 25
SECUNDARIAS
asumen según reglamento VS-103 25
VS-104 25
VS-105 25
VS-106 25
VS-107 25
b
cm
VP-101 25
VP-102 25
VP-103 30
VS-101 25
(𝐕𝐏−𝟏�𝟐)=(𝐕𝐏−𝟏�𝟒)=(𝐕𝐏−𝟏�𝟓)
S
EN DE VIGAS
h
cm
30
40
45
40
40
30
30
30
30
30
30
30
h
cm
30
40
45
30
−𝟏�𝟒)=(𝐕𝐏−𝟏�𝟓)
RIGIDEZ DE COLUMNAS
E= 2173706.51 Tn/m2
B H ALTURA INERCIA K (I/L)
TIPO DE COLUMNA
m m m m4 m3
C-1 0.40 0.30 3.00 0.000900 0.000300
C-2 0.40 0.65 3.00 0.009154 0.003051
C-3 0.50 0.70 3.00 0.014292 0.004764
RIGIDEZ DE VIGAS
NIVELES (1, 2, 3, 4 Y 5)
K (emp.)
Ton/m
869.483
8843.765
13807.062
METODO DE WILBUR "P
PRIMER NIVEL EJE "X"
DATOS:
Kc1 = 0.000300000 m3 �𝟏=𝟒𝟖𝐄/�𝟏[(𝟒(�𝟏))/(∑▒�𝐜𝟏
Kc2 = 0.003051389 m3 (�𝟏+�𝟐)/(∑▒ 〖��� +
Kc3 = 0.004763889 m3 ▒▒��𝟏)/𝟏𝟐 〗 )]
(∑
E= 2173706.512 Tn/m2
h1 = 3 m Kv1 = Kv2
h2 = 3 m
h1+h2 = 6 m
EJE A-A
COLUMNAS Kc VIGAS Kv
C1 0.00030 V1 0.00013
C2 0.00305 V2 0.00012
C2 0.00305 V3 0.00012
C2 0.00305
C1 0.00030
0.00000 TOTAL 0.00037
TOTAL 0.00975 m3
K= 5518.5786982963 Tn/m
EJE B-B
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 16270.4930184819 Tn/m
EJE C-C
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00042566
C3 0.00476389 V2 0.00039967
C3 0.00476389 V3 0.00039967
C3 0.00476389 V4 0.00039967
C3 0.00476389 V5 0.00053477
C2 0.00305139 TOTAL 0.00215944
TOTAL 0.02515833 m3
K= 18433.3162735036 Tn/m
EJE D-D
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 16270.4930184819 Tn/m
EJE E-E
COLUMNAS Kc VIGAS Kv
C1 0.00030000 V1 0.00029762
C2 0.00305139 V2 0.00028986
C2 0.00305139 V3 0.00028986
C2 0.00305139 V4 0.00028986
C2 0.00305139 V5 0.00037244
C1 0.00030000 TOTAL 0.00153962
TOTAL 0.01280556 m3
K= 10738.3071158579 Tn/m
RIGIDEZ TOTAL
KX = 67231.188124622 Tn/m
DO DE WILBUR "PRIMER NIVEL"
PRIMER NIVEL EJE "Y"
DATOS:
𝐄/�𝟏[(𝟒(�𝟏))/(∑▒�𝐜𝟏)+ Kc1 = 0.000300000 m3
𝟐)/(∑▒ 〖��� + Kc2 = 0.003051389 m3
𝟏)/𝟏𝟐 〗 )] Kc3 = 0.004763889 m3
E= 2173706.512 Tn/m2
h1 = 3 m
h2 = 3 m
h1+h2 = 6 m
EJE 1-1
COLUMNAS Kc VIGAS
C1 0.0003000 V1
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
m3 TOTAL 0.0097542 m3
K= 6363.453625653 Tn/m
EJE 2-2
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 10913.35993969 Tn/m
EJE 3-3
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 10913.35993969 Tn/m
EJE 4-4
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 10913.35993969 Tn/m
EJE 5-5
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 10913.35993969 Tn/m
EJE 6-6
COLUMNAS Kc VIGAS
0.0000000
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
TOTAL 0.0094542 m3
K= 5608.473381474 Tn/m
RIGIDEZ TOTAL
KY = 55625.366766 Tn/m
"Y"
Kv
0.00017578
0.00013993
0.00009615
0.00019198
0.00060384 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00000000
0.00013993
0.00009615
0.00019264
0.00042872 m3
METODO DE WILBUR "SE
SEGUNDO NIVEL EJE "X"
DATOS: �𝟏=𝟒𝟖𝐄/�𝟐[(𝟒(�𝟏))/(∑▒�𝐜𝟐)+(�𝟏+�𝟐)/
Kc1 = 0.000300000 m3 ▒▒��𝟏)/𝟏𝟐 〗 ) +(��+��)/(∑▒��𝟐)]
〖��� +(∑
Kc2 = 0.003051389 m3
Kc3 = 0.004763889 m3
E= 2173706.512 Tn/m2 Kv1 = Kv2
h1 = 3 m Kc1 = Kc2
h2 = 3 m
h1+h2 = 6 m
EJE A-A
COLUMNAS Kc VIGAS Kv1
C1 0.00030 V1 0.00013
C2 0.00305 V2 0.00012
C2 0.00305 V3 0.00012
C2 0.00305
C1 0.00030
0.00000 TOTAL 0.00037
TOTAL 0.00975 m3
K= 1544.8517026201 Tn/m
EJE B-B
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 5707.4501684601 Tn/m
EJE C-C
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00042566
C3 0.00476389 V2 0.00039967
C3 0.00476389 V3 0.00039967
C3 0.00476389 V4 0.00039967
C3 0.00476389 V5 0.00053477
C2 0.00305139 TOTAL 0.00215944
TOTAL 0.02515833 m3
K= 7454.9589302099 Tn/m
EJE D-D
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 5707.4501684601 Tn/m
EJE E-E
COLUMNAS Kc VIGAS Kv
C1 0.00030000 V1 0.00029762
C2 0.00305139 V2 0.00028986
C2 0.00305139 V3 0.00028986
C2 0.00305139 V4 0.00028986
C2 0.00305139 V5 0.00037244
C1 0.00030000 TOTAL 0.00153962
TOTAL 0.01280556 m3
K= 4873.8749685167 Tn/m
RIGIDEZ TOTAL
KX = 25288.585938267 Tn/m
O DE WILBUR "SEGUNDO NIVEL"
SEGUNDO NIVEL EJE "Y"
))/(∑▒�𝐜𝟐)+(�𝟏+�𝟐)/(∑▒ DATOS:
𝟐 〗 ) +(��+��)/(∑▒��𝟐)] Kc1 = 0.000300000 m3
Kc2 = 0.003051389 m3
Kc3 = 0.004763889 m3
E= 2173706.512 Tn/m2
h1 = 3 m
h2 = 3 m
h1+h2 = 6 m
EJE 1-1
COLUMNAS Kc VIGAS
C1 0.0003000 V1
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
m3 TOTAL 0.0097542 m3
K= 2258.120223764 Tn/m
EJE 2-2
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 2669.04379312 Tn/m
EJE 3-3
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 2669.04379312 Tn/m
EJE 4-4
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 2669.04379312 Tn/m
EJE 5-5
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 2669.04379312 Tn/m
EJE 6-6
COLUMNAS Kc VIGAS
0.0000000
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
TOTAL 0.0094542 m3
K= 1722.047881879 Tn/m
RIGIDEZ TOTAL
KY = 14656.343278 Tn/m
E "Y"
Kv
0.00017578
0.00013993
0.00009615
0.00019198
0.00060384 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00000000
0.00013993
0.00009615
0.00019264
0.00042872 m3
METODO DE WILBUR "T
TERCER NIVEL EJE "X"
DATOS:
Kc1 = 0.000300000 m3 ��=𝟒𝟖𝐄/��[(𝟒(��))/(∑▒�𝐜�)+(�𝟐+��)/
Kc2 = 0.003051389 m3 (∑
▒▒�𝐯𝟐) +(��+�𝟒)/(∑▒���)]
Kc3 = 0.004763889 m3
E= 2173706.512 Tn/m2
h2 = 3 m
h3 = 3 m
h4 = 3 m
h2+h3 = 6 m
h3+h4 = 6 m
EJE A-A
COLUMNAS Kc VIGAS Kv
C1 0.00030 V1 0.00013
C2 0.00305 V2 0.00012
C2 0.00305 V3 0.00012
C2 0.00305
C1 0.00030
0.00000 TOTAL 0.00037
TOTAL 0.00975 m3
K= 1033.5026927545 Tn/m
EJE B-B
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 4145.7354285533 Tn/m
EJE C-C
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00042566
C3 0.00476389 V2 0.00039967
C3 0.00476389 V3 0.00039967
C3 0.00476389 V4 0.00039967
C3 0.00476389 V5 0.00053477
C2 0.00305139 TOTAL 0.00215944
TOTAL 0.02515833 m3
K= 5763.919341074 Tn/m
EJE D-D
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 4145.7354285533 Tn/m
EJE E-E
COLUMNAS Kc VIGAS Kv
C1 0.00030000 V1 0.00029762
C2 0.00305139 V2 0.00028986
C2 0.00305139 V3 0.00028986
C2 0.00305139 V4 0.00028986
C2 0.00305139 V5 0.00037244
C1 0.00030000 TOTAL 0.00153962
TOTAL 0.01280556 m3
K= 3983.3336661976 Tn/m
RIGIDEZ TOTAL
KX = 19072.226557133 Tn/m
DO DE WILBUR "TERCER NIVEL"
TERCER NIVER EJE "Y"
DATOS:
)/(∑▒�𝐜�)+(�𝟐+��)/ Kc1 = 0.000300000 m3
∑▒���)] Kc2 = 0.003051389 m3
Kc3 = 0.004763889 m3
E= 2173706.512 Tn/m2
h2 = 3 m
h3 = 3 m
h4 = 3 m
h2+h3 = 6 m
h3+h4 = 6 m
EJE 1-1
COLUMNAS Kc VIGAS
C1 0.0003000 V1
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
m3 TOTAL 0.0097542 m3
K= 1648.069421582 Tn/m
EJE 2-2
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 1715.300026547 Tn/m
EJE 3-3
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 1715.300026547 Tn/m
EJE 4-4
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 1715.300026547 Tn/m
EJE 5-5
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 1715.300026547 Tn/m
EJE 6-6
COLUMNAS Kc VIGAS
0.0000000
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
TOTAL 0.0094542 m3
K= 1188.636737975 Tn/m
RIGIDEZ TOTAL
KY = 9697.9062657 Tn/m
"Y"
Kv
0.00017578
0.00013993
0.00009615
0.00019198
0.00060384 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00000000
0.00013993
0.00009615
0.00019264
0.00042872 m3
METODO DE WILBUR "C
CUARTO NIVEL EJE "X"
DATOS:
Kc1 = 0.000300000 m3 �𝟒=𝟒𝟖𝐄/�𝟒[(𝟒(�𝟒))/(∑▒�𝐜𝟒)+(��+�𝟒)/
Kc2 = 0.003051389 m3 (∑
▒▒�𝐯�) +(�𝟒+�𝟓)/(∑▒��𝟒)]
Kc3 = 0.004763889 m3
E= 2173706.512 Tn/m2
h3 = 3 m
h4 = 3 m
h5 = 3 m
h3+h4 = 6 m
h4+h5= 6 m
EJE A-A
COLUMNAS Kc VIGAS Kv
C1 0.00030 V1 0.00013
C2 0.00305 V2 0.00012
C2 0.00305 V3 0.00012
C2 0.00305
C1 0.00030
0.00000 TOTAL 0.00037
TOTAL 0.00975 m3
K= 1033.5026927545 Tn/m
EJE B-B
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 4145.7354285533 Tn/m
EJE C-C
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00042566
C3 0.00476389 V2 0.00039967
C3 0.00476389 V3 0.00039967
C3 0.00476389 V4 0.00039967
C3 0.00476389 V5 0.00053477
C2 0.00305139 TOTAL 0.00215944
TOTAL 0.02515833 m3
K= 5763.919341074 Tn/m
EJE D-D
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 4145.7354285533 Tn/m
EJE E-E
COLUMNAS Kc VIGAS Kv
C1 0.00030000 V1 0.00029762
C2 0.00305139 V2 0.00028986
C2 0.00305139 V3 0.00028986
C2 0.00305139 V4 0.00028986
C2 0.00305139 V5 0.00037244
C1 0.00030000 TOTAL 0.00153962
TOTAL 0.01280556 m3
K= 3983.3336661976 Tn/m
RIGIDEZ TOTAL
KX = 19072.226557133 Tn/m
O DE WILBUR "CUARTO NIVEL"
CUARTO NIVEL EJE "Y"
DATOS:
)/(∑▒�𝐜𝟒)+(��+�𝟒)/ Kc1 = 0.000300000 m3
∑▒��𝟒)] Kc2 = 0.003051389 m3
Kc3 = 0.004763889 m3
E= 2173706.512 Tn/m2
h3 = 3 m
h4 = 3 m
h5 = 3 m
h3+h4 = 6 m
h4+h5= 6 m
EJE 1-1
COLUMNAS Kc VIGAS
C1 0.0003000 V1
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
m3 TOTAL 0.0097542 m3
K= 1648.069421582 Tn/m
EJE 2-2
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 1715.300026547 Tn/m
EJE 3-3
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 1715.300026547 Tn/m
EJE 4-4
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 1715.300026547 Tn/m
EJE 5-5
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 1715.300026547 Tn/m
EJE 6-6
COLUMNAS Kc VIGAS
0.0000000
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
TOTAL 0.0094542 m3
K= 1188.636737975 Tn/m
RIGIDEZ TOTAL
KY = 9697.9062657 Tn/m
"Y"
Kv
0.00017578
0.00013993
0.00009615
0.00019198
0.00060384 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00000000
0.00013993
0.00009615
0.00019264
0.00042872 m3
METODO DE WILBUR "Q
QUINTO NIVEL EJE "X"
DATOS:
Kc1 = 0.000300000 m3 �𝟓=𝟒𝟖𝐄/�𝟓[(𝟒(�𝟓))/(∑▒�𝐜𝟓)+(�𝟒+�𝟓)/
Kc2 = 0.003051389 m3 (∑
▒▒�𝐯𝟒) +(�𝟓+��)/(∑▒��𝟓)]
Kc3 = 0.004763889 m3
E= 2173706.512 Tn/m2
h4 = 3 m
h5 = 3 m
h6 = 0 m
h4+h5 = 6 m
h5+h6 = 3 m
EJE A-A
COLUMNAS Kc VIGAS Kv
C1 0.00030 V1 0.00013
C2 0.00305 V2 0.00012
C2 0.00305 V3 0.00012
C2 0.00305
C1 0.00030
0.00000 TOTAL 0.00037
TOTAL 0.00975 m3
K= 1361.4134303819 Tn/m
EJE B-B
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 5424.8348749165 Tn/m
EJE C-C
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00042566
C3 0.00476389 V2 0.00039967
C3 0.00476389 V3 0.00039967
C3 0.00476389 V4 0.00039967
C3 0.00476389 V5 0.00053477
C2 0.00305139 TOTAL 0.00215944
TOTAL 0.02515833 m3
K= 7487.921549228 Tn/m
EJE D-D
COLUMNAS Kc VIGAS Kv
C2 0.00305139 V1 0.00029895
C3 0.00476389 V2 0.00028070
C3 0.00476389 V3 0.00028070
C3 0.00476389 V4 0.00028070
C3 0.00476389 V5 0.00037559
C2 0.00305139 TOTAL 0.00151665
TOTAL 0.02515833 m3
K= 5424.8348749165 Tn/m
EJE E-E
COLUMNAS Kc VIGAS Kv
C1 0.00030000 V1 0.00029762
C2 0.00305139 V2 0.00028986
C2 0.00305139 V3 0.00028986
C2 0.00305139 V4 0.00028986
C2 0.00305139 V5 0.00037244
C1 0.00030000 TOTAL 0.00153962
TOTAL 0.01280556 m3
K= 5127.6660405717 Tn/m
RIGIDEZ TOTAL
KX = 24826.670770015 Tn/m
O DE WILBUR "QUINTO NIVEL"
QUINTO NIVEL EJE "Y"
DATOS:
)/(∑▒�𝐜𝟓)+(�𝟒+�𝟓)/ Kc1 = 0.000300000 m3
∑▒��𝟓)] Kc2 = 0.003051389 m3
Kc3 = 0.004763889 m3
E= 2173706.512 Tn/m2
h4 = 3 m
h5 = 3 m
h6 = 0 m
h4+h5 = 6 m
h5+h6 = 3 m
EJE 1-1
COLUMNAS Kc VIGAS
C1 0.0003000 V1
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
m3 TOTAL 0.0097542 m3
K= 2155.538797154 Tn/m
EJE 2-2
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 2265.155543252 Tn/m
EJE 3-3
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 2265.155543252 Tn/m
EJE 4-4
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 2265.155543252 Tn/m
EJE 5-5
COLUMNAS Kc VIGAS
C2 0.0030514 V1
C3 0.0047639 V2
C3 0.0047639 V3
C3 0.0047639 V4
C2 0.0030514 TOTAL
m3 TOTAL 0.0203944 m3
K= 2265.155543252 Tn/m
EJE 6-6
COLUMNAS Kc VIGAS
0.0000000
C2 0.0030514 V2
C2 0.0030514 V3
C2 0.0030514 V4
C1 0.0003000 TOTAL
TOTAL 0.0094542 m3
K= 1562.258891821 Tn/m
RIGIDEZ TOTAL
KY = 12778.419862 Tn/m
"Y"
Kv
0.00017578
0.00013993
0.00009615
0.00019198
0.00060384 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00017689
0.00014169
0.00009698
0.00019397
0.00060952 m3
Kv
0.00000000
0.00013993
0.00009615
0.00019264
0.00042872 m3
MODE
RESUMEN "MÉTODO DE WILBUR"
K5 = 24826.671 Tn/m
KX KY
NIVELES
Tn/m Tn/m
PRIMER NIVEL 67231.188124622 55625.36676587
SEGUNDO NIVEL 25288.585938267 14656.343278124
K4 = 19072.227 Tn/m
TERCER NIVEL 19072.226557133 9697.9062657464
CUARTO NIVEL 19072.226557133 9697.9062657464
QUINTO NIVEL 24826.670770015 12778.419861985
K3 = 19072.227 Tn/m
K2 = 25288.586 Tn/m
K1 = 67231.188 Tn/m
𝐄𝐉𝐄 �
MODELO DINÁMICO
K5 = 12778.42 Tn/m
K4 = 9697.9063 Tn/m
K3 = 9697.9063 Tn/m
K2 = 14656.343 Tn/m
K1 = 55625.367 Tn/m
𝐄𝐉𝐄 �