COMPARATIVO DE AVANCE DE OBRA - CURVA "S"

"AMPLIACION DE LA INFRAESTRUCTURA SEGUNDO NIVEL DE LA I.E.P. VICENTE DE LA VEGA PJ 09 DE OCTUBRE II - ETAPA, DISTRITO
OBRA :
CHICLAYO – CHICLAYO – LAMBAYEQUE"
MES: FEBRERO DEL 2018
ENTIDAD : SOCIEDAD DE BENEFICENCIA DE CHICLAYO

Curva S
250,000.00

Row 39 Row 38
200,000.00

146,381.40
150,000.00 146,381.40
S/. 133,787.50

107,165.75
100,000.00 100,970.48

56,813.98
50,000.00 50,239.42

26,051.37 MESES

0.00 0.00
QUIN. 1 QUIN. 2 QUIN. 3 QUIN. 4

QUIN. 1 QUIN. 2 QUIN. 3 QUIN. 4


AVANCE QUINCENAL EJECUTADO S/. 56,813.98 44,156.50 32,817.02 12,593.98
AVANCE QUINCENAL PROGRAMADO S/. 26,051.37 24,188.05 56,926.34 39,215.65
AVANCE QUINCENAL ACUMULADO S/. 0 56,813.98 100,970.48 133,787.50 146,381.40
AVANCE QUINCENAL ACUM. PROGRAMADO S/. 0 26,051.37 50,239.42 107,165.75 146,381.40
AVANCE MENSUAL EJECUTADO % 38.81% 30.17% 22.42% 8.60%
AVANCE MENSUAL PROGRAMADO % 17.80% 16.52% 38.89% 26.79%
AVANCE ACUM. EJECUTADO % 38.81% 68.98% 91.40% 100.00%
AVANCE ACUM. PROGRAMADO % 17.80% 34.32% 73.21% 100.00%