“IT MUST WORK”

Issue Date:
November 2006

Downloaded Date: 05/17/2007 05:49:52


The latest update of this document is located in the BP ETP and Projects Library
Foreword

To be prepared by Andy Ingels at the request of Dave Brookes due in November 2006

py
Co
d
l le
ro
nt
co
Un

Foreword

Reliability Implementation Manual 1


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Executive Summary
The BP Subsea Reliability Strategy, presented in The BP Subsea Reliability Strategy, A guide for BP
Leaders [1], aims to improve reliability performance of equipment, increase first year operability, and reduce
early life failures within subsea systems worldwide. This document develops the strategy principles first
introduced in the original publication, in April 2003, of this guide for BP Leaders and identifies how these
can be adopted into BP subsea projects.

GP 78-03, Guidance on Practice for Achieving Reliability in Subsea Projects [2], requires the use of this
manual to identify the required Reliability Tasks necessary to meet the requirements of the strategy. GP 78-
04, Guidance on Practice for Reliability Techniques for Subsea Projects [3], similarly requires the
appendices to this manual to implement the required Reliability Tasks in projects. This manual is included
in the ETP library for use with GP 78-03 and GP 78-04. The use of GP 78-06, Guidance on Practice for
Subsea Prototype Qualification Procedure [4], and GP 78-26, Guidance on Practice for Subsea Reliability
and Maintenance Data Collection [5] is required by GP 78-03, GP 78-04 and this manual.

Ten specific Reliability Tasks have been developed to enable subsea projects to implement the Reliability
Strategy by achieving the following objectives:

py
1. Define reliability and maintainability goals and requirements for the system under development,

Co
and link to the BP CVP and other relevant BP processes
2. Plan Reliability Tasks by CVP stage to meet the reliability and maintainability goals and
requirements
d
3. Design the system to meet the reliability and maintainability goals and requirements (where
le
possible)
4. Provide assurance that the requirements have been met and assurance of the extent to which
l
ro

the goals have been met


5. Capture and feedback reliability data into BP lessons learned databases and those of suppliers as
nt

appropriate.
co

The aim is that GP 78-03 and GP 78-04 together with this manual, GP 78-06 and GP 78-26 will provide a
consistent approach to achieving reliability across all BP subsea projects and will convey a clear and
consistent message of the requirements through the procurement cycle.
Un

The key tasks for reliability achievement are grouped by CVP stage with flowcharts and tables defining how
and when different activities should be completed.

For each CVP stage a Reliability Task table provides guidance on specific activities and associated timing.
However, they do not prescribe exactly how the work will be carried out or by whom. This is deliberate.
Every project is different. Teams should make judgements on how to implement the strategy according to the
resources and skills available. A set of comprehensive appendices support the task tables with more detailed
guidance.

The technical risk categorisation task (R1) assesses the level of technical risk within the subsea project. This
enables the user to determine the importance of each of the Reliability Tasks, identify the reliability effort
required for the project and implement the requirements of GP 78-03, GP 78-04 and this manual accordingly.

Executive Summary

Reliability Implementation Manual 2


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Contents
FOREWORD 1
EXECUTIVE SUMMARY 2
CONTENTS 3
1. INTRODUCTION 4
2. EVOLUTION OF THE RELIABILITY STRATEGY TO DATE 6
3. RELIABILITY ACTIVITY REQUIREMENTS BY CVP STAGE 8
4. HOW TO USE THIS MANUAL - WORKED EXAMPLE 12
5. THE ROLE AND RELATIONSHIP OF QM TO RELIABILITY 17
6. VERIFICATION AND VALIDATION OF RELIABILITY TASKS 18
7. APPRAISE STAGE RELIABILITY TASKS 19
8. SELECT STAGE RELIABILITY TASKS 23

py
9. DEFINE STAGE RELIABILITY TASKS 29
10. EXECUTE STAGE RELIABILITY TASKS 36

Co
11. OPERATE STAGE RELIABILITY TASKS 50
12. GLOSSARY 54
13. LINK TO RELIABILITY STANDARDS 56
d
14. REFERENCES 57
le
15. BP CONTACTS AND CHAMPIONS 58
l
ro
nt

Appendix R1 Technical Risk Categorisation


co

Appendix R2 Defining R&M Requirements


Un

Appendix R3 Reliability Planning

Appendix R4 Reliability Assurance

Appendix R5 Reliability Value Analysis

Appendix R6 Reliability Analysis and Modelling

Appendix R7 Design & Manufacture for Reliability

Appendix R8 Contractor & Supplier Selection & Contracting

Appendix R9 Reliability Data Collection and Lessons Capture

Appendix R10 Reliability Qualification Activities

Contents

Reliability Implementation Manual 3


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
1. Introduction
The purpose of The Reliability Implementation Manual is to offer guidance on how the BP Subsea Reliability Strategy should be
implemented within subsea projects. The majority of subsea projects undertaken by BP involve development or enhancement of
equipment and systems. This Reliability Strategy aims to improve reliability performance of equipment, increase first year
operability, and reduce early life failures within our subsea systems worldwide, and can be summarised by the following graph.

Design
Designout
outall
all Foreseeable
Foreseeableearly
earlylife
lifeand
andthrough
throughlife
lifefailures
failures

Early Life Failures Random Failures Wear out Failures

Remove
Remove Remove
RemoveororMinimize
Minimize Decommission
Decommission
Failure rate

expensive
expensiveearlyearly foreseeable
foreseeablethrough
throughlife
life before
before
life
lifefailures
failures failures
failures wear
wearout
out

py
Co Operating time
d
Historical performance
le
Reliability Strategy Goal
l
ro

This document develops the principles contained in The BP Subsea Reliability Strategy, A guide for BP Leaders [1] (The Strategy
nt

Guide) and identifies how these can be adopted into subsea projects. It provides the necessary supporting guidance required by GP
78-03, Guidance on Practice for Achieving Reliability in Subsea Projects [2], and GP 78-04, Guidance on Practice for Reliability
Techniques for Subsea Projects [3], to implement the BP Subsea Reliability Strategy within BP subsea projects.
co

New technology development projects and field development projects using novel equipment / new technologies will inevitably
Un

involve a significant level of design and qualification testing and this manual interfaces with the qualification requirements of GP 78-
06, Guidance on Practice for Subsea Prototype Qualification Procedure [4]. The practices in this manual, though designed for field
development projects, may therefore also provide useful guidance to achieve improvement in technology reliability for new
technology developments projects.

This manual is relevant for all subsea system equipment likely to be included in the subsea procurement specification. The following
diagram describes a typical subsea system.

Design analysis techniques for different types of equipment will mean that the interpretation and application of the guidelines
outlined in this manual may be slightly different for different types of subsea equipment. It is also important to note that the
approach that has been developed is not limited in application to subsea, and has the potential to be applied across projects in all
disciplines.

Importantly for the reliability of subsea projects to continue to meet BP requirements and continue to improve with time, collection
of performance data is essential. GP 78-26 [5] defines the requirements for data collection as recommended by this manual.

In addition to this manual’s alignment to CVP, it is also closely linked to and supports the objectives of other BP processes such as
Front End Loading (FEL) and Value Improvement Processes (VIP), referenced amongst others, in the Major Projects common
process (MPcp).

Introduction

Reliability Implementation Manual 4


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
PRODUCTION FACILITY SUPPORT VESSEL DRILL RIG

Master Hydraulic Intervention Surface tree Workover control


Control Power Unit Surface Support (upper safety system
Station • Controls block)
• Umbilical • HPU
Chemicals • Master contr. unit
Power/ • Lift Surface tree
Comms • Heave comp. adaptor joint • Umbilical reels
Unit
Choke/sep • ROV • Surface tree shut
metering down panels
Riser tension • ESD panels
Pipelines or umbilical joint • Local control point
hangoff/term.

SEA LEVEL

py
Risers Umbilical Tool carrier(s) W.O. riser joints

Misc. tools for sea


line pull Co Stress joint
d
Emerg. D’.connect Pk
in/connections, Tools for
le
running of contr. R running of
O Lower riser pack tubing
module, pig launcher,
l

protection structure, V hanger, tree


ro

etc. Tree protection struc. cap, etc.


nt

Tree cap

Control
co

module Tree
Un

Choke
Tubing hanger

Manifold / Downhole
sensors/valves
Import distribution module Prod.
riser base or Guide
tie-in spool base Packer
Reservoir
Foundation structure
Export (could be common
riser base or for trees and
tie-in spool manifold)

Diagrammatic Representation of a Typical Subsea System

Introduction

Reliability Implementation Manual 5


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
2. Evolution of the Reliability Strategy to Date
The BP Subsea Reliability Strategy, first introduced in 2003, is based on closely interlinked processes identified as key to achieving
competence in reliability management. The identified processes fall into three main categories that have the underlying themes of
Identification, Implementation and Investment. These processes, described in The Strategy Guide [1], are key practices that
companies should have in place as part of their everyday business management and without these processes in place, companies will
be unable to demonstrate their ability to achieve the level of reliability expected of their products by BP.

Emanating from these processes are the 10 specific Reliability Tasks (R1 to R10), initially defined in the original version of this
manual, which was published in February 2005 as The Reliability Handbook, to be implemented within a project to achieve the
required level of reliability.

In 2006, implementation of these tasks became a mandatory requirement for BP subsea projects through the issue of GP 78-03 [2]
and GP 78-04 [3]. At the same time this manual was renamed, produced electronically and updated both to align with these two GPs
and to provide supporting essential guidance for projects. In addition, The Strategy Guide [1], has been updated to make readers
aware of the GPs, to show the linkage between the 10 Reliability Tasks and the key processes, and to align the definition of the key
processes with those described in API RP 17N “Recommended Practice Subsea Production System Reliability & Technical Risk

py
Management” [6] which has been drafted since The Strategy Guide [1] was first published. The hierarchy of these BP documents
and other relevant GPs is shown in the following diagram.

The BP Subsea Reliability Strategy


Co GP 78-06
d
A Guide for BP Leaders
Qualification of
le
Technology for
Subsea Projects
l
ro

GP 78-03
nt

Achieving GP 78-26
Reliability in Subsea Reliability
co

Subsea Projects & Maintenance


Data Collection
Un

GP 78-04 GP 78-05
Reliability Testing of Subsea
Techniques for Equipment: FAT,
Reliability Subsea Projects EFAT and SIT
Implementation
Manual
GP 78-30
Reliability Integrated Subsea
Implementation System Testing/
Manual Commissioning/
Appendices Start-up

Evolution of Reliability Strategy

Reliability Implementation Manual 6


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
The Strategy Guide is intended for BP leaders although it is expected that all BP engineers will read this manual. GP 78-03 is aimed
at more senior members of the BU and project team whilst the other documents are intended for engineers involved in implementing
reliability activities. The typical readership within BP of the documents is shown below. Contractors and suppliers will, at different
levels in their organisation, also need to follow a similar level of readership in order to tender and undertake their contractual
requirements

Strategy GP 78-03 Reliability GP 78-04 Reliability


Guide Implementation Implementation
Manual Manual
Appendices
Senior
Management 9 9
Gatekeeper,
EA, TA
9 9 9
Project
Manager 9 9 9 9
Reliability
Lead 9 9 9 9 9
9 9 9 9 9

py
Project
Engineers

9 Document that should be read to understand what is required by BP

Co
9 Document that is best read to gain further understanding and detail
d
l le
ro
nt
co
Un

Evolution of Reliability Strategy

Reliability Implementation Manual 7


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
3. Reliability Activity Requirements by CVP Stage
This manual ties in directly to the BP Capital Value Process (CVP) and provides guidelines on how to improve reliability throughout
the life of a subsea system. This encompasses engineering, procurement, installation, commissioning and operation. As such this
document is intended to help project engineers focus on reliability goals and requirements, forecast and allocate resources and set
direction for reliability activities.

The BP Capital Value Process is used both for project assurance and to successfully steer and manage a project from field appraisal
through the FEED and detailed design stages and into operation. Each CVP stage is divided by a ‘Gate’, which requires the
submission of a ‘Decision Support Package’ (DSP) for approval by the project ‘Gatekeepers’ before moving to the next stage of the
project.

Develop the
Choose the Right Project Project Right Deliver the Project Right

*APPRAISE *SELECT *DEFINE *EXECUTE *OPERATE


Gate Gate Gate Gate Gate
DSP DSP DSP DSP DSP

py
Co
The output from the reliability activities form part of the reliability assurance documentation, collated as the RAD, which shall be
available to support the DSP at each CVP stage gate.
d
Roles and Responsibilities
le
The Reliability Strategy has implications for contractors (engineering services) and suppliers (hardware) working for BP.
l
ro

The main reliability responsibility of contractors and suppliers is to develop processes to deliver systems that meet BP requirements.
They shall be able to carry out reliability and availability modelling, manage reliability data, modify design and test for reliability and
nt

to be able to provide reliability assurance to projects.


co

It is the responsibility of the BP project team integrated with its selected engineering contractors to determine reliability goals and
requirements and make decisions that encompass reliability assessment. The managing team shall carry out reliability value analysis,
investigate high level system reliability, plan and budget for reliability, give direction to the contractors and suppliers, carry out
Un

review activities including validation and verification of Reliability Tasks, and assess and manage technical risks.

All subsea project managers, shall be responsible for communicating the reliability expectations to their teams and suppliers, and
shall be accountable for delivery of reliability performance.

A Reliability Lead, reporting to the project manager, shall be appointed for each subsea project and shall be
• Accountable for ensuring that the R&M requirements are achieved and championing the Reliability Strategy;
• Responsible for maintaining the overall project Reliability Plan, schedule and assurance documentation;
• Employing specialist reliability resources as required;
• Prioritising the application of reliability techniques to obtain maximum benefit;
• Overall leadership of BP contractors, suppliers and sub-suppliers to achieve effective reliability
implementation and alignment with goals and requirements.

Package managers shall be accountable for delivery of subsea equipment to address the R&M goals and meet the R&M requirements
for the package and responsible for maintaining the package Reliability Plan, schedule and assurance documentation.

Reliability Tasks
This manual contains guidance on how and when Reliability Tasks shall be carried out to generate the maximum benefit to the
project. The Reliability Tasks are designed to influence the way reliability is managed during design and manufacture in the subsea

Activities by CVP

Reliability Implementation Manual 8


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
industry. They shall influence the way systems are selected, with increased emphasis placed on a supplier’s reliability management
capability. This approach demands greater assurance from suppliers that the required level of reliability will be achieved.

Projects shall plan for their reliability activities from the outset and high-level R&M goals and requirements, described in the RAD,
should be included within the Basis of Design (BOD) to demonstrate satisfying the Statement of Requirements (SOR). Each project
shall have documented systems in place to meet the expectations, including justification, where necessary, why certain tasks are not
applicable to that project.

The Reliability Task tables that follow in Sections 7 to 11, for each CVP stage, aim to provide guidance on specific activities and
associated timing. However, they do not prescribe exactly how the work will be carried out or by whom. This is deliberate. Every
project is different. Teams should make judgements on how to implement the initiative according to the resources and skills
available. In some cases (such as for long lead items), it may be necessary to accelerate the reliability process to keep up with the
design process i.e. do certain CVP stage Reliability Tasks before the official start of that CVP stage.

The following table lists the Reliability Tasks (R1 to R10) and is a synopsis of the Reliability Tasks required per CVP stage. Blank
entries in the table indicate that a specific Reliability Task is not required in the respective CVP stage. The labels A, S, D, etc are
given to distinguish between the different CVP stages as explained in Section 4 following. i.e. A = Appraise, S= Select, etc.

py
Reliability Task Name / Reliability Appraise Select Define Execute Execute Operate
Implementation Manual Appendix ref #. Engineering & Construction

Co
Procurement & Handover

R1 Technical Risk Categorisation A1 S1 D1 E1 C1

R2 Defining R&M Goals and Requirements A2 S2 D2 E2 C2


d
R3 Reliability Planning A3 S3 D3 E3 C3 O3
le

R4 Reliability Assurance A4 S4 D4 E4 C4 O4
l
ro

R5 Reliability Value Analysis S5 D5 O5


nt

R6 Reliability Analysis & Modelling S6 D6 E6 O6

R7 Design and Manufacture for Reliability D7 E7


co

Contractor and Supplier Selection and


R8 A8 S8 D8
Contracting
Un

Reliability Data Collection and Lessons


R9 C9 O9
Capture
R10 Reliability Qualification Activities A10 S10 D10 E10 C10 O10

Core Reliability Task required for all subsea projects


Reliability Task required for all subsea projects but detail and resources will vary significantly with technical risk
Reliability Task required for projects intending to use technology that requires significant qualification
Reliability Task required for replacement of installed hardware

Activities by CVP

Reliability Implementation Manual 9


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Input Tasks
Six Input Tasks, listed in the table below, have been defined to ensure that the necessary data is made available, by the project team
and to the project, to undertake the Reliability Tasks listed the table above. The table below also lists the Input Tasks in terms of
when they are required by CVP stage (using the same CVP coding as for the Reliability Tasks i.e. A = Appraise, etc).

Input Tasks Synopsis Requirement by


Required for CVP stage
Reliability Tasks
A S D E C O

The MPcp requires the capture and review of lessons learned at every CVP stage. The
lessons learned usually cover the whole life of the project from strategic thinking and
Lessons
decision making, through project execution and the delivery of benefits. The TAs, supported
I.1 Learned
by the project team shall be responsible for ensuring that past lessons impacting on reliability 9 99 9 9 9
Review
performance are considered at every CVP stage. Clear actions shall to be identified to ensure
the lessons are implemented on the project. These shall then input to the reliability activities.
An assessment of project risks is required by the BP Risk Management Guidelines for Major
Projects at each CVP stage. These activities should explicitly address risks that impact
product reliability with clear actions to ensure the risks are mitigated through the project and
Project Risk
I.2
Review
are addressed in the Project Risk Response plans. These shall then input to the reliability 9 99 9 9

py
activities. Reliability effort will not bring value to a project unless it is carried out to the
appropriate level. A project, which adopts reliability, and then is forced to cut resources will
likewise not realise the benefits of the effort.

Co
Integrity Management is a mandatory process in BP. The Project Quality Management
System (QMS) aims to ensure that the specified levels of integrity, quality and reliability
required to meet BP business goals are attained, demonstrated and delivered in operation.
Quality Strong Quality Management implementation is therefore fundamental to meet and achieve
I.3 9 99 9 9 9
d
Management reliability requirements. The R&M goals and requirements and Reliability Plan shall reflect
the requirements of QM, both in design and manufacture, and Reliability Tasks identified to
le
address quality improvement requirements. Also, data derived from QM activities, needed
as evidence of qualification and/or reliability assurance, shall be sought.
l

There is a strong interface between safety management and reliability management. Both
ro

disciplines consider the avoidance of failure and their consequences. The objective of
reliability management is to avoid failures that may generate any adverse consequence
nt

including loss of functionality, production downtime, a need for intervention or safety


Safety incidents. The consequences of functional failure (loss of operability) of a safety critical
I.4
Management system are higher than for non-safety equipment. It is essential therefore that the higher risks 99 9 9 9
co

are accounted for in the reliability analysis to determine any required reliability
improvements for the equipment. If a Safety Critical Element requires a very high level of
reliability then this shall be reflected in the technical risk categorisation and associated
Un

Reliability Tasks at each CVP stage.


RM data from historical projects and other operating facilities is required to support the
assessment of reliability, availability & production efficiency. i.e. data feed into reliability
analysis. Historical RM data should be used to identify the achieved reliability in similar
conditions and failure modes that have been experienced and to help determine the R&M
goals and requirements for the project. The BP reliability databases, held by operators,
Reliability
I.5
Data
should be interrogated and collected at appropriate times in the design to provide inputs to 99 9 9 9
reliability analysis and assurance. For each system, subsystem and component, as
appropriate, the expected service conditions shall be considered in order that historical data
available is shown to be relevant. This input task relies on earlier projects collecting RM data
as required by GP 78-26, “Guidance on Practice for Subsea Reliability and Maintenance
Data Collection”.
The BP MPcp requires a Technology Plan to be identified and updated through the project at
each CVP stage. The increased risks associated with use of new technology or existing
technology in a new environment should be recognised by the project team early on and
actions taken to identify acceptable reliability performance requirements together with the
Qualification
I.6
Status
means for demonstrating that acceptable reliability performance may be expected in service. 9 99 9 9 9
The high cost of discovering unqualified hardware at subsystem, component or constituent
part level late in a project means that this is an essential task. This input task identifies the
Technology Readiness Level of equipment and is based on GP 78-06, “Guidance on Practice
for Qualification of Technology for Subsea projects”

Activities by CVP

Reliability Implementation Manual 10


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Reliability Activity Definition Levels
As the project moves through its lifecycle, more is known about the detail of the design and hence the plan to manage the reliability
of the design. To reflect this, the scope for reliability activity is considered at a definition level appropriate to the CVP project stages,
namely:

CVP Stage Activity Level Definition


Involves the impact of subsea infrastructure on the total project
A Appraise Stage Project level
performance
Involves the entire subsea system as a combination of Well System,
S Select Stage System level
Control System, Manifold System, Connection System, etc.
Involves individual subsystems, e.g. Well System (as a combination of
D Define Stage Package level Wellhead, Tree, Tubing Hanger), Production Controls (as a combination
of SCM, HPU. MCS, etc.)
Execute Stage
Involves individual components within each sub-system such as: Gate
E Engineering and Component level
Valve, Tree Cap, Connector, SCM, Sensor, etc., manufacturing processes
Procurement Phase
Execute Stage
Installation and Involves equipment, tasks, procedures and interfaces particularly in
C Construction and
operation level relation to installation hardware.

py
Handover Phase

Co
d
l le
ro
nt
co
Un

Activities by CVP

Reliability Implementation Manual 11


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
4. How to Use this Manual - Worked Example
In order to implement the Reliability Strategy, Sections 7 to 11 of this manual provide the information needed by the Project
Reliability Lead and package managers to build the required Reliability Plan for the project. The sections are structured in terms of
specific reliability engineering and technical risk management tasks, grouped by CVP stage. A Reliability Plan template in the form
of a spreadsheet is provided via this link: T3 Define Reliability Plan Template. The structure of the Reliability Plan is detailed in
Appendix R3. The Appendices to this manual provide the necessary detailed guidance and provide links to templates for engineers
performing the tasks.

For each CVP stage, a summary flowchart shows the relevant Option Technical Risk Upgrade Option R&M
Reliability Tasks which are colour coded blue. The flow Categorisation Goals and Requirements
S1 S2
chart boxes are labelled A for Appraise, S for Select, D for
Define, etc. and numbered according to the Reliability Task
numbering and associated appendices to this manual. Update Reliability Plan Update Qualification
for Select and Define Plan for Options
S3 S10
A– Appraise
S– Select
D– Define High Level Option RAM Option Reliability Value

py
E– Execute engineering and procurement phase Modelling Analysis
S6 S5
C– Execute construction and handover phase
O– Operate.

Co
Contractor Reliability
Capability and Scope for Define
The flowchart for Select, taken from Page 23, is shown for S8
d
example.
le
Reliability Assurance to assist
There are some Reliability Tasks that need to be performed in Option Selection
l

S4
parallel (i.e. S1-S2, S3-S10, etc.).
ro

Define Gate
nt
co

Additional tasks normally undertaken to satisfy CVP, or other


BP processes, are also required as inputs to the Reliability
Un

Tasks and have the code, I. They are:

• Lessons Learned (I.1),


• Project Risk Management (I.2), Input Tasks Required by
• Quality Management (I.3),
• Safety Management (I.4),
I.1 Lessons Learned S1, S2, S8
• Reliability Data Management (I.5) I.2 Project Risk Review S1, S2
• Qualification Status (I.6) I.3 Quality Management S3, S4, S8, S10

These are colour coded red and are shown alongside the CVP I.4 Safety Management S1
flowchart in a table which indicates which Reliability Tasks I.5 Reliability Data S2, S6
they input to. The Select input tasks, taken from Page 23, are
I.6 Qualification Status S1, S10
shown here.

The flowcharts and referenced task input provide information


concerning the order in which the tasks should be performed.

For each CVP stage, the first Reliability Task is Technical Risk Categorisation (see Appendix R1). The output of this task is
a technical risk category (A, B, C or D) for the project, an option, a package or component.

How to use this handbook

Reliability Implementation Manual 12


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
For each CVP stage, the flow charts are followed by a set of CVP Reliability Task tables to be used to build the Reliability Plan.
These look up tables provide details of the requirements for each Reliability Task shown in the flowchart and describe:

• the Task Goal


• the Task Description
• the Task Input
• the Task Output
• the Task Resources

The task description tables also contain columns for each of the four technical risk categories (A, B, C & D) which show (i) the
importance of the task, (ii) the need for the task and the type of reliability activity (quantitative/qualitative) and (iii) the predicted
effort required for that task appropriate to each technical risk category. Colour coding schemes are used in the tables to relate the
category of the project/package/component to the recommended level of reliability activity.

The Select stage Reliability Task S3, taken from page 26, is shown as a worked example:

Technical
CVP Task Descriptions Risk
Category

py
A B C D

S3 Update Reliability Plan for Select and Define

Co
Task Goal Define at a more detailed level, the type of activity required to demonstrate
reliability in the project.
Description
d
Input
l le
ro

Output
nt

Resources
co

The Importance of the task is shown in the Goal section and is scored in terms of: H High M Medium L Low.

The importance designation given for each technical risk category has been predetermined and shall be followed as described.
Un

Technical
CVP Task Descriptions Risk
Category
A B C D

S3 Update Reliability Plan for Select and Define


Task Goal Define at a more detailed level, the type of activity required to demonstrate
reliability in the project.
H H M L Importance

Description

Input

Output
Resources

Hence, it can be seen, for example, that Task S3 is of medium importance for a technical risk category C project option.

How to use this handbook

Reliability Implementation Manual 13


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
The task description is broken into a number of action steps and references the relevant appendix, in this case R3, and a hyperlink to
the appendix. By linking to Appendix R3 additional detail necessary to compile a reliability plan is provided to assist.

Technical
CVP Task Descriptions Risk Ref
Category
A B C D

S3 Update Reliability Plan for Select and Define


Task Goal Define at a more detailed level, the type of activity required to demonstrate
reliability in the project.
H H M L Importance

Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project
schedule.
• The resources required to facilitate these activities, including the
definition of the Reliability Team

py
Identify a high level vision for reliability activities in the Execute stage of the
project.
Input

Co
Output
Resources
d
le

The required input for a Reliability Task (earlier Reliability Tasks and Input Tasks) is shown with the associated task reference (S1,
l
ro

S2, I.3, etc). The required output from the task is also shown. i.e. in this case, an updated Reliability Plan.
nt

Technical
CVP Task Descriptions Risk Ref
Category
co

A B C D

S3 Update Reliability Plan for Select and Define


Un

Task Goal Define at a more detailed level, the type of activity required to demonstrate
reliability in the project.
H H M L Importance

Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project
schedule.
• The resources required to facilitate these activities, including the
definition of the Reliability Team
Identify a high level vision for reliability activities in the Execute stage of the
project.
Input Option technical risk categorisation S1
Option R&M goals and requirements S2
Quality Management I.3
Qualification Plan S10
Appraise stage Reliability Plan A3
Output An updated Reliability Plan
Resources

How to use this handbook

Reliability Implementation Manual 14


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Further colour coding shows the level of detail required for each activity within the task for each project/package/component
technical risk category. This shows whether a particular activity needs to be carried out and how. This relates directly to the
indicated effort as quantitative activities inherently require more effort than qualitative activities. The different quantitative and
qualitative approaches and requirements are explained in each of the Appendices.

Technical
CVP Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

S3 Update Reliability Plan for Select and Define


Task Goal Define at a more detailed level, the type of activity required to demonstrate
reliability in the project.
H H M L Importance

Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project

py
schedule.
• The resources required to facilitate these activities, including the
definition of the Reliability Team

Co
Identify a high level vision for reliability activities in the Execute stage of the
project.
Input Option technical risk categorisation S1
Option R&M goals and requirements S2
d
Quality Management I.3
Qualification Plan S10
le
Appraise stage Reliability Plan A3
Output An updated Reliability Plan
l

Resources
ro

Quantitative tasks involve considering characteristics by numerical properties representing amount, size, probability, etc.
nt

Qualitative tasks involve considering characteristics by descriptive, non-numerical or semi-numerical properties.


co

Note: If a project is required to carry out a reliability activity in a quantitative manner, it is also required to carry out any
Un

relevant qualitative aspects of the activity.

How to use this handbook

Reliability Implementation Manual 15


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
The estimated Effort required for each task is shown in the Resources section and is scored in terms of approximate man-hours to
complete the task. It should be noted that every project is different and this resource ranking is intended to give a general indication,
not a prescriptive maximum. The resource / effort ranking is defined as;

VH Very High > 200 man hours


H High < 200 man hours
M Medium < 100 man hours
L Low < 50 man hours
VL Very Low < 10 man hours

So, in the example below, a technical risk category A or B design option is estimated to require up to 50 man hours to construct the
Reliability Plan during Select, whereas a technical risk category C or D design option is estimated to require less than 10 hours.

Technical
CVP Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

S3 Update Reliability Plan for Select and Define


Task Goal Define at a more detailed level, the type of activity required to demonstrate
reliability in the project.
H H M L Importance

py
Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional

Co
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
d
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project
le
schedule.
• The resources required to facilitate these activities, including the
l

definition of the Reliability Team


ro

Identify a high level vision for reliability activities in the Execute stage of the
project.
Input Option technical risk categorisation S1
nt

Option R&M goals and requirements S2


Quality Management I.3
co

Qualification Plan S10


Appraise stage Reliability Plan A3
Output An updated Reliability Plan
Un

Resources The plan should be defined by the project Reliability Lead together with a
L L VL VL Effort
reliability specialist in negotiation with the project manager.

As the project moves through CVP, the project Reliability Lead and package managers shall use the relevant CVP Reliability Task
table as a guide to help build and update the project Reliability Plan. The tables facilitate the use of the technical risk category for an
item (project, option, package, component, process) to determine the need for and the importance of a task, understand what is
required from the task and to estimate the level of resources needed for that task.

How to use this handbook

Reliability Implementation Manual 16


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
5. The Role and Relationship of QM to Reliability
Strong Quality Management (QM) implementation is fundamental to meet and achieve R&M goals and requirements. It is
vitally important, therefore, that BP, contractors and suppliers implement appropriate QM processes and controls in all
subsea projects from concept design through manufacture, assembly and construction, following BP Engineering and Quality
Management Guidelines. These guidelines are entered in the ETP library as a 50 series ETP.

The design of a system or package will define the optimum reliability that shall be achieved for that equipment based on
manufacturing and operational risks. Design decisions can both increase and decrease the inherent reliability of the
equipment and shall take into account the controls required to maintain reliability during manufacture, assembly and
construction.

For example, material specifications may be changed to reduce cost at the design stage; however the associated difficulty of
managing the lower cost material during manufacture may result in lower reliability and extra overall cost.

Manufacturing, assembly and fabrication processes can only maintain or reduce the reliability theoretically inherent in the
design.

Therefore:

• The QM Process shall ensure that reliability goals and requirements are set in the Design phase and are managed

py
throughout manufacturing and installation to ensure reliability meets or exceeds actual expectations in operation;

• The QM effort and resources shall be allocated to ensure that equipment reliability is not compromised by poor

Co
quality assurance and control processes during manufacture, assembly, test, handling, storage and installation.

Integration of Integrity Management, Quality Management and Reliability Management


d
Integrity Management is a mandatory process in BP. The Project Quality Management System (QMS) aims to ensure that the
le
specified levels of integrity, quality and reliability requirements to meet BP business goals are attained, demonstrated and delivered
into operations. Likewise, the implementation of the BP Reliability Strategy is a mandatory process of the subsea function (see GP
l

78-03 and GP 78-04). It is not the intention of this manual to describe the QMS that would normally be required within a subsea
ro

project. The reliability team shall undertake its responsibilities in close collaboration with the QM function, incorporating their
requirements within the project QMS.
nt

In BP subsea projects the QMS shall incorporate R&M goals and requirements and practices. This typically addresses the following:
co

• In forming the Reliability Team, attention to its structure and linkage to the QM function shall be addressed.
• Formation of the Reliability Team within in the project team, including as a minimum a Reliability Lead, to report directly
Un

to the Discipline Project Manager, with a functional link to the EA.


• Integrate the activities defined by the Subsea Reliability Strategy into the QMS.
• Define the Field Availability requirements and incorporate the Reliability Plan into the QMS to identify the reliability
tasks to be implemented in the design, manufacturing, fabrication, transportation, preservation, construction and
installation activities, and any quality verification stage improvement processes to be applied.
• Provide verification and validation activities and data as evidence of qualification and/or reliability assurance, to be
reviewed and approved by the reliability management team.
• Roles, responsibilities and accountabilities of the QM and Reliability Teams and the necessary interfaces.
• Quality Management resources shall be involved in and agree the completion and verification of Reliability Plans and
Reliability Assurance Documents.

Integration of Reliability into Contractor and Supplier QMS

It is important for BP to recognise and for contractors and suppliers to understand that industry standard QMS do not normally
address equipment reliability and that good reliability practices should be integrated within their existing QMS. It is envisaged
therefore that contractors and suppliers shall be assessed on their historical performance and how their approach to reliability is
integrated into their design and manufacturing QM systems. Further details on required reliability capabilities can be found in
Appendix R8 “Contractor and Supplier Selection and Contracting”

Role and Relationship of QM

Reliability Implementation Manual 17


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
6. Verification and Validation of Reliability Tasks
It is essential to ensure that the Reliability Tasks are carried out correctly and effectively and that reliability decisions are
based on appropriate data and assumptions. Throughout the project lifecycle it is necessary to invoke internal processes for
the verification and validation of the reliability activities carried out in the project. Verification and validation of Reliability
Tasks is a very important activity within the BP Reliability Strategy.

BP or a BP appointed third party shall review the Reliability Tasks to verify that the tasks are being performed correctly and that
valid data, models, assumptions, etc are being used. Depending on the task, the reviews should be performed by two or more of the
following:

• A BP engineer from the current project team familiar with the reliability activity
• A BP engineer from outside the project team familiar with the reliability activity
• Peer review team
• Independent external verification and validation authority with expertise and experience in subsea reliability
• A member of the BP Project QM team

py
Greater confidence can be gained from the verification and validation process, when carried out by a reviewer independent to the
original task. Verification and validation should be carried out at a number of levels as described below:

Co
Validation

Validation is the process which substantiates whether a physical entity, a model, data, a test or assumption within their
d
domain of applicability, possesses a satisfactory range of accuracy consistent with the intended application. i.e. “Are we using
le
the right data or model?”, “Is it the correct test?”
Data: Ensure that all data and assumptions are validated against historical data and experience to ensure that decisions are being
l
ro

based on correct assumptions.


Models: Validate all models used to ensure the results predicted correlate with the results seen in reality.
nt

Tests: Validate all planned testing to ensure that the correct test is being performed. For example, a test designed to demonstrate
functionality does not necessarily demonstrate reliability.
co

Verification
Un

Verification is the process which determines the extent to which a procedure, task, physical product or model conforms to its
specification. i.e. “Are we performing the task correctly?”, “Does the valve hold pressure?”

Data: Verify all data, design assumptions and reliability models used for reliability analyses to be obtained from valid sources and
databases.

Processes: Ensure that all required processes and activities, deemed as necessary by the application of this manual, have been
completed appropriately.

Capability: Benchmark the capability of the organisation to perform against the key BP reliability processes. This information
should be shared within BP.

Peer Reviews

As part of the verification and validation process, Peer Reviews organised as normal practice to satisfy CVP should review the
Reliability Plan, the status of the required reliability activities and assure that the reliability risks associated with the project are
properly identified and being correctly mitigated. The Peer Review team should therefore include personnel familiar with reliability
techniques and their application.

Verification & Validation

Reliability Implementation Manual 18


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

7. Appraise Stage Reliability Tasks


Goal Determine project feasibility and alignment with business strategy
Understand project drivers; identify viable opportunities to pursue, with an emphasis on business
Activities
goals and the probability of success.
Define project technical risk category by consideration of major project challenges and technical
Reliability risks together with the need for improved reliability and novel technology.
Input Consider the role of reliability within the project and its decisions, and consider how this should be
managed and developed.

High Level Technical Identify High Level R&M


Risk Categorisation Goals & Requirements
A1 A2

py
Create Reliability Plan for Qualification Plan for

Co
Appraise & Select Technology Stretch
A3 A10
d
le
Contractor Reliability
Capability for Select
l

A8
ro
nt

Initiate Reliability
Assurance (RAD)
co

A4
Un

Select Gate

Input Tasks Required by


I.1 Lessons Learned A1, A2, A8
I.2 Project Risk Review A1, A2
I.3 Quality Management A3, A4, A8, A10
I.6 Qualification Status A1, A10

Appraise

Reliability Implementation Manual 19


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Appraise Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

Ι.1 Project Lessons Learned


Description A Lessons search and a Project Knowledge Management Plan are required by the
BP MPcp at the start of the Appraise stage. The lessons learned at this stage
should cover the whole life of the project from strategic thinking and decision
making, through project execution and the delivery of benefits.

Ι.2 Project Risk Review


Description An assessment of project risks is required by the BP Risk Management
Guidelines for Major Projects at the start of the Appraise stage. By being
rigorous in the risk review in the early stages of a project it is possible to
demonstrate the existence of these risk areas to the Asset management and
develop appropriate risk response plans including contingency allowances to the
estimate and programme. Specific areas where risks to reliability achievement
should be addressed are the application of new or unproven technology or the
application of existing technology in new or extended environments.

Ι.3 Quality Management

py
The R&M goals and requirements and Reliability Plan shall reflect the
requirements of QM, both in design and manufacture, and Reliability Tasks
identified to address quality improvement requirements.

Co
Ι.6 Qualification Status
Description The BP MPcp requires a Technology Plan to be identified at the Appraise stage
with sources of funding identified to ensure appropriate use and viable
development of any necessary innovative technologies. A high level review of
d
technology needed in the project together with its current qualification status
(TRL) is required at the start of the Appraise stage. This activity should address
le
both the field environment and the need for improved reliability through
implementation of new technology.
l

A1 High Level Technical Risk Categorisation


ro

Task Goal Identify the overall level of technical risk involved in the project by deciding into
which technical risk category the project is classed.
H H H H Importance
nt

Description Identify other projects in the region or similar environments with appropriate R1
characteristics, to learn from experiences
• Project environment
co

• Development complexity
• Reservoir conditions
• Greenfield vs. Brownfield
Un

Consider the major project challenges and technical risks.


Identify requirements for reliability improvement.
Using the technical risk categorisation table, select a project risk category.
Later in Appraise, confirm the project technical risk category is in accordance
with the qualification status of the required technology identified in terms of its
TRL.
Input Lessons learned from previous projects Ι.1
Project risks Ι.2
High level R&M goals and requirements A2
Qualification status of technology Ι.6
Output A statement of overall project technical risk category with justification.
Resources The decision-maker should seek the advice of technical experts. VL VL VL VL Effort

Appraise

Reliability Implementation Manual 20


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Appraise Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

A2 Identify High Level Reliability and Maintainability Goals and Requirements


Task Goal Identify high-level R&M goals and requirements for the project as a whole. H M L L Importance
Description Consider the potential impact of identified technical risks on project value. R2
Explore the acceptability of the major technical risks.
Weigh up the balance between maintainability strategy and reliability strategy
and identify strategy focus to be finalised in Select stage.
From the above specify the following R&M goals and requirements:
• Organisational requirements
• Overall production availability requirements/goals
• MFOP goals (if appropriate)
• Reliability goals for new technology
Input Key business objectives
Lessons learned from previous projects Ι.1
Project technical risk categorisation A1
Project risk management Ι.2
Output • A statement of the project R&M goals and requirements should be included

py
in the BOD to demonstrate satisfying the SOR.
• Specification of Project R&M goals and requirements including those for
tender and procurement documents
Resources The evaluation should be carried out by the Appraise team supported by a

Co
VL VL VL VL Effort
reliability specialist.
A3 Create Reliability Plan for Appraise and Select
Task Goal Indicate at a high level, the type of activity required to demonstrate reliability in
H M L L Importance
d
the project.
Description Ascertain from the R&M goals and requirements the general level of effort R3
le
considered beneficial to achieve any reliability improvement required.
Identify Reliability Tasks required as part of the qualification process for high
technical risk category projects.
l
ro

Outline a practical Reliability Plan for the Select stage (based on the CVP
Reliability Task tables), including:
• The reliability activities required.
nt

• When they are required within the Select project schedule.


• The reliability leadership and organisation for Select stage.
• The resources required to facilitate these activities.
co

Identify a high level vision for reliability activities in later stages of the project
Input Project technical risk categorisation A1
Quality Management I.3
Un

High level R&M goals and requirements A2


Qualification requirements A10
Output A preliminary Reliability Plan
Resources The plan should be outlined by the Reliability Lead in negotiation with the
project manager. It should be included with the risk and uncertainty assessments VL VL VL VL Effort
of the high level CVP Plan.
A10 Qualification Plan for Technology Stretch
Task Goal Indicate at a high level, the activity required to demonstrate qualification in the
project.
H M Importance

Description Initiate the qualification process for unqualified technology utilising a


qualification matrix and identify the level of activity required in later CVP stages.
R10
Input Technology qualification status (TRL) Ι.6
Reliability Plan A3
Quality Management I.3
Output A preliminary qualification matrix and Qualification Plan
Resources The qualification plan should be outlined in conjunction with the Reliability Lead
VL VL Effort
and relevant suppliers and specialists.

Appraise

Reliability Implementation Manual 21


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Appraise Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

A8 Contractor Reliability Capability for Select


Task Goal Account for reliability engineering capability in the tendering process. H H M L Importance
Description Investigate engineering contractor commitment to reliability engineering (both R8
long term and short term) that results in an improvement in reliability
performance and consider use of incentives.
Include project R&M goals and requirements and required Reliability Tasks in
tender and procurement documents and prepare contractor reliability capability
evaluation criteria.
When reviewing tenders, evaluate engineering contractor’s capability to design
for reliability together with their ability to perform specific Reliability Tasks.
This shall take into account organisational systems and processes they have in
place to support reliability improvement.
Examine tenders for specific reliability engineering activities. The award of
contracts may consider all or some of the following:
• Change Management Procedures
• Implementation of Lessons Learned Systems
• Reliability Data Management

py
Reliability Analysis and Modelling
• Design for Reliability
• Reliability Assurance

Co
Reliability Value Analysis
Input Lessons learned from previous projects Ι.1
Quality Management I.3
Project technical risk categorisation A1
d
High level R&M goals and requirements A2
Reliability Plan A3
le
Output Assessment of engineering contractor reliability capability and a preliminary
execution schedule including reliability activities, targets and incentives
l

Resources The contractor reliability capability should be evaluated by a reliability specialist


ro

L L VL VL Effort
in conjunction with the project Reliability Lead
A4 Initiate Reliability Assurance
nt

Task Goal Initiate the development of a Reliability Assurance Document (RAD). H M M L Importance
Description Define Reliability Assurance Document format for the project. R4
co

Within the RAD:


• Describe the project technical risk category providing background
information and evidence to support the category selected.

Un

Describe high level R&M goals and requirements of the contender options.
• Record the outline of the preliminary Reliability Plan and Qualification
Plan for each contender option.
• Summarise engineering contractor reliability capability from tenders.
Input Project technical risk categorisation A1
Quality Management I.3
High level R&M goals and requirements A2
Reliability Plan A3
Qualification Plan A10
Contractor reliability capability assessment A8
Output A Reliability Assurance Document (Appraise) to be included with the Decision
Support Package (DSP) presented for the Select Gate.
Resources The RAD should be prepared by the Reliability Lead with support from a
VL VL VL VL Effort
reliability specialist as appropriate.

Appraise

Reliability Implementation Manual 22


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

8. Select Stage Reliability Tasks

Goal Select preferred project option(s)


Select, develop and compare project option(s) and appropriate technologies by focusing on the
Activities
uncertainties, technical risks and other associated economic factors.
Define R&M goals and requirements to achieve business goals. Option evaluation should consider
Reliability
reliability assessment and technical risk categorisation of each option. Consider how technical
Input
risk/uncertainty shall be managed. Apply lessons learned.

Option Technical Risk Upgrade Option R&M


Categorisation Goals and Requirements
S1 S2

Update Reliability Plan Update Qualification


for Select and Define Plan for Options

py
S3 S10

Co
High Level Option RAM Option Reliability Value
Modelling Analysis
S6 S5
d
le
Contractor Reliability
l

Capability and Scope for Define


ro

S8
nt

Reliability Assurance to assist


co

Option Selection
S4
Input Tasks Required by
Un

I.1 Lessons Learned S1, S2, S8


I.2 Project Risk Review S1, S2 Define Gate
I.3 Quality Management S3, S4, S8, S10
I.4 Safety Management S1
I.5 Reliability Data S2, S6
I.6 Qualification Status S1, S10

Select

Reliability Implementation Manual 23


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

Ι.1 Project Lessons Learned


Description An assessment of similar projects and any applicable lessons is required by the
BP MPcp to ensure relevant lessons have been identified and applied to the
project at the start of the Select stage. The BP MPcp also requires that project
lessons from Appraise and Select are captured at the end of the Select stage.

Ι.2 Project Risk Review


Description An assessment of project risks is required by the BP MPcp at the start of the
Select stage before the Project Risk Management Plan can be drafted. It is
essential that the risk to the achievement of reliability is specifically considered in
the project and that the team have the space and vision to remain long sighted in
their aims and objectives.

Ι.3 Quality Management


Description In defining the R&M goals and requirements and building a Reliability Plan, the
requirements of the QM system shall be identified such that the Reliability Tasks,
both in design and manufacture, address any identified quality improvement

py
requirements.

Ι.4 Safety Management


Description If safety critical hardware forms an integral part of an option or the project, this

Co
shall be identified and reflected in the technical risk categorisation and associated
Reliability Tasks. It is important that safety critical hardware achieve a high level
of reliability and availability performance by undergoing reliability analysis for
functionality and operability.
d
Ι.5 Reliability Data
le
Description A review of relevant reliability data is required during the Select stage to provide
approximate figures for the potential reliability that may be achieved by the
different design concepts under consideration. This data inputs to the reliability
l
ro

activities.

Ι.6 Qualification Status


nt

Description The BP MPcp requires the Technology Plan to be updated in Select to ensure
progress on development and implementation of all unproven essential (enabling)
and value enhancing technologies such that risks are acceptable and mitigation
co

plans identified. A high level review of technology needed for each option
together with its current qualification status (TRL) is required at the start of the
Select stage. This activity should address both the field environment and the
Un

need for improved reliability through implementation of new technology and/or


layout.

Select

Reliability Implementation Manual 24


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

S1 Option Technical Risk Categorisation


Task Goal Determine the technical risk category of each development option. H H H H Importance
Description This technical risk categorisation task focuses on development options. It is R1
important to consider the novelty of the options and level of experience with the
technology.
Identify other projects with similar development technologies and consider in
terms of appropriate characteristics and experience including:
• Project environment
• Reservoir conditions
• Development complexity
• Brownfield issues
Consider the major project challenges and technical risks by option including any
requirement for reliability stretch.
Identify requirements for reliability improvement.
Identify requirements for safety critical hardware.
Using the technical risk categorisation table, select a technical risk category for
each option under consideration.
Later in Select, confirm the option category is in accordance with the
qualification status of the technology required for the option identified in terms of

py
its TRL.
Input Lessons learned from previous projects & engineer/supplier liaison Ι.1
Appraise stage project technical risk categorisation A1

Co
Project risks Ι.2
High level option R&M goals and requirements S2
Requirements for safety critical hardware I.4
Qualification status of required technology for each option Ι.6
d
Output A statement of technical risk category, with justification, for each development
option under consideration.
le
Resources The decision-maker should seek the advice of technical experts. VL VL VL VL Effort

S2 Update Option Reliability and Maintainability Goals and Requirements


l
ro

Task Goal Define R&M goals and requirements for specified options. H H M L Importance
Description Review environmental and operability conditions that affect the reliability or R2
maintainability of each system option under investigation
nt

Consider the potential impact of identified option risks on option value.


Explore the acceptability of the major option risks.
co

Identify balance between maintainability strategy and reliability strategy for each
option
Update organisational requirements for each option
Un

Define R&M goals and acceptance criteria for each option:


• Overall production availability requirements/goals for the major
subsea packages
• MFOP goals, if appropriate
• Reliability goals for new technology
Following reliability and value analysis (S5 & S6) and accounting for
CAPEX/OPEX implications, update the R&M goals and requirements
accordingly if appropriate.
Input Key business objectives
Lessons learned from previous projects Ι.1
Reliability data I.5
Option technical risk categorisation S1
Reliability Plan at end of Appraise A3
Project risk management Ι.2
Appraise stage R&M goals and requirements A2
Output • A statement of the option R&M goals and requirements should be included
in the BOD to demonstrate satisfying the SOR.
• Specification of option R&M goals and requirements including those for
tender and procurement documents
Resources The evaluation should be carried out by the Select team supported by a reliability
L L VL VL Effort
specialist.

Select

Reliability Implementation Manual 25


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

S3 Update Reliability Plan for Select and Define


Task Goal Define at a more detailed level, the type of activity required to demonstrate
reliability in the project.
H H M L Importance

Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project
schedule.
• The resources required to facilitate these activities, including the
definition of the Reliability Team
Identify a high level vision for reliability activities in the Execute stage of the
project.
Input Option technical risk categorisation S1
Option R&M goals and requirements S2

py
Quality Management I.3
Qualification Plan S10

Co
Appraise stage Reliability Plan A3
Output An updated Reliability Plan
Resources The plan should be defined by the Reliability Lead with support from a reliability
L L VL VL Effort
specialist where necessary in negotiation with the project manager.
d
S10 Update Qualification Plan for Options
Task Goal Indicate at a high level, the activity required to demonstrate qualification for each
le
option.
H H Importance

Description Update the qualification matrix for unqualified technology and identify the level
l

of activity required in later CVP stages for each option, in particular those items R10
ro

requiring significant qualification to minimise project schedule inputs.


Input Technology qualification status (TRL) Ι.6
nt

Quality Management I.3


Appraise Qualification Plan A10
Option Reliability Plan S3
co

Output Qualification matrix and Qualification Plan for each option


Resources The Qualification Plan should be outlined in conjunction with the Reliability
L L Effort
Lead and relevant suppliers and specialists.
Un

Select

Reliability Implementation Manual 26


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

S6 High Level Option RAM Modelling


Task Goal Assess the probability of system failure modes and their impact on availability
for each option
H M M L Importance

Description Identify system failure modes that will cause production outages through a R6
preliminary FMECA.
Keeping analysis at a package level, assess the probability of system failure
modes.
Feed this information into a high level RAM model
Use the RAM model to assess the acceptability of the system configuration and
the relative importance of the various system elements (packages).
Perform Common Cause Failure Analysis to identify packages vulnerable to
common cause failures. (Quantitatively where data permits).
Interface with value analysis to identify potential for reliability improvement
Input Project/option technical risk categorisation S1
R&M goals and requirements S2
Reliability Value Analysis S5
Reliability Data I.5

py
Output FMECA and CCFA reports and associated mitigation action list.
• Report RAM analysis results as evidence of reliability achievement at this
stage of analysis in the Reliability Assurance Document.
• For technical risk category D, the output from previous project work should

Co
be sufficient.
Resources The RAM analysis should be carried out by the reliability specialist with direct
review/input from the project team. A reliability specialist should support M L L VL Effort
engineers performing FMECA/CCFA activities.
d
S5 Option Reliability Value Analysis
le
Task Goal Determine the commercial value of investing in specific reliability improvement
for the various options under consideration to deliver high level R&M goals and H H M L Importance
requirements.
l
ro

Description Define value acceptance criteria e.g. maximise value R5


Determine the reliability improvement required for each option from the R&M
goals and requirements and by comparison with the RAM analysis results.
nt

Investigate the impact of reliability improvement on the overall value of the


project and /or investigate the impact of value improving options on the overall
reliability of the project.
co

Evaluate the investment/effort trade-off with the reliability/value achieved.


If the investment required is greater than can be economically achieved/justified
the R&M goals and requirements may have to change.
Un

Input Project/option technical risk categorisation S1


R&M goals and requirements S2
RAM analysis model and results S6
Output Summary to include an estimate of the level of investment/effort required to
improve value/achieve reliability targets for each option
Resources The reliability value analysis should be defined by a reliability specialist with
L L VL VL Effort
input from the project manager.

Select

Reliability Implementation Manual 27


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

S8 Contractor Reliability Capability and Scope for Define


Task Goal Account for reliability engineering capability in the tendering process, achieve
long-term improvement in reliability performance
H H M L Importance

Description Investigate contractor commitment to reliability engineering (both long term and R8
short term) that results in an improvement in reliability performance and consider
use of incentives.
Include project R&M goals and requirements and required Reliability Tasks in
tender and procurement documents and prepare contractor reliability capability
evaluation criteria.
When reviewing tenders, evaluate contractor’s capability to design/manufacture
for reliability together with their ability to perform specific Reliability Tasks.
This shall take into account organisational systems and processes they have in
place to support reliability improvement
Examine tenders for specific reliability engineering activities. The award of
contracts may consider all or some of the following:
• Change Management procedures
• Implementation of Lessons Learned Systems
• Reliability Data Management

py
• Reliability Analysis and Modelling
• Design for Reliability
• Reliability Assurance

Co
• Reliability Value Analysis
Input Lessons learned from previous projects Ι.1
Quality Management I.3
Project technical risk categorisation S1
d
R&M goals and requirements S2
le
Reliability Plan S3
Qualification Plan S10
l

High level systems reliability modelling S6


ro

Reliability value analysis S5


Output Assessment of contractor reliability capability and their preliminary schedule
including required reliability activities, targets and incentives for Define.
nt

Resources The contractor reliability capability should be evaluated by a reliability specialist


L L VL VL Effort
in conjunction with the project Reliability Lead
co

S4 Reliability Assurance to Assist Option Selection


Task Goal Update the Reliability Assurance Document (RAD) to provide assurance and
evidence that the best value option has been selected.
H H M L Importance
Un

Description Review RAD format for the project. Within the RAD: R4
• Describe the technical risk category for each option providing background
information and evidence to support the category selected
• Describe option R&M goals and requirements
• Present results of the high level systems reliability modelling of each option
and any value analysis for reliability improvement
• Present the updated version of the Reliability Plan and Qualification Plan
including relevant estimates of effort and resource
• Summarise how QM reliability requirements shall be addressed
• Summarise contractor reliability capability from tenders
Input Project technical risk categorisation S1
Reliability requirements S2
Reliability Plan S3
Qualification Plan S10
Quality Management I.3
High level systems reliability modelling S6
Reliability value analysis S5
Contractor reliability capability assessment S8
Appraise stage RAD A4
Output A Reliability Assurance Document (Select) to be included with the DSP
presented for the Define Gate
Resources The RAD should be prepared by the Reliability Lead with support from a
L L VL VL Effort
reliability specialist as appropriate.

Select

Reliability Implementation Manual 28


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

9. Define Stage Reliability Tasks

Goal Finalise project scope, cost and schedule and obtain project funding
Develop and define the selected option(s) and provide the appropriate level of detailed planning and
Activities design to determine the scope of the project and to develop more detailed cost and schedule
estimates.
Perform technical risk categorisation for packages. Finalise reliability assessment of the project;
Reliability
create a clear reliability strategy to define in detail the reliability activities and resources required
Input
for the project. These requirements shall be defined within project specifications.

Package Technical Risk Allocate Package R&M


Categorisation Goals and Requirements
D1 D2

py
Update System
Architecture to Meet R&M Update Reliability Plan Update Qualification
for Define and Execute Plan for all Packages

Co
Goals & Requirements
D7 D3 D10
d
Package RAM Modelling Package Reliability
le
Value Analysis
D6 D5
l
ro

Contractor / Supplier
nt

Reliability Capability &


Requirements for Execute
co

D8
Input Tasks Required by
I.1 Lessons Learned D1, D2, D8
Un

Update Reliability
I.2 Project Risk Review D1, D2 Assurance
I.3 Quality Management D2, D3, D4, D8, D10 D4
I.4 Safety Management D1
I.5 Reliability Data D2, D6, D8 Execute Gate
I.6 Qualification Status D1, D10

Define

Reliability Implementation Manual 29


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

Ι.1 Project Lessons Learned


Description The BP MPcp requires the Project Knowledge Management Plan to be updated
for the Define stage activities accounting for the relevant networks and systems
for knowledge sharing that have been identified. A regular two-way transfer of
knowledge between the project and the company is essential to ensure lessons are
identified, captured and transferred to the relevant parties as the project
progresses.

Ι.2 Project Risk Review


Description The BP MPcp requires the Project Risk Management Plan to be confirmed at the
start of Define with the assessment of project risks being demonstrated to be at an
acceptable level. The risk register is required to be updated to represent the
current status of risks, opportunities and response plans with quantification on
expected values wherever possible.

Ι.3 Quality Management


Description The R&M goals and requirements and Reliability Plan specified in Define shall

py
reflect the requirements of QM, from design through to manufacture, and
Reliability Tasks identified shall address any necessary quality improvement
needs. Also, data derived from QM activities, required as evidence of
qualification and/or reliability assurance, shall be required.

Co
Ι.4 Safety Management
Description If safety critical hardware forms an integral part of a package or the project, this
shall be identified and reflected in the technical risk categorisation and associated
d
Reliability Tasks. The safety analysis may be used as a starting point for the
reliability analysis but the project shall recognise the different context of the two
le
analyses and ensure that functionality critical failure modes are also identified,
evaluated and managed.
l

Ι.5 Reliability Data


ro

Description For each system, subsystem and component, as appropriate, the expected service
conditions shall be considered in order that historical data available is shown to
nt

be relevant. A review of relevant reliability data is therefore required during the


Define stage to provide approximate figures for the potential reliability that may
be achieved by the designs under consideration. This data then inputs to the
co

reliability activities.

Ι.6 Qualification Status


Un

Description The BP MPcp requires the Technology Plan to be updated in Define to ensure
that progress on development and implementation of all unproven essential
(enabling) and value enhancing technologies are completed by the appropriate
time in Execute. A review of technology needed for each package together with
its current qualification status (TRL) is required at the start of the Define stage.

Define

Reliability Implementation Manual 30


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

D1 Package Technical Risk Categorisation


Task Goal Determine the technical risk category of the major engineering packages H H H H Importance
Description This technical risk categorisation task focuses on the major engineering packages, R1
for example risers or trees. Although full detail will not be known about the
packages, issues such as water depth or reservoir conditions quickly indicate the
higher technical risk technologies.
As the project team increases, engineers responsible for the major packages will
join the team. They shall consider the technical risk category of their particular
package. In particular it is necessary to consider
• Novelty - it is often the minor changes that cause the major problems
• Interfaces between packages, equipment and companies
• Requirements for reliability improvement
• Safety critical hardware
Using the technical risk categorisation table, select a technical risk category for
each package under consideration. Where possible, this should be finalised with
suppliers before Execute.
Later in Defne, confirm the package technical risk category is in accordance with
the package technology qualification status identified in terms of its TRL.
Input Lessons learned from previous projects & engineer/supplier liaison Ι.1

py
Select stage project technical risk categorisation S1
Project and package risks I.2
Package R&M goals and requirements D2

Co
Requirements for safety critical hardware I.4
Qualification status of required technology for each package Ι.6
Output A statement of technical risk category, with justification, for each major
engineering package.
d
Resources The technical risk categorisation should be defined by BP package engineers with
L L L L Effort
the support of the reliability specialist.
le
D2 Allocate Package Reliability and Maintainability Goals and Requirements
Task Goal Update System R&M goals and requirements for the selected Option and allocate
l

H H M L Importance
ro

requirements to equipment packages.


Description Review environmental and operability conditions that affect the reliability or R2
maintainability of each package, also address manufacture, ease of construction,
nt

quality and ease of installation.


Consider the potential impact of identified package risks on system value.
Explore the acceptability of the package technical risks.
co

Identify balance between maintainability strategy and reliability strategy for each
package and ensure the design specifications reflect these strategies.
Specify organisational requirements for each package
Un

Define R&M goals and acceptance criteria for each package:


• Package reliability goals/stretch
• Package maintainability goals
• Package MFOP goals (as appropriate)
Following package reliability and value analysis and architecture improvements
(D5, D6 and D7), update the R&M goals and requirements accordingly.
Input Key business objectives
Lessons learned from previous projects Ι.1
Reliability data I.5
Project/package technical risk categorisation D1
Project risk management Ι.2
QM requirements I.3
Reliability Plan at end of Select S3
Select stage R&M goals and requirements S2
Output • Statement of the package R&M goals and requirements to be included in
RAD.
• Specification of package R&M goals and requirements to be included in
tender and procurement documents
Resources The evaluation should be carried out by the Define team supported by a reliability
L L VL VL Effort
specialist.

Define

Reliability Implementation Manual 31


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

D3 Update Reliability Plan for Define and Execute


Task Goal Define at a more detailed level, the activities required to demonstrate reliability in
the project.
H H M L Importance

Description Review the updated Reliability Plan defined at Select. Make an updated R3
assessment of the level of effort considered necessary to achieve the R&M goals
and requirements, the qualification requirements and QM requirements.
Update and identify a practical Reliability Plan for Define and Execute stages
based on the CVP Reliability Task tables and the technical risk categorisation
results, including which reliability activities are required, when they are required
and what resources are required to facilitate these activities (they should allow for
including installation commissioning and operations expertise, as appropriate).
These activities should include (but not be limited to) the following:
• FMECA (both for reliability and qualification)
• TRAP (Levels 1 & 2)
• FTA/RBD at system and sub-system level (both for reliability and
qualification as appropriate) and RAM Model
• Development of a reliability testing programme (in conjunction with the
qualification testing programme) to demonstrate reliability. Reliability
analysis during the Define stage facilitates the decision regarding what to

py
test and how to test.
The overall project schedule may require early procurement of some long lead
items, in which case relevant reliability activities should be planned for early.
Input Project/package technical risk categorisation D1

Co
Project/package R&M goals and requirements D2
Quality Management I.3
Select stage Reliability Plan S3
Qualification Plan D10
d
Output An updated Reliability Plan
le
Resources The plan should be defined by the project Reliability Lead together with a
M M L VL Effort
reliability specialist in negotiation with the project manager.
l

D10 Identify Qualification Plan for all Packages


ro

Task Goal Specify the activities required to demonstrate qualification for each package. H H M L Importance
Description Update the qualification matrix for all equipment and identify the qualification
nt

testing and associated acceptance criteria required in Define and Execute for each R10
package.
Input Technology qualification status (TRL) Ι.6
co

Quality Management I.3


Select Qualification Plan S10
Package Reliability Plan D3
Un

Output Qualification matrix and Qualification Plan for each package


Resources The Qualification Plan should be outlined in conjunction with the Reliability
L L VL VL Effort
Lead and relevant suppliers and specialists.

Define

Reliability Implementation Manual 32


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

D6 Package RAM Modelling


Task Goal Assess the probability of package failure modes & their impact on system
availability
H M L L Importance

Description Identify package failure modes that will cause production outages through a R6
FMECA.
Considering the failure logic within each package, using RBDs or FTA assess the
probability of package failure modes.
Refine the Select RAM analysis model in more detail for each package
Assess the importance of the various components to the package failure modes
Perform Common Cause Failure Analysis to identify package components
vulnerable to common cause failures.
Interface with value analysis to optimise reliability improvement and/or support
decision making on the cost effectiveness and reliability impact of design
improvements
Input Project technical risk categorisation D1
R&M goals and requirements D2
Reliability value analysis D5

py
High level Select stage system reliability analysis S6
Reliability data I.5
Output • FMECA, RBD, FTA, CCFA reports and associated mitigation action list.

Co
Report RAM analysis results as evidence of reliability achievement at this
stage of analysis in the Reliability Assurance Document.
• For technical risk category D, the output from previous project work should
be sufficient.
Resources The RAM analysis should be carried out by a reliability specialist with direct
d
review/input from the project team. A reliability specialist should support M L L VL Effort
engineers performing FMECA/RBD/FTA/CCFA activities.
le
D5 Package Reliability Value Analysis
l

Task Goal Determine the commercial value of investing in specific reliability improvement
ro

for the package design to deliver the necessary R&M goals and requirements.
H M M L Importance

Description Define value acceptance criteria e.g. maximise value. R5


Determine the reliability improvement required for each package from the R&M
nt

goals and requirements.


Investigate the impact of reliability improvement on the overall value of the
project and/or the impact of value enhancements on the overall reliability of the
co

project.
Evaluate the investment/effort required to achieve the reliability improvement.
If the investment required is greater than can be economically achieved the R&M
Un

goals and requirements may have to change.


Input Project/package technical risk categorisation D1
R&M goals and requirements D2
RAM analysis model and results D6
System reliability value analysis at Select S5
Output Summary to include an estimate of the level of investment/effort required to
improve value/achieve reliability targets for each package
Resources The value analysis should be defined by a reliability specialist with input from
L L VL VL Effort
the project manager.

Define

Reliability Implementation Manual 33


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

D7 Update System Architecture to Meet R&M goals and requirements


Task Goal Review and improve system design to meet overall system R&M goals and
requirements.
H M L L Importance

Description Determine the reliability improvement required for the system as a whole and for R7
each package from the analyses in D5 and D6.
For each reliability improvement required, determine whether the improvement is
best achieved through:
• changing the configuration;
• improving component reliability;
• introducing redundancy.
As part of the Value Improvement Process during design, it is necessary to
consider reliability improvement opportunities. It is also necessary to evaluate
the impact on reliability of other value improving and cost reducing
opportunities.
A critical aspect of design for reliability, as well as identifying the need for
change, is the identification of the impact of change on reliability. Follow up
from a change order should include a re-assessment of technical risk, reliability
and availability.

py
Input Project technical risk categorisation D1
R&M goals and requirements D2
Systems reliability analysis D6

Co
Reliability value analysis D5
Output Summary report describing recommendations for design improvement to
achieve reliability improvement to meet the R&M goals and requirements
Resources The system design should be assessed for reliability improvement and impacts of
M L VL VL Effort
d
change by the Define team supported by a reliability specialist.
D8 Contractor/Supplier Reliability Capability and Requirements for Execute
le
Task Goal Account for reliability engineering capability in the tendering process, achieve
long-term improvement in reliability performance
H H M L Importance
l
ro

Description Investigate contractor/supplier commitment to reliability engineering (both long R8


term and short term) that results in an improvement in reliability performance and
consider use of incentives.
nt

Include project R&M goals and requirements and required Reliability Tasks in
tender and procurement documents and prepare contractor/supplier reliability
capability evaluation criteria.
co

When reviewing tenders, evaluate contractor’s/supplier’s capability to


design/manufacture for reliability together with their ability to perform specific
Reliability Tasks. This takes into account organisational systems and processes
Un

they have in place to support reliability improvement.


Examine tenders for specific reliability engineering activities, the award of
contracts may consider all or some of the following:
• Change Management procedures
• Implementation of Lessons Learned Systems
• Reliability Data Management
• Reliability Analysis and Modelling
• Design/Manufacture for Reliability
• Reliability and Qualification Testing
• Reliability Assurance
• Reliability Value Analysis
Input Lessons learned from previous projects Ι.1
Quality Management I.3
Reliability data I.5
Project/package technical risk categorisation D1
R&M goals and requirements D2
Reliability Plan D3
Qualification Plan D10
Package reliability modelling D6
Reliability value analysis D5
Output Assessment of contractor/supplier reliability capability and a preliminary
execution schedule including reliability activities, targets and incentives
Resources The contractor/supplier reliability capability should be evaluated by a reliability
L L VL VL Effort
specialist in conjunction with the project Reliability Lead.

Define

Reliability Implementation Manual 34


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

D4 Update Reliability Assurance


Task Goal Update the Reliability Assurance Document (RAD) to provide assurance and
evidence that the system and package design is achieving required reliability.
H H M L Importance

Description Review Reliability Assurance Document format for the project. R4


Within the RAD:
• Describe the project technical risk category for each major package
providing background information and evidence to support the category
selected.
• Describe the project/package R&M goals and requirements also included in
the Basis of Design and package specification documents
• Present results of the systems reliability modelling of the selected option
• Present the updated version of the Reliability Plan and Qualification Plan
including relevant estimates of effort and resource.
• Summarise how QM reliability requirements will be addressed
• Describe any changes made to system design/architecture that impact
reliability
• Present summary of contractor/supplier reliability capability from tenders
Input Project technical risk categorisation D1
R&M goals and requirements D2

py
Reliability Plan D3
Qualification Plan D10
Quality Management I.3

Co
Systems reliability analysis D6
Reliability value analysis D5
Updated system/package design D7
Contractor/supplier reliability capability assessment D8
d
Select stage RAD S4
le
Output A Reliability Assurance Document (Define) to be included along with the
Decision Support Package (DSP) presented for the Execute Gate.
l

Resources The RAD should be prepared by the Reliability Lead and package engineers with
L L VL VL Effort
ro

support from a reliability specialist as appropriate.


nt
co
Un

Define

Reliability Implementation Manual 35


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

10. Execute Stage Reliability Tasks

Execute Engineering and Procurement Phase

Goal Finalise detailed design and procure equipment with approved cost and schedule.
Manage detailed engineering and procurement to ensure that the project achieves its cost, schedule
Activities
and operability goals.
The Reliability Plan shall be fully implemented through detailed design and procurement to ensure
Reliability
that all necessary reliability activities are carried out and that all equipment and systems are
Input
designed, procured and verified against R&M requirements.

Component Technical Risk Update Package R&M

py
Categorisation Goals and Requirements
E1 E2

Design and Procure to


meet R&M Goals and Co
Update Reliability Plan for Update Qualification Plan
d
Execute for all Packages
Requirements
E3 E10
le
E7
l

Detailed Reliability
ro

Analysis
E6
nt
co

Manufacture Packages to
meet R&M Goals and
Requirements
Un

E7

Reliability & Qualification


Testing
E10

Update Reliability
Input Tasks Required by Assurance
E4
I.1 Lessons Learned E1, E2, E6, E7, E10
I.2 Project Risk Review E1, E2 Construction Gate
I.3 Quality Management E2, E3, E4, E7, E10
I.4 Safety Management E1
I.5 Reliability Data E2, E6, E10
I.6 Qualification Status E1, E10

Execute

Reliability Implementation Manual 36


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

Ι.1 Project Lessons Learned


Description The BP MPcp requires the Project Knowledge Management Plan to be updated
for the Execute stage activities accounting for the relevant networks and systems
for knowledge sharing that have been identified including peer assists and after
action reviews as appropriate. A regular two-way transfer of knowledge between
the project and the company is essential to ensure lessons are identified, captured
and transferred to the relevant parties as the project progresses.

Ι.2 Project Risk Review


Description The BP MPcp requires the Execute risk targets to be confirmed within the Define
boundaries or variances explained, such that the overall assessment of project
risks can be demonstrated to be at an acceptable level. A formal cross-discipline
process is in place to track performance, manage risks and communicate these
and lessons learned openly across the project.

Ι.3 Quality Management


Description The R&M goals and requirements and Reliability Plan for Execute shall reflect

py
the requirements of QM, from design into manufacture, and Reliability Tasks
shall address quality improvement needs. The QM activities at Execute have the
potential of having the biggest impact on whether the design reliability can be
achieved or not. Also, data derived from QM activities, required as evidence of

Co
qualification and/or reliability assurance, is required.

Ι.4 Safety Management


Description The use of safety critical hardware in a package or the project shall be confirmed
d
at the start of Execute. The necessary high level of reliability and availability
performance shall be assured by undergoing reliability analysis and implemented
le
through design and manufacture for functionality and operability.

Ι.5 Reliability Data


l
ro

Description For each system, subsystem and component, as appropriate, the expected service
conditions shall be considered in order that historical data available is shown to
be relevant. A review of relevant reliability data is required during the Execute
nt

stage to provide approximate figures for the potential reliability that may be
achieved by the selected design.

Ι.6 Qualification Status


co

Description The BP MPcp requires that all technology options as defined in the Technology
Plan are resolved by Execute and the results are supported by an implementation
Un

plan inclusive of technical, financial and schedule risk mitigation plans. A review
of the current qualification status (TRL) of each component of each package is
required at the start of the Execute stage. This activity should address any
changes such as operating environment, technology, architecture, manufacturing
process, materials, etc. since previous projects.

Execute

Reliability Implementation Manual 37


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

E1 Component Technical Risk Categorisation


Task Goal Determine technical risk category of the engineering package major components H H H H Importance
Description This technical risk categorisation task focuses on the major components of the R1
engineering packages, for example valves, materials, seals, sensors, control pods,
etc. The purpose is to quickly indicate the higher technical risk components and
packages.
BP and contractor engineers responsible for the major packages shall consider
and take ownership of the reliability technical risk category of the components of
their particular package. It shall consider
• Novelty - it is often the minor changes that cause the major problems
• Interfaces between packages, equipment and companies including key
installation equipment
• Requirements for reliability improvement
• Safety critical hardware
Using the technical risk categorisation table, select a technical risk category for
each component under consideration.
Confirm the component category is in accordance with its technology
qualification status identified in terms of its TRL.
Input Lessons learned from previous projects Ι.1

py
Define stage project technical risk categorisation D1
Project and package risks I.2
Package R&M goals and requirements E2

Co
Requirements for safety critical hardware I.4
Qualification status of each major component in the system Ι.6
Output A statement of technical risk category, with justification, for each major
component.
d
Resources The technical risk categorisation should be agreed between BP and the contractor
package engineers with the support of the reliability specialist and other relevant M M M M Effort
le
technical experts.
E2 Update Package Reliability and Maintainability Goals and Requirements
l
ro

Task Goal Review/update package R&M goals and requirements in response to supplier’s
R&M activities and design improvements.
H H M L Importance

Description Review and update package R&M goals and requirements once package R2
nt

components are specified in more detail.


Consider the potential impact of identified package design and manufacturing
risks on overall system availability and value.
co

Consider the potential impact of identified construction and installation risks on


overall system availability and value.
Input Key business objectives
Un

Lessons learned from previous projects Ι.1


Reliability data I.5
Package/component technical risk categorisation E1
Project risk management Ι.2
Quality Management I.3
Define stage R&M goals and requirements D2
Reliability Plan at end of Define D3
Output Updated statement of the package R&M goals and requirements to be included in
updated RAD.
Resources The evaluation should be carried out by the Execute team, including suppliers
M L L VL Effort
and installation contractors, supported by a reliability specialist.

Execute

Reliability Implementation Manual 38


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

E3 Update Reliability Plan for Execute


Task Goal Define at a more detailed level, the activities required to demonstrate reliability
during the Execute stage.
H H M L Importance

Description Review the Reliability Plan produced at Define. Make an updated assessment of R3
the level of effort considered necessary to achieve the R&M goals and
requirements, the qualification requirements and QM requirements.
Update the detailed Reliability Plan for the Execute stage including which
reliability activities are required, when they are required and what resources are
required to facilitate these activities. These activities should include (but not be
limited to) the following:
• FMECA (for reliability and qualification)
• TRAP (Levels 1 & 2)
• FTA/RBD at system and sub-system level (for reliability and qualification
as appropriate) and updating of the RAM Model
• Development and implementation of testing programme to demonstrate
reliability
Input Project technical risk categorisation E1
R&M goals and requirements E2
Quality Management I.3

py
Define stage Reliability Plan D3
Qualification Plan E10
Output An updated Reliability Plan.

Co
Resources The plan should be defined by the project Reliability Lead together with a
reliability specialist in negotiation with the project manager and the BP and H M L VL Effort
contractor package engineers.
E10 Update Qualification Plan for all Packages
d
Task Goal Update the activities required to demonstrate qualification for each package. H H M L Importance
le
Description Update the qualification matrix for all equipment and identify the qualification
testing and associated acceptance criteria required during Execute for each R10
package.
l

Ι.6
ro

Input Technology qualification status (TRL)


Quality Management I.3
Define Qualification Plan D10
nt

Package Reliability Plan E3


Output Qualification matrix and Qualification Plan for each package
co

Resources The Qualification Plan should be developed in conjunction with the Reliability
H M L VL Effort
Lead and relevant suppliers and specialists.
Un

Execute

Reliability Implementation Manual 39


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

E6 Detailed Reliability Analysis


Task Goal Identify and assess the probability of package failure modes and define
clear mitigation strategies
H H M L Importance

Description Identify and evaluate package and component failure modes that will cause R6
production outages through a FMECA.
Considering the failure logic within each package, assess the probability of
package failure modes using RBDs or FTA. This should also address interface
and installation failure modes and should recognise the impact or failure through
the system.
Assess the importance of the various components to the failure modes
Perform CCFA to identify items vulnerable to common cause failures.
Define Specific, Measurable, Achievable, Realistic and Time-Bound (SMART)
Mitigation actions.
Investigate the design of the system and packages and identify any further
technical risks to be managed through the TRAP Level 1 process
Towards the end of detailed design, investigate the design of critical packages
and components and identify any further technical risks to be managed through
the TRAP Level 2 process.

py
Update Define stage RAM analysis to represent full equipment scope and system
architecture using verified data relevant to supplied equipment.
Input Project technical risk categorisation E1

Co
Lessons Learned I.1
R&M goals and requirements E2
RAM analysis from Define stage D6
Reliability value analysis from Define stage D5
d
Reliability data I.5
Output Report results of each activity as evidence of required mitigations to ensure
le
reliability achievement. Once actions are closed out they should be reported in
the Reliability Assurance Document. For technical risk category D, the output
l

from previous project work should be sufficient.


ro

Resources RAM analysis should be carried out by a reliability specialist with direct
review/input from the project team. Other reliability analysis should be carried
VH H M L Effort
out by all relevant members of the project team (BP, contractors and suppliers)
nt

with support from a reliability specialist.


co
Un

Execute

Reliability Implementation Manual 40


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

E7 Design and Procure to Meet R&M goals and requirements


Task Goal Design and procure packages which meet the R&M goals and requirements H H M L Importance
Description During Execute it is essential to ensure that the design meets the R&M goals and R7
requirements and that reliability is considered as integral to the design process.
Manufacturing and assembly implications should be considered in design
decisions so that the design’s reliability potential is not compromised by these
processes. Last minute design changes and associated manufacturing errors can
result in early life failures.
Any relevant mitigations identified as required in the reliability analysis
(FMECA, TRAP, etc) should be implemented as required during Execute.
Change Control: BP, contractors and suppliers shall ensure they have robust
change control procedures in place to ensure that any changes to the design are
fully understood and correctly implemented and qualified if they are necessary.
These shall be flagged to the project team and appropriate MoC and Risk Review
processes should be initiated.
Design Quality Control: The contractor/supplier shall possess a design document
control process which meets BP’s quality acceptance criteria.
Review or Initiate Reliability and Qualification Tests: In some cases additional
tests may be initiated where they are deemed necessary. R10
Input Project technical risk categorisation E1

py
R&M goals and requirements E2
Reliability Plan for Execute E3
Qualification Plan for Execute

Co
E10
Detailed reliability analysis E6
Lessons learned from previous projects I.1
Output List of closed out reliability mitigations and corrective actions implemented
during design to be included in the Reliability Assurance Document.
d
Resources The package design should be managed for reliability achievement by the
le
package manager with verification carried out by the Reliability Lead with M M L VL Effort
support from a reliability specialist.
l
ro
nt
co
Un

Execute

Reliability Implementation Manual 41


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

E7 Manufacture Packages to Meet R&M goals and requirements


Task Goal Manufacture packages which meet the R&M goals and requirements H H M L Importance
Description During Execute it is essential to ensure that the design’s reliability potential is not R7
compromised by the manufacturing and assembly process. Manufacturing defects
in components often result in early life failures. It is important therefore to ensure
that no defects occur during manufacture or in subsequent assembly.
Any relevant mitigations identified as required in the reliability analysis
(FMECA, TRAP, etc) should be implemented as required during manufacture.
Change Control: BP, contractors and suppliers companies shall ensure they have
robust change control procedures in place to ensure that any changes in the
manufacturing process are avoided if possible or are fully understood and
correctly implemented and qualified if they are necessary. These shall to be
flagged to the project team and appropriate MoC and Risk Review processes
should be initiated.
Manufacture Quality Control: The supplier shall possess a manufacturing process
which meets BP’s product quality acceptance criteria. Any weak or defective
components shall be identified and removed. Where appropriate (e.g. for volume
production items) sampling tests to be included to detect defect rates.
Review or Initiate Reliability and Qualification Tests: The plan for Reliability
and Qualification tests shall be reviewed and in some cases additional tests may

py
be initiated where they are deemed necessary.
Link to FRACAS (Failure Reporting And Corrective Action System) Information
on the defects and loss of quality shall be recorded in the suppliers FRACAS

Co
system. R10
Input Project technical risk categorisation E1
R&M goals and requirements E2
Reliability Plan for Execute E3
d
Qualification Plan for Execute E10
Detailed reliability analysis E6
le
Lessons learned from previous projects I.1
Quality Management I.3
l
ro

Output List of closed out reliability mitigations and corrective actions implemented
during manufacture and assembly to be included in the Reliability
Assurance Document.
nt

Resources The package manufacture should be managed for reliability achievement by the
package manager with verification carried out by the Reliability Lead with M M L VL Effort
support from a reliability specialist.
co
Un

Execute

Reliability Implementation Manual 42


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

E10 Reliability and Qualification Testing


Task Goal Perform the required equipment tests to improve confidence in the ability of the
equipment to function satisfactorily in service
H H M L Importance

Description Reliability/qualification tests planned and defined during Define & Execute shall R10
be implemented as the manufacturing and assembly proceeds. The majority of
qualification is testing performed in Execute but long lead items may need testing
in Define.
Based on the qualification requirements identified through the use of qualification
matrices during Define and further requirements identified during FMECA /
TRAP processes, perform traditional qualification tests and, where appropriate,
Accelerated Life tests and stress-screening tests.
Investigate failed or defective parts and submit to the Failure Reporting
System. Results of successful tests shall be assessed and submitted as a
contribution to the Reliability Assurance Document.
Use the results from FAT and SIT to further demonstrate appropriate
qualification.
Input Lessons learned from previous projects I.1
Quality Management I.3

py
Reliability data I.5
Project/package technical risk categorisation E1
R&M goals and requirements E2

Co
Reliability Plan for Execute E3
Qualification Plan for Execute E10
Detailed reliability analysis E6
Output Reports of qualification tests carried out and any particular findings from the tests
d
that shall be addressed. These should be referenced in the Reliability Assurance
Document.
le
Resources The qualification programme should be managed for reliability achievement by
the package manager with verification carried out by the Reliability Lead with VH H M VL Effort
l

support from a reliability specialist.


ro

E4 Update Reliability Assurance


Task Goal Update the Reliability Assurance Document (RAD) to provide assurance and
nt

evidence that the system and package design has been designed, manufactured H H M L Importance
and tested to achieve required reliability.
Description Review RAD format for the project. Within the RAD: R4
co

• Describe the technical risk categories for each package and major
component providing background information and evidence to support the
category selected.
Un

• Describe the project/package R&M goals and requirements also included in


the Basis of Design and package specification documents
• Present results of the reliability analyses carried out in Execute and
demonstrate mitigation actions being completed and closed out.
• Present the updated version of the Reliability Plan and Qualification Plan
including necessary reliability and qualification testing
• Summarise how QM reliability requirements have been addressed
• Describe any changes made to system design/architecture that impact
reliability
• Present summary results of the reliability/qualification testing carried out
Input Project/package/component technical risk categorisation E1
R&M goals and requirements E2
Reliability Plan E3
Qualification Plan E10
Quality Management I.3
Reliability analysis results E6
Updated design. Evidence of implementation of manufacturing/assembly E7
mitigation actions
Reliability and qualification testing results E10
Reliability Assurance Document (Define) D4
Output A Reliability Assurance Document (Execute)
Resources The RAD should be compiled by the Reliability Lead and package engineers with
input from suppliers and support from a reliability specialist as appropriate.
H M L VL Effort
Ownership of the RAD should be transferred to the installation team at handover
of equipment from suppliers.

Execute

Reliability Implementation Manual 43


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Execute Construction and Handover Phase

Goal Produce an operating asset consistent with scope, cost, schedule and operability requirements.
Manage construction and handover to ensure that the project achieves its cost, schedule and
Activities
operability goals.
Define, evaluate and implement tests and procedures as required by the Reliability Plan. Prepare the
Reliability Reliability Assurance Document for handover to demonstrate that all reliability activities have been
Input carried out and that all equipment and systems and procedures are verified against R&M
requirements.

Procedure Technical Update R&M and


Risk Categorisation Construction Task
Goals & Requirements
C1 C2

py
Co
Update Reliability Plan Update Qualification
including Testing & Plan
Procedure Validation
C3 C10
d
le

Hardware & Procedure


l
ro

Testing
C10
nt

Complete Reliability
co

Assurance for Start-up


C4
Un

Reliability Data and


Lessons Capture
C9

Input Tasks Required by


Operate Gate
I.1 Lessons Learned C1, C2, C10
I.2 Project Risk Review C1, C2
I.3 Quality Management C2, C3, C4, C10
I.4 Safety Management C1
I.5 Reliability Data C2, C10
I.6 Qualification Status C1, C10

Execute

Reliability Implementation Manual 44


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

Ι.1 Project Lessons Learned


Description The BP MPcp requires the Project Knowledge Management Plan to be updated
for the Execute stage and prepared for the transition to Operate, with the impact
within the project of lessons learned, recorded. Plans for managing information
and transferring it for use in Operations shall be in place. A process of Lessons
Capture is required as part of this before the end of Execute. A continuation of
knowledge sharing processes through Execute such as peer assists and after
action reviews should be maintained as appropriate. .A review of lessons learned
relating to construction and handover activities are part of this.

Ι.2 Project Risk Review


Description The BP MPcp requires the Execute risk targets to be confirmed such that the
overall assessment of project risks can be demonstrated to be at an acceptable
level. An assessment of project risks relating to construction and handover
activities is particularly important during this phase of Execute.

Ι.3 Quality Management

py
Description The QM activities at Execute have the potential of having the biggest impact on
whether the design reliability can be achieved or not. The Reliability Tasks
therefore shall address the QM requirements. This is particularly important

Co
during assembly, construction and in testing. Also, data derived from QM
activities, required as evidence of qualification and/or reliability assurance, shall
be sought.

Ι.4 Safety Management


d
Description The consequences of functional failure (loss of operability) of a safety critical
le
system are higher than for non-safety equipment. It is essential that the higher
risks associated with safety critical equipment are accounted for in the reliability
tasks at this stage of Execute, particularly in terms of assembly and construction
l
ro

for functionality and operability and in terms of specification for reliability and
acceptance testing.

Ι.5 Reliability Data


nt

Description A review of reliability data associated with historical failures arising from
installation and commissioning activities is required during the Execute stage to
co

inform the reliability activities.

Ι.6 Qualification Status


Un

Description The BP MPcp requires that the design intent is rigorously controlled through
procurement and construction, with the application of new technology tested and
operational implications reflected in commissioning and start-up plans. The
current qualification status (TRL) of each component of each package together
with details of any remaining qualification testing is required at hand over from
the manufacturer to the installation team.

Execute

Reliability Implementation Manual 45


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

C1 Procedure Technical Risk Categorisation


Task Goal Determine the technical risk category of the procedures to be used for
construction, installation and testing.
H H H H Importance
Description This technical risk categorisation task focuses on the procedures to be used R1
during construction, installation and testing. The purpose is to quickly indicate
the higher technical risk procedures where there is potential for the procedures to
affect the reliability of equipment to be installed e.g. through increased stresses,
minor surface damage, incorrect connections, etc
The technical risk category of the procedures shall consider
• Novelty in equipment used for installation or in procedures - it is often the
minor changes that cause the major problems
• Interfaces between packages, equipment and companies including installation
equipment.
• Workforce experience
• Safety critical hardware
• Qualification status of packages and equipment
Using the technical risk categorisation table, select a technical risk category for
each procedure under consideration.
Input Lessons learned from previous projects Ι.1

py
Technical risk categorisation of project specific novel installation equipment D1
Project and package risks I.2
Package R&M goals and requirements E2

Co
Requirements for safety critical hardware I.4
Qualification status of each major component in the system I.6
Output A statement of technical risk category, with justification, for each procedure.
Resources The technical risk categorisation should be agreed between BP and the contractor
d
with the support of the reliability specialist and other relevant technical experts VL VL VL VL Effort
including engineers responsible for installation, testing, etc.
le
C2 Update R&M and Construction Task Goals and Requirements
Task Goal Review/update R&M and construction Reliability Task requirements in response
l

H H M L Importance
ro

to qualification, construction and installation activities


Description Review and update R&M goals and requirements as qualification, construction, R2
installation and testing progresses.
nt

Consider the potential impact of identified construction risks on overall system


availability and value.
Assess the potential consequences of failure during a procedure both in relation to
co

hardware damage and delayed start-up


Determine the acceptability of the risks for each procedure.
From the detailed RAM analysis, confirm the maintainability strategy and the
Un

consequential spares and vessel availability necessary to achieve overall project


availability goals/requirements.
Input Key business objectives
Lessons learned from previous projects I.1
Reliability data I.5
Detailed RAM analysis E6
Project technical risk categorisation R1
Project risk management I.2
Quality Management requirements I.3
Reliability Plan at handover of equipment from suppliers E3
Execute stage R & M goals and requirements E2
Output An updated statement of the R&M goals and requirements to be included in
updated RAD
Resources The evaluation should be carried out by the Construction and Handover Execute
M L VL VL Effort
team supported by a reliability specialist.

Execute

Reliability Implementation Manual 46


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

C3 Update Reliability Plan including Testing and Procedure Validation


Task Goal Define at a more detailed level, the activities required to demonstrate reliability
during this phase of the Execute stage.
H H M L Importance

Description Review the Reliability Plan. Make an updated assessment of the level of effort R3
considered necessary to achieve the R&M goals and requirements, the
qualification requirements and QM requirements.
Update the detailed Reliability Plan for this part of the Execute stage including
which reliability activities are be required, when they are be required and what
resources are required to facilitate these activities. These activities should
include (but not be limited to) the following:
• Process FMECA
• Procedure Operation Risk Analysis
• FTA, ETA as required by FMECA and Operation Risk Analysis
• Procedure Testing/Simulation
• Confirmation and implementation of reliability testing programme to
demonstrate reliability
• The definition and responsibilities of the Reliability Team shall reflect the
transferred responsibility following delivery of the equipment to the
construction and installation teams.

py
Input Project technical risk categorisation C1
R&M goals and requirements C2
Quality Management I.3

Co
Execute stage Reliability Plan E3
Qualification Plan C10
Output An updated Reliability Plan
Resources The plan should be defined by the project Reliability Lead together with a
d
reliability specialist in negotiation with the project manager and the BP and L L VL VL Effort
contractor package engineers.
le
C10 Update Qualification Plan
l

Task Goal Update the activities required to demonstrate qualification for each package H H M L Importance
ro

Description Update the qualification matrix for all equipment and identify the remaining
qualification testing and associated acceptance criteria that are required before R10
installation and handover to operations.
nt

Input Technology qualification status (TRL) Ι.6


Quality Management I.3
co

Execute Qualification Plan E10


Reliability Plan C3
Output Qualification matrix and Qualification Plan for each package
Un

Resources The Qualification Plan should be developed in conjunction with the Reliability
L L VL VL Effort
Lead and relevant suppliers and specialists.

Execute

Reliability Implementation Manual 47


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

C10 Hardware and Procedure Testing


Task Goal Ensure that procedures used during assembly, installation and testing does not
impact on reliability of installed hardware.
Perform the required equipment tests to improve confidence in the ability of the
H H M L Importance

equipment to function satisfactorily in service


Description Procedures to be used for assembly, installation, commissioning and start-up R10
should be tested or simulated prior to implementation to ensure that the
procedures do not affect the reliability of the installed hardware. Incorrect
procedures often result in unexpected early life failures of hardware or delays in
start-up.
The reliability and qualification tests planned and defined during Define and
Execute stages shall be implemented as assembly, installation and
commissioning proceed.
Use the results from acceptance testing, SIT, post-installation tests,
commissioning and other testing to further demonstrate appropriate qualification.
Input Lessons learned from previous projects I.1
Quality Management I.3
Reliability data I.5
Procedure technical risk categorisation C1

py
R&M goals and requirements C2
Reliability Plan for Execute C3
Qualification Plan for Execute C10

Co
Detailed reliability analysis E6
Output Reports of tests carried out and any particular findings from the tests that require
addressing. These should be referenced in the Reliability Assurance Document.
Resources The qualification programme should be managed for reliability achievement by
d
the contractor Execute project team with verification carried out by the VH H M VL Effort
Reliability Lead with support from the reliability specialist as appropriate.
le
C4 Complete Reliability Assurance for Start-up
Task Goal Complete the Reliability Assurance Document (RAD) to provide assurance and
l

H H M L
ro

evidence that the system and packages have been built and tested to achieve Importance
required reliability.
Description Review Reliability Assurance Document for the project. R4
nt

Within the RAD:


• Describe the technical risk categories for each procedure providing
background information and evidence to support the category selected.
co

• Update the R&M goals and requirements for construction activities and
testing procedures
• Present results of the procedure testing carried out including demonstration
Un

of mitigation actions being completed and closed out


• Present the updated version of the Reliability Plan and Qualification Plan
including the necessary reliability and qualification testing
• Summarise how QM reliability requirements have been addressed
• Describe any changes made to procedures that impact reliability
• Present summary results of the testing carried out
Input Project and procedure technical risk categorisation C1
R&M goals and requirements C2
Reliability Plan C3
Quality Management I.3
Qualification Plan C10
Procedure, reliability and qualification testing results C10
Execute Design and Manufacture Phase RAD E4
Output • Completed Reliability Assurance Document for Project
• The RAD should be included along with the Decision Support Package
(DSP) presented for the Operate Gate.
Resources The RAD should be compiled by the contractor Execute team / Reliability Lead
H M L VL Effort
with support from a reliability specialist as appropriate.

Execute

Reliability Implementation Manual 48


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

C9 Reliability Data and Lessons Capture


Task Goal To demonstrate performance to regulatory authorities and to provide data for
future analysis and design.
H H M L Importance

Description Record reliability failures and good practices during the project stage up to the
point of package or system handover to operations. R9
All data shall be collected to meet the requirements of GP 78-26.
Key lessons shall also be retrieved and fed back into future projects via BP
Project Lessons Learned processes defined within the BP MPcp Knowledge
Management Process and recorded in the ETP shared learning library.
Corrective actions shall also be recorded and shall be based on a failure analysis
conducted, where appropriate, with the equipment suppliers to understand the
technical and root causes of failure.
Input Information concerning:
• Failures,
• Near misses,
• Good practices
Output Reliability Data
Lessons learned
Resources Data should be collected by the contractor Execute team and fed to BP corporate
H H M VL Effort

py
reliability data management function.

Co
d
l le
ro
nt
co
Un

Execute

Reliability Implementation Manual 49


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

11. Operate Stage Reliability Tasks

Goal Evaluate asset to ensure performance to specifications and maximum return to shareholders.
Support and evaluate the project end result over a one-year initial operating period and through the
Activities
life of the field.
Monitoring of technical performance, compare with assumptions and feedback results and lessons
Reliability learned. Investigate options for reliability improvements when replacing items at scheduled
Input maintenance or through failure. Treat major modifications as new projects and follow reliability
principles and practices.

Operate Reliability
Plan
O3

py
Collection, Analysis &
Validation of Reliability

Co
Data
O9 d
Qualification of Design Reliability Analysis of Reliability Value
le
Improvements Design Improvements Analysis of Design
O10 O6 Improvements
l

O5
ro
nt

Update Reliability Minor Upgrades &


Assurance Modifications
co

O4
Un

Input Tasks Required by


I.1 Lessons Learned O3, O6, O9
I.3 Quality Management O3, O4, O9, O10
I.4 Safety Management O3
I.5 Reliability Data O6, O9
I.6 Qualification Status O10

Operate

Reliability Implementation Manual 50


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Operate Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

Ι.1 Project Lessons Learned


Description The BP MPcp requires the Project Knowledge Management Plan to be finalised
for the transition to Operate, with the impact within the project of lessons learned
recorded. Plans for managing information and transferring it for use in
Operations shall be implemented. A process of Lessons Capture is required as
part of this handover process. A process shall also be set-up to inform future
projects and development work on the longer-term application of novel
technology incorporated within the project as well as a retrospect review of key
lessons.

Ι.3 Quality Management


Description The QM activities at Operate still have the potential of having significant impact
on whether the design reliability can be achieved or not. Also, data derived from
QM activities, required as evidence of qualification and/or reliability assurance,
shall be sought. A review of the Reliability Tasks needed to meet the QM
requirements is required, particularly in relation to operations and data collection.

Ι.4 Safety Management

py
Description It is essential that the higher risks associated with safety critical equipment are
accounted for in the Operate Reliability Tasks to optimise functionality and
operability and to manage any required reliability improvements for the

Co
equipment. A review of the Operate Reliability Tasks needed as part of Safety
Management requirements is therefore required.

Ι.5 Reliability Data


d
Description A review of relevant reliability data is required during the Operate stage to
provide approximate figures for the potential reliability that may be achieved by
le
the installed design. This data shall be used as a comparator with actual achieved
reliability. Data may also be required to assess the benefits of replacing hardware
with improved components.
l
ro

Ι.6 Qualification Status


Description The BP MPcp requires that plans are put in place to monitor and assess the
nt

performance of the plant and component systems through operations against the
Basis of Design. This shall involve feedback with appropriate technology groups
and other projects. In addition, during the Operate stage equipment may need to
co

be replaced, either through scheduled maintenance or because of unexpected


failure. In the interim, alternative equipment may become qualified for
application in the project and its qualification status (TRL) shall be updated and
Un

made available to the project.

Operate

Reliability Implementation Manual 51


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Operate Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

O3 Operate Reliability Plan


Task Goal Plan the R&M activities required during Operate for continued reliability
assurance and feedback H H M L Importance

Description Ascertain from the R&M goals and requirements the general level of effort R3
considered beneficial to achieve the required reliability and production
availability.
Ascertain QM and safety management requirements.
Outline a practical plan for reliability for the Operate stage including:
• The reliability activities required
• When they are required within the Operate project schedule
• The reliability leadership and organisation for Operate stage
• What resources are required to facilitate these activities
Outline procedures for data collection both for feedback to future projects and to
provide evidence for regulatory authorities in line with GP 78-26
Outline procedures for investigating and reporting failures
Outline procedures for replacing equipment with identical or improved
components following failure or at scheduled replacement including the
reliability analysis/assessment that is required to support the decision
Input Project RAD C4

py
Lessons learned from previous projects and operations I.1
Quality Management I.3
Safety management I.4

Co
Output Reliability Plan for Operate
Resources The plan should be outlined by the project Reliability Lead together with a
M L L VL Effort
reliability specialist in negotiation with the project manager.
O9 Collection, Analysis & Validation of Reliability Data
d
Task Goal To validate predicted reliability against experience, to demonstrate performance
H H M L Importance
le
to regulatory authorities and to provide data for future analysis and design.
Description All data shall be collected to meet the requirements of GP 78-26.
Set up systems and procedures to ensure data is collected and collated R9
l
ro

from all relevant activities such as:


• testing (qualification, FAT, SIT)
• commissioning
nt

• operation
• monitoring
• inspection
co

• intervention and repair


This data shall include service conditions, durations, and intervention
requirements specific to project designs.
Un

Particular note should be made of non-conformances and failures which should


be investigated and reported thoroughly.
Data shall be collated according to BP (OREDA) standard guidelines into a
reliability database and analysed to provide validation against predicted
performance.
Key lessons shall also be retrieved and fed back into future projects via BP
Project Lessons Learned processes and recorded in the ETP shared learning
library.
Reliability data and key lessons shall also be fed back to suppliers to inform them
on the performance of their product and hence allow them to understand the need
for reliability improvement
Input Detailed reliability analysis E6
Project lessons learned I.1
Quality Management I.3
Reliability data I.5
Output Submissions to BP/OREDA and lessons learned databases
Resources Data should be collected by operations group and fed to BP corporate reliability
H H M VL Effort
data management function.

Operate

Reliability Implementation Manual 52


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
Appraise Select Define Execute Operate

Technical
Operate Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix

O10 Qualification of Design Improvements


Task Goal To ascertain the options for replacing hardware (either at scheduled replacement
or following failure) with components having improved reliability.
H H M L Importance

Description Check qualification of technology development since start-up to ascertain if


improved technology is available for use.
Input Quality Management I.3
Qualification Status I.6
Output Identification of improved technology available for use
Resources Reliability specialist and Reliability Lead
L L VL VL Effort

O6 Reliability Analysis of Design Improvement


Task Goal To ascertain the options for and the benefits of replacing hardware (either at
scheduled replacement or following failure) with components having improved H H M L Importance
reliability.
Description Confirm if predicted reliability of component has been achieved during life of
project.
R6
Undertake root cause analysis for significant or repeated failures
Perform a technical risk categorisation exercise and risk analysis (e.g. FMECA)
R1

py
for all replacement hardware
Input Project RAM model E6
Lessons learned during this and other projects I.1

Co
Reliability data I.5
Output Risk assessment for hardware replacement
Resources Detailed reliability analysis should be performed by a Reliability Specialist L L VL VL Effort
d
O5 Reliability Value Analysis of Design Improvement
le
Task Goal To ascertain the value of replacing hardware (either at scheduled replacement or
following failure) with components having improved reliability.
H H M L Importance

Description Update previous detailed RAM Analysis and Reliability Value Analysis to
l

determine value and benefits of improved hardware.


R5
ro

Input Project RAM model E6


Project value analysis model E5
nt

Output Value analysis justification for hardware replacement


Resources Project RVA should be performed by a reliability specialist with input from the
L L VL VL Effort
project manager
co

O4 Update Reliability Assurance


Task Goal Update the Reliability Assurance Document (RAD) to provide assurance and
Un

evidence that the system continues to achieve the required reliability and
production availability. Demonstrate that replacement hardware has been
H H M L Importance

designed, manufactured and tested to achieve required reliability.


Description Confirm predicted hardware availability with actual performance R4
Provide evidence that QM R&M goals and requirements continue to be met
Provide details of failures and their causes
Update technical risk category for replacement hardware
Update reliability analysis, qualification and all testing as appropriate
Updated Reliability Plan for Operate
Input Project RAD C4
Reliability Plan for Operate O3
Quality Management I.3
Summary of results from data collection O9
Qualification test results for replacement hardware O10
Updated reliability analysis O6
Reliability value analysis results for replacement hardware O5
Output Updated RAD
Resources Reliability Lead
L L VL VL Effort

Operate

Reliability Implementation Manual 53


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
12. Glossary
This glossary has been formed to provide explanation of acronyms used in the manual and its appendices.

BP Terms

ALERT Holistic Early Uncertainty Assessment


BOD Basis of Design
CVP Capital Value Process
DSP Decision Support Package
EA Engineering Authority
FEL Front End Loading
GO Great Operator
HSSE Health, Safety, Security, and Environment

py
MPcp Major Projects common process
PHSER Project, Health, Safety and Environmental Review

Co
RAD Reliability Assurance Document
RM Reliability and Maintenance
SCE Safety Critical Equipment
d
SMART Specific, Measurable, Achievable, Realistic and Time-Bound
le
SOR Statement of Requirements
l
ro

TA Technical Authority
TRAP Technical Risk Assurance Process
nt

VIP Value Improvement Process


co

Industry Terms
Un

ALT Accelerated Life Testing


CAPEX Capital Expenditure required for all stages of the project (including identified operating spares on
hand over)
CCFA Common Cause Failure Analysis
CMMIS Computerised Maintenance Management & Information Systems
EFAT Extended Factory Acceptance Test
ESS Environmental Stress Screening
ETA Event Tree Analysis
Failure Mode Description of the manner in which failure has occurred or may occur
FAT Factory Acceptance Test
FEED Front End Engineering Design
FMECA Failure Modes and Effects Criticality Analysis
FRACAS Failure Reporting And Corrective Action System
FTA Fault Tree Analysis
HALT Highly Accelerated Life Testing

Glossary

Reliability Implementation Manual 54


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
HASS Highly Accelerated Stress Screening
Hazard Rate The fraction of failures of items in service per unit time
HAZID Hazard identification
HAZOP Hazard and Operability
HIPPS High Integrity Pressure Protection System
HPU Hydraulic Power Unit
IMR Inspection, Maintenance and Repair
ISO International Standards Organisation
JIP Joint Industry Project
LCC Life Cycle Costing
MCS Master Control System
MFFOP Minimum Failure Free Operating Period
MFOP Maintenance Free Operating Period
MoC Management of Change

py
MTBF Mean Time Between Failure
MTTF Mean Time To Failure, (average value of the times to failure)

Co
NPV Net Present Value
OPEX Operating Expenditure over the operational life of a development
OREDA Offshore Reliability Database
d
le
QM Quality Management
QMS Quality Management System
l
ro

R&M Reliability and Maintainability


RAM Reliability, Availability and Maintainability
nt

RBD Reliability Block Diagram


co

RCA Root Cause Analysis


RCMM Reliability Capability Maturity Model
Un

RVA Reliability Value Analysis


SCC Stress Corrosion Cracking
SCM Subsea Control Module
SIT System Integration Test
SST Step Stress Testing
TRL Technology Readiness Level
WELL MASTER Reliability Database of Well-completion Equipment Technical Effectiveness

Glossary

Reliability Implementation Manual 55


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
13. Link to Reliability Standards
There are a number of national and international standards and guidelines that support and direct the implementation of reliability
activities within projects. This manual is not designed to replace these, but to support and link into them. The following table shows
how the 10 Reliability Tasks required by this manual relate to some of these standards. Any work carried out in accordance with
these standards for these tasks should be considered to also satisfy the requirements of this manual. However, working with
contractors and suppliers in the application of this manual in accordance with GP 78-03 and GP 78-04 may introduce variances
between the requirements of the standards and the GPs. In such an instance BP shall determine the practice to be followed with due
regard to local regulatory requirements.

The list of codes and standards given below is offered for high level guidance and may not be all inclusive. It is important to ensure
that more detailed equipment and procedure specific codes and standards are identified and complied with as may be necessary.

OREDA standard ISO 14224 [12]

py
ISO 9000-4/IEC-60300 [14]
Norsok standard Z-016 [7]

ISO/TS 29001:2003 [11]


AS/NZS 4360:1999, [8]

Mapping of Key Tasks to

IEC 61508/61511 [16]


Co
ISO 9001:2000 [10]

International Reliability
DNV-RP-A203 [9]

API RP 17 – N [6]
IEC-60605-3 [15]
OLF GL 70 [13]
Standards

ISO 20815 [17]

ISO 15663 [18]

ISO 13628 [19]


d
l le

Technical Risk
9 9
ro

R1
Categorisation
Defining R&M goals
R2 9 9 9 9 9 9 9 9
nt

and requirements
R3 Reliability Planning 9 9 9 9 9
co

R4 Reliability Assurance 9 9 9 9 9 9 9 9 9
Reliability Value
9 9 9
Un

R5
Analysis
Reliability Analysis and
R6
Modelling 9 9 9 9 9 9
Design and Manufacture
R7
for Reliability 9 9 9 9 9 9 9 9
Contractor and Supplier
R8 Selection and 9 9 9
Contracting
Reliability Data
R9
Collection 9 9 9 9 9 9
Reliability Qualification
R10
Activities 9 9 9 9 9 9 9 9

Link to Standards

Reliability Implementation Manual 56


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
14. References
[1] BP Subsea Reliability Strategy, A guide for BP Leaders’ published in April 2003

[2] BP GP 78-03, Guidance on Practice for Achieving Reliability in Subsea Projects, July 2006

[3] BP GP 78-04, Guidance on Practice for Reliability Techniques for Subsea Projects, July 2006

[4] BP GP 78-06, Guidance on Practice for Subsea Prototype Qualification Procedure, July 2006

[5] BP GP 78-26, Guidance on Practice for Subsea Reliability & Maintenance Data Collection

[6] API RP 17N “Recommended Practice “Subsea Production System Reliability & Technical Risk Management”

[7] Norsok standard Z-016: "Regularity management and reliability technology", Rev. 1, Dec. 1998.

[8] Standards Australia and Standards New Zealand AS/NZS 4360:1999, "Risk Management".

[9] DNV-RP-A203 "Qualification procedures for new technology", September 2001.

py
[10] ISO 9001:2000, “Quality Management Systems”

Co
[11] ISO/TS 29001:2003: Petroleum, petrochemical and natural gas industries -- Sector-specific quality
management systems -- Requirements for product and service supply organizations
d
[12] ISO 14224 Petroleum and gas industries - Collection and exchange of reliability and maintenance data for
equipment.
le

[13] Norwegian Oil Industry Association Guideline OLF GL 70, "Guidelines for the application of IEC 61508 and
l
ro

IEC 61511 in the petroleum activities on the continental shelf", Feb. 2001.
nt

[14] ISO 9000-4/IEC-60300 Dependability Management, 2003.

[15] IEC-60605-3 Equipment reliability testing, 1986.


co

[16] IEC 61508/61511 Functional safety of electrical/electronic/programmable electronic safety related systems,
Un

part 1-7.

[17] ISO/DIS 20815 Petroleum, petrochemical and natural gas industries – Production assurance and reliability
management, 2005

[18] ISO 15663 Petroleum and natural gas industries – Life cycle costing

[19] ISO 13628 Petroleum and natural gas industries – Design and operation of subsea production systems

References

Reliability Implementation Manual 57


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library
15. BP Contacts and Champions
The following list of names is not offered as a comprehensive list. There have been many other helpful contributors, simply too
many to name, so apologies are offered for exclusions.

Aberdeen Sunbury
Zander Bruce zander.bruce@uk.bp.com Andy Bennett andy.bennett@uk.bp.com
Keith Williams keith.williams2@uk.bp.com David Brookes david.brookes@uk.bp.com
Steve Burchell steve.burchell@uk.bp.com
Houston
Craig Duell craig.duell@uk.bp.com
Tom Ames tom.ames@bp.com
Alan Edwards alan.edwards@uk.bp.com
Bill Broman william.broman@bp.com
Kevin Muller kevin.muller@uk.bp.com
Mike Byrd michael.byrd@bp.com
Andy Sworn andy.sworn@uk.bp.com
Barbara Fagan barbara.fagan@bp.com
Paul Tooms paul.tooms@uk.bp.com
Ray Fleming ray.fleming@bp.com
Geoff Vine geoff.vine@uk.bp.com

py
Gary Harrison gary.harrison@bp.com
Mark Worsley mark.worsley@uk.bp.com
Cathal Kelly cathal.kelly@bp.com

Co
Christopher Lindsey-Curran chris.l-c@bp.com
Mark Siegmund mark.siegmund@bp.com
Trevor Smith trevor.smith@bp.com
d
Norway
le
Eiliv Janssen eiliv.janssen@no.bp.com
l
ro
nt
co

External Consultants
Liz Garry e.garry@boreasconsultants.com
Un

Caroline Roberts-Haritonov c.roberts@boreasconsultants.com


Neil Robertson n.robertson@boreasconsultants.com
John Strutt j.strutt@boreasconsultants.com
Karl Woods k.woods@boreasconsultants.com

Contacts & Champions

Reliability Implementation Manual 58


Downloaded Date: 05/17/2007 05:49:52
The latest update of this document is located in the BP ETP and Projects Library