S.NO LOCATION SANITARY WARE STATUS DESCRIPTION OF DELAY INSPECTION REPORT


1 MV-1 FF MASTER BATHROOM 1(RC 1.17) a. Thermostat and ppr connection Installed Approved
b.Bathtub and accessories Not yet installed Delay because of marbel not yet finish
c. wc frame installation Installed Approved
d.wc, bidet,wash basin, basin mixer installation Not yet installed Delay because of marbel not yet finish
e. shower drain and floor drain Installed Approved

2 MV-1 GF MASTER BATHROOM (RC 0.06) a.thermostat installation Installed Raised/Under review
b.ppr connection Installed Raised/Under review
c. bathtub and accessories Not yet installed Delay because of marbel not yet finish
d.wc frame installation Installed Approved
e. wc,bidet , wash basin, basin mixer installation Not yet installed Delay because of marbel not yet finish
f. shower drain and floor drain Not yet installed to be install along with marbel

3 MV-2 PRIVATE LIVING ROOM TOILET a. Wc frame installation Installed Need approved drawing to raise the inspection
b. Wc,bidet, wash basin,basin mixer installation Not yet installed Delay because of marbel not yet finish

4 DUNE VILLA TOILET & WASH 2 a. Wc frame installtion Installed Approved


b. Wc,bidet, wash basin,basin mixer installation Not yet installed Delay because of marbel not yet finish

5 DUNE VILLA ENTRANCE TOILET SHOWER a.thermostat and ppr connection Installed Approved
b.wc frame installation Installed Approved
c. Wc,bidet, wash basin,basin mixer installation Not yet installed Delay because of marbel not yet finish

6 DUNE VILLA TOILET & WASH 1 a. Wc frame installtion Installed Approved


b. Wc,bidet, wash basin,basin mixer installation Not yet installed Installation belongs to THG

7 CLUB HOUSE GF SPA a. Wc frame installtion Installed Need approved drawing to raise the inspection
b. Wc,bidet, wash basin,basin mixer installation Not yet installed Delay because of marbel not yet finish

8 CLUB HOUSE MASTER BATHROOM FF a. Wc frame installtion Installed Need approved drawing to raise the inspection
b. Wc,bidet, wash basin,basin mixer installation Not yet installed Delay because of marbel not yet finish
c.thermostat and ppr connection need approved drawing to fix.

9 MV-1FF LADY'S MASTER BATHROOM1 a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG
10 MV-1FF LADY'S MASTER BATHROOM2 a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG
11 MV-1FF LADY'S MASTER BATHROOM3 a. Wc frame installtion incomplete(water proofing to be done) Remaining sanitary ware installation
belongs to THG
12 MV-1 FF MASTER BATHROOM2 (RC 1.17) a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG
13 MV-2 MASTER BATHROOM SUITE a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG
14 MV-2 MASTER BATHROOM 1 a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG
15 MASTER BATHROOM 2 MV-2 a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG
16 MV-2 OFFICE TOILET a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG

17 MV-1GF TOILET AND WASH 1 a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG
18 MV-1GF LADIES TOILET & WASH 1 a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG
19 MV-1FF FAMILY WASH & TOILET a. Wc frame installtion Installed Remaining sanitary ware installation
belongs to THG
20 MV-2 WASH & TOILET 2 a. Wc frame installtion incomplete(need wall chipping) Remaining sanitary ware installation
belongs to THG