ID Task Task Name Duration Start Finish 27 Dec '1717 Jan '18 07 Feb '1828 Feb '1821 Mar

27 Dec '1717 Jan '18 07 Feb '1828 Feb '1821 Mar '1811 Apr '1802 May '18
Mode M T W T F S S M T W T F S S M T W
1 PROYECTO 97 days Thu 18/01/18 Tue 24/04/18
2 APROBACION DEL PROYECTO 0 days Thu 18/01/18 Thu 18/01/18 18/01
3 IMPORTACION DE LONA 13 days Thu 18/01/18 Tue 30/01/18
4 FABRICACION Y PINTURA DE ESTRUCTURAS 47 days Thu 18/01/18 Mon 05/03/18
5 FABRICACION 37 days Thu 18/01/18 Fri 23/02/18
6 ARENADO Y PINTURA 14 days Tue 20/02/18 Mon 05/03/18
7 MONTAJE DE ESTRUCTURAS 47 days Sun 04/03/18 Thu 19/04/18
8 PERFORACION DE COLUMNAS 26 days Sun 04/03/18 Thu 29/03/18
9 FASE 1 5 days Sun 04/03/18 Thu 08/03/18
10 FASE 2 12 days Sun 18/03/18 Thu 29/03/18
11 PRUEBAS DE DIAMANTINAS 9 days Fri 09/03/18 Sat 17/03/18
12 MONTAJE 14 days Fri 30/03/18 Thu 12/04/18
13 RETOQUES DE PINTURA 8 days Thu 12/04/18 Thu 19/04/18
14 INSTALACION DE COBERTURA 12 days Tue 10/04/18 Sat 21/04/18
15 TOMA DE MEDIDAS DE LONA 6 days Tue 10/04/18 Sun 15/04/18
16 PLANTILLAJE DE LONA 6 days Tue 10/04/18 Sun 15/04/18
17 FABRICACION DE LONA 7 days Tue 10/04/18 Mon 16/04/18
18 DEMORA POR MURO DE EJE 9 4 days Mon 16/04/18 Thu 19/04/18
19 INSTALACION DE LONA 12 days Tue 10/04/18 Sat 21/04/18
20 FASE 1 7 days? Tue 10/04/18 Mon 16/04/18
21 FASE 2 3 days? Thu 19/04/18 Sat 21/04/18
22 AJUSTES 5 days Fri 20/04/18 Tue 24/04/18
23 FIN 0 days Tue 24/04/18 Tue 24/04/18 24/04

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: Cronograma y ruta critica
Summary Manual Task Critical
Date: Wed 16/05/18
Project Summary Duration-only Critical Split
External Tasks Manual Summary Rollup Progress
External Milestone Manual Summary

Page 1
02 May '1823 May '1813 Jun '1804 Jul '18 25 Jul '18 15 Aug '1805 Sep '1826 Sep '1817 Oct '1807 Nov '1828 Nov '1819 Dec '1809 Jan '19 30 Jan '19 20 Feb '1913 Mar '1903 Apr '1924 Apr '19
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S

24/04

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: Cronograma y ruta critica
Summary Manual Task Critical
Date: Wed 16/05/18
Project Summary Duration-only Critical Split
External Tasks Manual Summary Rollup Progress
External Milestone Manual Summary

Page 2