Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Implementation
Manual
py
Implementing Subsea Reliability
Improvement in Projects
Co
d
lel
ro
nt
co
Un
Issue Date:
November 2006
To be prepared by Andy Ingels at the request of Dave Brookes due in November 2006
py
Co
d
l le
ro
nt
co
Un
Foreword
GP 78-03, Guidance on Practice for Achieving Reliability in Subsea Projects [2], requires the use of this
manual to identify the required Reliability Tasks necessary to meet the requirements of the strategy. GP 78-
04, Guidance on Practice for Reliability Techniques for Subsea Projects [3], similarly requires the
appendices to this manual to implement the required Reliability Tasks in projects. This manual is included
in the ETP library for use with GP 78-03 and GP 78-04. The use of GP 78-06, Guidance on Practice for
Subsea Prototype Qualification Procedure [4], and GP 78-26, Guidance on Practice for Subsea Reliability
and Maintenance Data Collection [5] is required by GP 78-03, GP 78-04 and this manual.
Ten specific Reliability Tasks have been developed to enable subsea projects to implement the Reliability
Strategy by achieving the following objectives:
py
1. Define reliability and maintainability goals and requirements for the system under development,
Co
and link to the BP CVP and other relevant BP processes
2. Plan Reliability Tasks by CVP stage to meet the reliability and maintainability goals and
requirements
d
3. Design the system to meet the reliability and maintainability goals and requirements (where
le
possible)
4. Provide assurance that the requirements have been met and assurance of the extent to which
l
ro
appropriate.
co
The aim is that GP 78-03 and GP 78-04 together with this manual, GP 78-06 and GP 78-26 will provide a
consistent approach to achieving reliability across all BP subsea projects and will convey a clear and
consistent message of the requirements through the procurement cycle.
Un
The key tasks for reliability achievement are grouped by CVP stage with flowcharts and tables defining how
and when different activities should be completed.
For each CVP stage a Reliability Task table provides guidance on specific activities and associated timing.
However, they do not prescribe exactly how the work will be carried out or by whom. This is deliberate.
Every project is different. Teams should make judgements on how to implement the strategy according to the
resources and skills available. A set of comprehensive appendices support the task tables with more detailed
guidance.
The technical risk categorisation task (R1) assesses the level of technical risk within the subsea project. This
enables the user to determine the importance of each of the Reliability Tasks, identify the reliability effort
required for the project and implement the requirements of GP 78-03, GP 78-04 and this manual accordingly.
Executive Summary
py
9. DEFINE STAGE RELIABILITY TASKS 29
10. EXECUTE STAGE RELIABILITY TASKS 36
Co
11. OPERATE STAGE RELIABILITY TASKS 50
12. GLOSSARY 54
13. LINK TO RELIABILITY STANDARDS 56
d
14. REFERENCES 57
le
15. BP CONTACTS AND CHAMPIONS 58
l
ro
nt
Contents
Design
Designout
outall
all Foreseeable
Foreseeableearly
earlylife
lifeand
andthrough
throughlife
lifefailures
failures
Remove
Remove Remove
RemoveororMinimize
Minimize Decommission
Decommission
Failure rate
expensive
expensiveearlyearly foreseeable
foreseeablethrough
throughlife
life before
before
life
lifefailures
failures failures
failures wear
wearout
out
py
Co Operating time
d
Historical performance
le
Reliability Strategy Goal
l
ro
This document develops the principles contained in The BP Subsea Reliability Strategy, A guide for BP Leaders [1] (The Strategy
nt
Guide) and identifies how these can be adopted into subsea projects. It provides the necessary supporting guidance required by GP
78-03, Guidance on Practice for Achieving Reliability in Subsea Projects [2], and GP 78-04, Guidance on Practice for Reliability
Techniques for Subsea Projects [3], to implement the BP Subsea Reliability Strategy within BP subsea projects.
co
New technology development projects and field development projects using novel equipment / new technologies will inevitably
Un
involve a significant level of design and qualification testing and this manual interfaces with the qualification requirements of GP 78-
06, Guidance on Practice for Subsea Prototype Qualification Procedure [4]. The practices in this manual, though designed for field
development projects, may therefore also provide useful guidance to achieve improvement in technology reliability for new
technology developments projects.
This manual is relevant for all subsea system equipment likely to be included in the subsea procurement specification. The following
diagram describes a typical subsea system.
Design analysis techniques for different types of equipment will mean that the interpretation and application of the guidelines
outlined in this manual may be slightly different for different types of subsea equipment. It is also important to note that the
approach that has been developed is not limited in application to subsea, and has the potential to be applied across projects in all
disciplines.
Importantly for the reliability of subsea projects to continue to meet BP requirements and continue to improve with time, collection
of performance data is essential. GP 78-26 [5] defines the requirements for data collection as recommended by this manual.
In addition to this manual’s alignment to CVP, it is also closely linked to and supports the objectives of other BP processes such as
Front End Loading (FEL) and Value Improvement Processes (VIP), referenced amongst others, in the Major Projects common
process (MPcp).
Introduction
SEA LEVEL
py
Risers Umbilical Tool carrier(s) W.O. riser joints
Tree cap
Control
co
module Tree
Un
Choke
Tubing hanger
Manifold / Downhole
sensors/valves
Import distribution module Prod.
riser base or Guide
tie-in spool base Packer
Reservoir
Foundation structure
Export (could be common
riser base or for trees and
tie-in spool manifold)
Introduction
Emanating from these processes are the 10 specific Reliability Tasks (R1 to R10), initially defined in the original version of this
manual, which was published in February 2005 as The Reliability Handbook, to be implemented within a project to achieve the
required level of reliability.
In 2006, implementation of these tasks became a mandatory requirement for BP subsea projects through the issue of GP 78-03 [2]
and GP 78-04 [3]. At the same time this manual was renamed, produced electronically and updated both to align with these two GPs
and to provide supporting essential guidance for projects. In addition, The Strategy Guide [1], has been updated to make readers
aware of the GPs, to show the linkage between the 10 Reliability Tasks and the key processes, and to align the definition of the key
processes with those described in API RP 17N “Recommended Practice Subsea Production System Reliability & Technical Risk
py
Management” [6] which has been drafted since The Strategy Guide [1] was first published. The hierarchy of these BP documents
and other relevant GPs is shown in the following diagram.
GP 78-03
nt
Achieving GP 78-26
Reliability in Subsea Reliability
co
GP 78-04 GP 78-05
Reliability Testing of Subsea
Techniques for Equipment: FAT,
Reliability Subsea Projects EFAT and SIT
Implementation
Manual
GP 78-30
Reliability Integrated Subsea
Implementation System Testing/
Manual Commissioning/
Appendices Start-up
py
Project
Engineers
Co
9 Document that is best read to gain further understanding and detail
d
l le
ro
nt
co
Un
The BP Capital Value Process is used both for project assurance and to successfully steer and manage a project from field appraisal
through the FEED and detailed design stages and into operation. Each CVP stage is divided by a ‘Gate’, which requires the
submission of a ‘Decision Support Package’ (DSP) for approval by the project ‘Gatekeepers’ before moving to the next stage of the
project.
Develop the
Choose the Right Project Project Right Deliver the Project Right
py
Co
The output from the reliability activities form part of the reliability assurance documentation, collated as the RAD, which shall be
available to support the DSP at each CVP stage gate.
d
Roles and Responsibilities
le
The Reliability Strategy has implications for contractors (engineering services) and suppliers (hardware) working for BP.
l
ro
The main reliability responsibility of contractors and suppliers is to develop processes to deliver systems that meet BP requirements.
They shall be able to carry out reliability and availability modelling, manage reliability data, modify design and test for reliability and
nt
It is the responsibility of the BP project team integrated with its selected engineering contractors to determine reliability goals and
requirements and make decisions that encompass reliability assessment. The managing team shall carry out reliability value analysis,
investigate high level system reliability, plan and budget for reliability, give direction to the contractors and suppliers, carry out
Un
review activities including validation and verification of Reliability Tasks, and assess and manage technical risks.
All subsea project managers, shall be responsible for communicating the reliability expectations to their teams and suppliers, and
shall be accountable for delivery of reliability performance.
A Reliability Lead, reporting to the project manager, shall be appointed for each subsea project and shall be
• Accountable for ensuring that the R&M requirements are achieved and championing the Reliability Strategy;
• Responsible for maintaining the overall project Reliability Plan, schedule and assurance documentation;
• Employing specialist reliability resources as required;
• Prioritising the application of reliability techniques to obtain maximum benefit;
• Overall leadership of BP contractors, suppliers and sub-suppliers to achieve effective reliability
implementation and alignment with goals and requirements.
Package managers shall be accountable for delivery of subsea equipment to address the R&M goals and meet the R&M requirements
for the package and responsible for maintaining the package Reliability Plan, schedule and assurance documentation.
Reliability Tasks
This manual contains guidance on how and when Reliability Tasks shall be carried out to generate the maximum benefit to the
project. The Reliability Tasks are designed to influence the way reliability is managed during design and manufacture in the subsea
Activities by CVP
Projects shall plan for their reliability activities from the outset and high-level R&M goals and requirements, described in the RAD,
should be included within the Basis of Design (BOD) to demonstrate satisfying the Statement of Requirements (SOR). Each project
shall have documented systems in place to meet the expectations, including justification, where necessary, why certain tasks are not
applicable to that project.
The Reliability Task tables that follow in Sections 7 to 11, for each CVP stage, aim to provide guidance on specific activities and
associated timing. However, they do not prescribe exactly how the work will be carried out or by whom. This is deliberate. Every
project is different. Teams should make judgements on how to implement the initiative according to the resources and skills
available. In some cases (such as for long lead items), it may be necessary to accelerate the reliability process to keep up with the
design process i.e. do certain CVP stage Reliability Tasks before the official start of that CVP stage.
The following table lists the Reliability Tasks (R1 to R10) and is a synopsis of the Reliability Tasks required per CVP stage. Blank
entries in the table indicate that a specific Reliability Task is not required in the respective CVP stage. The labels A, S, D, etc are
given to distinguish between the different CVP stages as explained in Section 4 following. i.e. A = Appraise, S= Select, etc.
py
Reliability Task Name / Reliability Appraise Select Define Execute Execute Operate
Implementation Manual Appendix ref #. Engineering & Construction
Co
Procurement & Handover
R4 Reliability Assurance A4 S4 D4 E4 C4 O4
l
ro
Activities by CVP
The MPcp requires the capture and review of lessons learned at every CVP stage. The
lessons learned usually cover the whole life of the project from strategic thinking and
Lessons
decision making, through project execution and the delivery of benefits. The TAs, supported
I.1 Learned
by the project team shall be responsible for ensuring that past lessons impacting on reliability 9 99 9 9 9
Review
performance are considered at every CVP stage. Clear actions shall to be identified to ensure
the lessons are implemented on the project. These shall then input to the reliability activities.
An assessment of project risks is required by the BP Risk Management Guidelines for Major
Projects at each CVP stage. These activities should explicitly address risks that impact
product reliability with clear actions to ensure the risks are mitigated through the project and
Project Risk
I.2
Review
are addressed in the Project Risk Response plans. These shall then input to the reliability 9 99 9 9
py
activities. Reliability effort will not bring value to a project unless it is carried out to the
appropriate level. A project, which adopts reliability, and then is forced to cut resources will
likewise not realise the benefits of the effort.
Co
Integrity Management is a mandatory process in BP. The Project Quality Management
System (QMS) aims to ensure that the specified levels of integrity, quality and reliability
required to meet BP business goals are attained, demonstrated and delivered in operation.
Quality Strong Quality Management implementation is therefore fundamental to meet and achieve
I.3 9 99 9 9 9
d
Management reliability requirements. The R&M goals and requirements and Reliability Plan shall reflect
the requirements of QM, both in design and manufacture, and Reliability Tasks identified to
le
address quality improvement requirements. Also, data derived from QM activities, needed
as evidence of qualification and/or reliability assurance, shall be sought.
l
There is a strong interface between safety management and reliability management. Both
ro
disciplines consider the avoidance of failure and their consequences. The objective of
reliability management is to avoid failures that may generate any adverse consequence
nt
are accounted for in the reliability analysis to determine any required reliability
improvements for the equipment. If a Safety Critical Element requires a very high level of
reliability then this shall be reflected in the technical risk categorisation and associated
Un
Activities by CVP
py
Handover Phase
Co
d
l le
ro
nt
co
Un
Activities by CVP
For each CVP stage, a summary flowchart shows the relevant Option Technical Risk Upgrade Option R&M
Reliability Tasks which are colour coded blue. The flow Categorisation Goals and Requirements
S1 S2
chart boxes are labelled A for Appraise, S for Select, D for
Define, etc. and numbered according to the Reliability Task
numbering and associated appendices to this manual. Update Reliability Plan Update Qualification
for Select and Define Plan for Options
S3 S10
A– Appraise
S– Select
D– Define High Level Option RAM Option Reliability Value
py
E– Execute engineering and procurement phase Modelling Analysis
S6 S5
C– Execute construction and handover phase
O– Operate.
Co
Contractor Reliability
Capability and Scope for Define
The flowchart for Select, taken from Page 23, is shown for S8
d
example.
le
Reliability Assurance to assist
There are some Reliability Tasks that need to be performed in Option Selection
l
S4
parallel (i.e. S1-S2, S3-S10, etc.).
ro
Define Gate
nt
co
These are colour coded red and are shown alongside the CVP I.4 Safety Management S1
flowchart in a table which indicates which Reliability Tasks I.5 Reliability Data S2, S6
they input to. The Select input tasks, taken from Page 23, are
I.6 Qualification Status S1, S10
shown here.
For each CVP stage, the first Reliability Task is Technical Risk Categorisation (see Appendix R1). The output of this task is
a technical risk category (A, B, C or D) for the project, an option, a package or component.
The task description tables also contain columns for each of the four technical risk categories (A, B, C & D) which show (i) the
importance of the task, (ii) the need for the task and the type of reliability activity (quantitative/qualitative) and (iii) the predicted
effort required for that task appropriate to each technical risk category. Colour coding schemes are used in the tables to relate the
category of the project/package/component to the recommended level of reliability activity.
The Select stage Reliability Task S3, taken from page 26, is shown as a worked example:
Technical
CVP Task Descriptions Risk
Category
py
A B C D
Co
Task Goal Define at a more detailed level, the type of activity required to demonstrate
reliability in the project.
Description
d
Input
l le
ro
Output
nt
Resources
co
The Importance of the task is shown in the Goal section and is scored in terms of: H High M Medium L Low.
The importance designation given for each technical risk category has been predetermined and shall be followed as described.
Un
Technical
CVP Task Descriptions Risk
Category
A B C D
Description
Input
Output
Resources
Hence, it can be seen, for example, that Task S3 is of medium importance for a technical risk category C project option.
Technical
CVP Task Descriptions Risk Ref
Category
A B C D
Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project
schedule.
• The resources required to facilitate these activities, including the
definition of the Reliability Team
py
Identify a high level vision for reliability activities in the Execute stage of the
project.
Input
Co
Output
Resources
d
le
The required input for a Reliability Task (earlier Reliability Tasks and Input Tasks) is shown with the associated task reference (S1,
l
ro
S2, I.3, etc). The required output from the task is also shown. i.e. in this case, an updated Reliability Plan.
nt
Technical
CVP Task Descriptions Risk Ref
Category
co
A B C D
Task Goal Define at a more detailed level, the type of activity required to demonstrate
reliability in the project.
H H M L Importance
Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project
schedule.
• The resources required to facilitate these activities, including the
definition of the Reliability Team
Identify a high level vision for reliability activities in the Execute stage of the
project.
Input Option technical risk categorisation S1
Option R&M goals and requirements S2
Quality Management I.3
Qualification Plan S10
Appraise stage Reliability Plan A3
Output An updated Reliability Plan
Resources
Technical
CVP Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project
py
schedule.
• The resources required to facilitate these activities, including the
definition of the Reliability Team
Co
Identify a high level vision for reliability activities in the Execute stage of the
project.
Input Option technical risk categorisation S1
Option R&M goals and requirements S2
d
Quality Management I.3
Qualification Plan S10
le
Appraise stage Reliability Plan A3
Output An updated Reliability Plan
l
Resources
ro
Quantitative tasks involve considering characteristics by numerical properties representing amount, size, probability, etc.
nt
Note: If a project is required to carry out a reliability activity in a quantitative manner, it is also required to carry out any
Un
So, in the example below, a technical risk category A or B design option is estimated to require up to 50 man hours to construct the
Reliability Plan during Select, whereas a technical risk category C or D design option is estimated to require less than 10 hours.
Technical
CVP Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional
Co
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
d
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project
le
schedule.
• The resources required to facilitate these activities, including the
l
Identify a high level vision for reliability activities in the Execute stage of the
project.
Input Option technical risk categorisation S1
nt
Resources The plan should be defined by the project Reliability Lead together with a
L L VL VL Effort
reliability specialist in negotiation with the project manager.
As the project moves through CVP, the project Reliability Lead and package managers shall use the relevant CVP Reliability Task
table as a guide to help build and update the project Reliability Plan. The tables facilitate the use of the technical risk category for an
item (project, option, package, component, process) to determine the need for and the importance of a task, understand what is
required from the task and to estimate the level of resources needed for that task.
The design of a system or package will define the optimum reliability that shall be achieved for that equipment based on
manufacturing and operational risks. Design decisions can both increase and decrease the inherent reliability of the
equipment and shall take into account the controls required to maintain reliability during manufacture, assembly and
construction.
For example, material specifications may be changed to reduce cost at the design stage; however the associated difficulty of
managing the lower cost material during manufacture may result in lower reliability and extra overall cost.
Manufacturing, assembly and fabrication processes can only maintain or reduce the reliability theoretically inherent in the
design.
Therefore:
• The QM Process shall ensure that reliability goals and requirements are set in the Design phase and are managed
py
throughout manufacturing and installation to ensure reliability meets or exceeds actual expectations in operation;
• The QM effort and resources shall be allocated to ensure that equipment reliability is not compromised by poor
Co
quality assurance and control processes during manufacture, assembly, test, handling, storage and installation.
78-03 and GP 78-04). It is not the intention of this manual to describe the QMS that would normally be required within a subsea
ro
project. The reliability team shall undertake its responsibilities in close collaboration with the QM function, incorporating their
requirements within the project QMS.
nt
In BP subsea projects the QMS shall incorporate R&M goals and requirements and practices. This typically addresses the following:
co
• In forming the Reliability Team, attention to its structure and linkage to the QM function shall be addressed.
• Formation of the Reliability Team within in the project team, including as a minimum a Reliability Lead, to report directly
Un
It is important for BP to recognise and for contractors and suppliers to understand that industry standard QMS do not normally
address equipment reliability and that good reliability practices should be integrated within their existing QMS. It is envisaged
therefore that contractors and suppliers shall be assessed on their historical performance and how their approach to reliability is
integrated into their design and manufacturing QM systems. Further details on required reliability capabilities can be found in
Appendix R8 “Contractor and Supplier Selection and Contracting”
BP or a BP appointed third party shall review the Reliability Tasks to verify that the tasks are being performed correctly and that
valid data, models, assumptions, etc are being used. Depending on the task, the reviews should be performed by two or more of the
following:
• A BP engineer from the current project team familiar with the reliability activity
• A BP engineer from outside the project team familiar with the reliability activity
• Peer review team
• Independent external verification and validation authority with expertise and experience in subsea reliability
• A member of the BP Project QM team
py
Greater confidence can be gained from the verification and validation process, when carried out by a reviewer independent to the
original task. Verification and validation should be carried out at a number of levels as described below:
Co
Validation
Validation is the process which substantiates whether a physical entity, a model, data, a test or assumption within their
d
domain of applicability, possesses a satisfactory range of accuracy consistent with the intended application. i.e. “Are we using
le
the right data or model?”, “Is it the correct test?”
Data: Ensure that all data and assumptions are validated against historical data and experience to ensure that decisions are being
l
ro
Tests: Validate all planned testing to ensure that the correct test is being performed. For example, a test designed to demonstrate
functionality does not necessarily demonstrate reliability.
co
Verification
Un
Verification is the process which determines the extent to which a procedure, task, physical product or model conforms to its
specification. i.e. “Are we performing the task correctly?”, “Does the valve hold pressure?”
Data: Verify all data, design assumptions and reliability models used for reliability analyses to be obtained from valid sources and
databases.
Processes: Ensure that all required processes and activities, deemed as necessary by the application of this manual, have been
completed appropriately.
Capability: Benchmark the capability of the organisation to perform against the key BP reliability processes. This information
should be shared within BP.
Peer Reviews
As part of the verification and validation process, Peer Reviews organised as normal practice to satisfy CVP should review the
Reliability Plan, the status of the required reliability activities and assure that the reliability risks associated with the project are
properly identified and being correctly mitigated. The Peer Review team should therefore include personnel familiar with reliability
techniques and their application.
py
Create Reliability Plan for Qualification Plan for
Co
Appraise & Select Technology Stretch
A3 A10
d
le
Contractor Reliability
Capability for Select
l
A8
ro
nt
Initiate Reliability
Assurance (RAD)
co
A4
Un
Select Gate
Appraise
Technical
Appraise Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
The R&M goals and requirements and Reliability Plan shall reflect the
requirements of QM, both in design and manufacture, and Reliability Tasks
identified to address quality improvement requirements.
Co
Ι.6 Qualification Status
Description The BP MPcp requires a Technology Plan to be identified at the Appraise stage
with sources of funding identified to ensure appropriate use and viable
development of any necessary innovative technologies. A high level review of
d
technology needed in the project together with its current qualification status
(TRL) is required at the start of the Appraise stage. This activity should address
le
both the field environment and the need for improved reliability through
implementation of new technology.
l
Task Goal Identify the overall level of technical risk involved in the project by deciding into
which technical risk category the project is classed.
H H H H Importance
nt
Description Identify other projects in the region or similar environments with appropriate R1
characteristics, to learn from experiences
• Project environment
co
• Development complexity
• Reservoir conditions
• Greenfield vs. Brownfield
Un
Appraise
Technical
Appraise Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
in the BOD to demonstrate satisfying the SOR.
• Specification of Project R&M goals and requirements including those for
tender and procurement documents
Resources The evaluation should be carried out by the Appraise team supported by a
Co
VL VL VL VL Effort
reliability specialist.
A3 Create Reliability Plan for Appraise and Select
Task Goal Indicate at a high level, the type of activity required to demonstrate reliability in
H M L L Importance
d
the project.
Description Ascertain from the R&M goals and requirements the general level of effort R3
le
considered beneficial to achieve any reliability improvement required.
Identify Reliability Tasks required as part of the qualification process for high
technical risk category projects.
l
ro
Outline a practical Reliability Plan for the Select stage (based on the CVP
Reliability Task tables), including:
• The reliability activities required.
nt
Identify a high level vision for reliability activities in later stages of the project
Input Project technical risk categorisation A1
Quality Management I.3
Un
Appraise
Technical
Appraise Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
Reliability Analysis and Modelling
• Design for Reliability
• Reliability Assurance
•
Co
Reliability Value Analysis
Input Lessons learned from previous projects Ι.1
Quality Management I.3
Project technical risk categorisation A1
d
High level R&M goals and requirements A2
Reliability Plan A3
le
Output Assessment of engineering contractor reliability capability and a preliminary
execution schedule including reliability activities, targets and incentives
l
L L VL VL Effort
in conjunction with the project Reliability Lead
A4 Initiate Reliability Assurance
nt
Task Goal Initiate the development of a Reliability Assurance Document (RAD). H M M L Importance
Description Define Reliability Assurance Document format for the project. R4
co
Describe high level R&M goals and requirements of the contender options.
• Record the outline of the preliminary Reliability Plan and Qualification
Plan for each contender option.
• Summarise engineering contractor reliability capability from tenders.
Input Project technical risk categorisation A1
Quality Management I.3
High level R&M goals and requirements A2
Reliability Plan A3
Qualification Plan A10
Contractor reliability capability assessment A8
Output A Reliability Assurance Document (Appraise) to be included with the Decision
Support Package (DSP) presented for the Select Gate.
Resources The RAD should be prepared by the Reliability Lead with support from a
VL VL VL VL Effort
reliability specialist as appropriate.
Appraise
py
S3 S10
Co
High Level Option RAM Option Reliability Value
Modelling Analysis
S6 S5
d
le
Contractor Reliability
l
S8
nt
Option Selection
S4
Input Tasks Required by
Un
Select
Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
requirements.
Co
shall be identified and reflected in the technical risk categorisation and associated
Reliability Tasks. It is important that safety critical hardware achieve a high level
of reliability and availability performance by undergoing reliability analysis for
functionality and operability.
d
Ι.5 Reliability Data
le
Description A review of relevant reliability data is required during the Select stage to provide
approximate figures for the potential reliability that may be achieved by the
different design concepts under consideration. This data inputs to the reliability
l
ro
activities.
Description The BP MPcp requires the Technology Plan to be updated in Select to ensure
progress on development and implementation of all unproven essential (enabling)
and value enhancing technologies such that risks are acceptable and mitigation
co
plans identified. A high level review of technology needed for each option
together with its current qualification status (TRL) is required at the start of the
Select stage. This activity should address both the field environment and the
Un
Select
Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
its TRL.
Input Lessons learned from previous projects & engineer/supplier liaison Ι.1
Appraise stage project technical risk categorisation A1
Co
Project risks Ι.2
High level option R&M goals and requirements S2
Requirements for safety critical hardware I.4
Qualification status of required technology for each option Ι.6
d
Output A statement of technical risk category, with justification, for each development
option under consideration.
le
Resources The decision-maker should seek the advice of technical experts. VL VL VL VL Effort
Task Goal Define R&M goals and requirements for specified options. H H M L Importance
Description Review environmental and operability conditions that affect the reliability or R2
maintainability of each system option under investigation
nt
Identify balance between maintainability strategy and reliability strategy for each
option
Update organisational requirements for each option
Un
Select
Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description For each option, review the preliminary Reliability Plan defined at Appraise. R3
Make an updated assessment of the level of effort considered necessary to
achieve the R&M goals and requirements set based on the technical risk
categorisation and the CVP Reliability Task tables. Identify additional
Reliability Tasks required for option technology qualification and by QM.
Update and identify a practical Reliability Plan for the Select and Define
stages including:
• The reliability activities required (e.g. FMECA, FTA, RBD,
Quantitative reliability analysis at system and sub-system level).
• When they will be required within the Select & Define project
schedule.
• The resources required to facilitate these activities, including the
definition of the Reliability Team
Identify a high level vision for reliability activities in the Execute stage of the
project.
Input Option technical risk categorisation S1
Option R&M goals and requirements S2
py
Quality Management I.3
Qualification Plan S10
Co
Appraise stage Reliability Plan A3
Output An updated Reliability Plan
Resources The plan should be defined by the Reliability Lead with support from a reliability
L L VL VL Effort
specialist where necessary in negotiation with the project manager.
d
S10 Update Qualification Plan for Options
Task Goal Indicate at a high level, the activity required to demonstrate qualification for each
le
option.
H H Importance
Description Update the qualification matrix for unqualified technology and identify the level
l
of activity required in later CVP stages for each option, in particular those items R10
ro
Select
Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Identify system failure modes that will cause production outages through a R6
preliminary FMECA.
Keeping analysis at a package level, assess the probability of system failure
modes.
Feed this information into a high level RAM model
Use the RAM model to assess the acceptability of the system configuration and
the relative importance of the various system elements (packages).
Perform Common Cause Failure Analysis to identify packages vulnerable to
common cause failures. (Quantitatively where data permits).
Interface with value analysis to identify potential for reliability improvement
Input Project/option technical risk categorisation S1
R&M goals and requirements S2
Reliability Value Analysis S5
Reliability Data I.5
•
py
Output FMECA and CCFA reports and associated mitigation action list.
• Report RAM analysis results as evidence of reliability achievement at this
stage of analysis in the Reliability Assurance Document.
• For technical risk category D, the output from previous project work should
Co
be sufficient.
Resources The RAM analysis should be carried out by the reliability specialist with direct
review/input from the project team. A reliability specialist should support M L L VL Effort
engineers performing FMECA/CCFA activities.
d
S5 Option Reliability Value Analysis
le
Task Goal Determine the commercial value of investing in specific reliability improvement
for the various options under consideration to deliver high level R&M goals and H H M L Importance
requirements.
l
ro
Select
Technical
Select Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Investigate contractor commitment to reliability engineering (both long term and R8
short term) that results in an improvement in reliability performance and consider
use of incentives.
Include project R&M goals and requirements and required Reliability Tasks in
tender and procurement documents and prepare contractor reliability capability
evaluation criteria.
When reviewing tenders, evaluate contractor’s capability to design/manufacture
for reliability together with their ability to perform specific Reliability Tasks.
This shall take into account organisational systems and processes they have in
place to support reliability improvement
Examine tenders for specific reliability engineering activities. The award of
contracts may consider all or some of the following:
• Change Management procedures
• Implementation of Lessons Learned Systems
• Reliability Data Management
py
• Reliability Analysis and Modelling
• Design for Reliability
• Reliability Assurance
Co
• Reliability Value Analysis
Input Lessons learned from previous projects Ι.1
Quality Management I.3
Project technical risk categorisation S1
d
R&M goals and requirements S2
le
Reliability Plan S3
Qualification Plan S10
l
Description Review RAD format for the project. Within the RAD: R4
• Describe the technical risk category for each option providing background
information and evidence to support the category selected
• Describe option R&M goals and requirements
• Present results of the high level systems reliability modelling of each option
and any value analysis for reliability improvement
• Present the updated version of the Reliability Plan and Qualification Plan
including relevant estimates of effort and resource
• Summarise how QM reliability requirements shall be addressed
• Summarise contractor reliability capability from tenders
Input Project technical risk categorisation S1
Reliability requirements S2
Reliability Plan S3
Qualification Plan S10
Quality Management I.3
High level systems reliability modelling S6
Reliability value analysis S5
Contractor reliability capability assessment S8
Appraise stage RAD A4
Output A Reliability Assurance Document (Select) to be included with the DSP
presented for the Define Gate
Resources The RAD should be prepared by the Reliability Lead with support from a
L L VL VL Effort
reliability specialist as appropriate.
Select
Goal Finalise project scope, cost and schedule and obtain project funding
Develop and define the selected option(s) and provide the appropriate level of detailed planning and
Activities design to determine the scope of the project and to develop more detailed cost and schedule
estimates.
Perform technical risk categorisation for packages. Finalise reliability assessment of the project;
Reliability
create a clear reliability strategy to define in detail the reliability activities and resources required
Input
for the project. These requirements shall be defined within project specifications.
py
Update System
Architecture to Meet R&M Update Reliability Plan Update Qualification
for Define and Execute Plan for all Packages
Co
Goals & Requirements
D7 D3 D10
d
Package RAM Modelling Package Reliability
le
Value Analysis
D6 D5
l
ro
Contractor / Supplier
nt
D8
Input Tasks Required by
I.1 Lessons Learned D1, D2, D8
Un
Update Reliability
I.2 Project Risk Review D1, D2 Assurance
I.3 Quality Management D2, D3, D4, D8, D10 D4
I.4 Safety Management D1
I.5 Reliability Data D2, D6, D8 Execute Gate
I.6 Qualification Status D1, D10
Define
Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
reflect the requirements of QM, from design through to manufacture, and
Reliability Tasks identified shall address any necessary quality improvement
needs. Also, data derived from QM activities, required as evidence of
qualification and/or reliability assurance, shall be required.
Co
Ι.4 Safety Management
Description If safety critical hardware forms an integral part of a package or the project, this
shall be identified and reflected in the technical risk categorisation and associated
d
Reliability Tasks. The safety analysis may be used as a starting point for the
reliability analysis but the project shall recognise the different context of the two
le
analyses and ensure that functionality critical failure modes are also identified,
evaluated and managed.
l
Description For each system, subsystem and component, as appropriate, the expected service
conditions shall be considered in order that historical data available is shown to
nt
reliability activities.
Description The BP MPcp requires the Technology Plan to be updated in Define to ensure
that progress on development and implementation of all unproven essential
(enabling) and value enhancing technologies are completed by the appropriate
time in Execute. A review of technology needed for each package together with
its current qualification status (TRL) is required at the start of the Define stage.
Define
Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
Select stage project technical risk categorisation S1
Project and package risks I.2
Package R&M goals and requirements D2
Co
Requirements for safety critical hardware I.4
Qualification status of required technology for each package Ι.6
Output A statement of technical risk category, with justification, for each major
engineering package.
d
Resources The technical risk categorisation should be defined by BP package engineers with
L L L L Effort
the support of the reliability specialist.
le
D2 Allocate Package Reliability and Maintainability Goals and Requirements
Task Goal Update System R&M goals and requirements for the selected Option and allocate
l
H H M L Importance
ro
Identify balance between maintainability strategy and reliability strategy for each
package and ensure the design specifications reflect these strategies.
Specify organisational requirements for each package
Un
Define
Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Review the updated Reliability Plan defined at Select. Make an updated R3
assessment of the level of effort considered necessary to achieve the R&M goals
and requirements, the qualification requirements and QM requirements.
Update and identify a practical Reliability Plan for Define and Execute stages
based on the CVP Reliability Task tables and the technical risk categorisation
results, including which reliability activities are required, when they are required
and what resources are required to facilitate these activities (they should allow for
including installation commissioning and operations expertise, as appropriate).
These activities should include (but not be limited to) the following:
• FMECA (both for reliability and qualification)
• TRAP (Levels 1 & 2)
• FTA/RBD at system and sub-system level (both for reliability and
qualification as appropriate) and RAM Model
• Development of a reliability testing programme (in conjunction with the
qualification testing programme) to demonstrate reliability. Reliability
analysis during the Define stage facilitates the decision regarding what to
py
test and how to test.
The overall project schedule may require early procurement of some long lead
items, in which case relevant reliability activities should be planned for early.
Input Project/package technical risk categorisation D1
Co
Project/package R&M goals and requirements D2
Quality Management I.3
Select stage Reliability Plan S3
Qualification Plan D10
d
Output An updated Reliability Plan
le
Resources The plan should be defined by the project Reliability Lead together with a
M M L VL Effort
reliability specialist in negotiation with the project manager.
l
Task Goal Specify the activities required to demonstrate qualification for each package. H H M L Importance
Description Update the qualification matrix for all equipment and identify the qualification
nt
testing and associated acceptance criteria required in Define and Execute for each R10
package.
Input Technology qualification status (TRL) Ι.6
co
Define
Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Identify package failure modes that will cause production outages through a R6
FMECA.
Considering the failure logic within each package, using RBDs or FTA assess the
probability of package failure modes.
Refine the Select RAM analysis model in more detail for each package
Assess the importance of the various components to the package failure modes
Perform Common Cause Failure Analysis to identify package components
vulnerable to common cause failures.
Interface with value analysis to optimise reliability improvement and/or support
decision making on the cost effectiveness and reliability impact of design
improvements
Input Project technical risk categorisation D1
R&M goals and requirements D2
Reliability value analysis D5
py
High level Select stage system reliability analysis S6
Reliability data I.5
Output • FMECA, RBD, FTA, CCFA reports and associated mitigation action list.
•
Co
Report RAM analysis results as evidence of reliability achievement at this
stage of analysis in the Reliability Assurance Document.
• For technical risk category D, the output from previous project work should
be sufficient.
Resources The RAM analysis should be carried out by a reliability specialist with direct
d
review/input from the project team. A reliability specialist should support M L L VL Effort
engineers performing FMECA/RBD/FTA/CCFA activities.
le
D5 Package Reliability Value Analysis
l
Task Goal Determine the commercial value of investing in specific reliability improvement
ro
for the package design to deliver the necessary R&M goals and requirements.
H M M L Importance
project.
Evaluate the investment/effort required to achieve the reliability improvement.
If the investment required is greater than can be economically achieved the R&M
Un
Define
Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Determine the reliability improvement required for the system as a whole and for R7
each package from the analyses in D5 and D6.
For each reliability improvement required, determine whether the improvement is
best achieved through:
• changing the configuration;
• improving component reliability;
• introducing redundancy.
As part of the Value Improvement Process during design, it is necessary to
consider reliability improvement opportunities. It is also necessary to evaluate
the impact on reliability of other value improving and cost reducing
opportunities.
A critical aspect of design for reliability, as well as identifying the need for
change, is the identification of the impact of change on reliability. Follow up
from a change order should include a re-assessment of technical risk, reliability
and availability.
py
Input Project technical risk categorisation D1
R&M goals and requirements D2
Systems reliability analysis D6
Co
Reliability value analysis D5
Output Summary report describing recommendations for design improvement to
achieve reliability improvement to meet the R&M goals and requirements
Resources The system design should be assessed for reliability improvement and impacts of
M L VL VL Effort
d
change by the Define team supported by a reliability specialist.
D8 Contractor/Supplier Reliability Capability and Requirements for Execute
le
Task Goal Account for reliability engineering capability in the tendering process, achieve
long-term improvement in reliability performance
H H M L Importance
l
ro
Include project R&M goals and requirements and required Reliability Tasks in
tender and procurement documents and prepare contractor/supplier reliability
capability evaluation criteria.
co
Define
Technical
Define Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
Reliability Plan D3
Qualification Plan D10
Quality Management I.3
Co
Systems reliability analysis D6
Reliability value analysis D5
Updated system/package design D7
Contractor/supplier reliability capability assessment D8
d
Select stage RAD S4
le
Output A Reliability Assurance Document (Define) to be included along with the
Decision Support Package (DSP) presented for the Execute Gate.
l
Resources The RAD should be prepared by the Reliability Lead and package engineers with
L L VL VL Effort
ro
Define
Goal Finalise detailed design and procure equipment with approved cost and schedule.
Manage detailed engineering and procurement to ensure that the project achieves its cost, schedule
Activities
and operability goals.
The Reliability Plan shall be fully implemented through detailed design and procurement to ensure
Reliability
that all necessary reliability activities are carried out and that all equipment and systems are
Input
designed, procured and verified against R&M requirements.
py
Categorisation Goals and Requirements
E1 E2
Detailed Reliability
ro
Analysis
E6
nt
co
Manufacture Packages to
meet R&M Goals and
Requirements
Un
E7
Update Reliability
Input Tasks Required by Assurance
E4
I.1 Lessons Learned E1, E2, E6, E7, E10
I.2 Project Risk Review E1, E2 Construction Gate
I.3 Quality Management E2, E3, E4, E7, E10
I.4 Safety Management E1
I.5 Reliability Data E2, E6, E10
I.6 Qualification Status E1, E10
Execute
Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
the requirements of QM, from design into manufacture, and Reliability Tasks
shall address quality improvement needs. The QM activities at Execute have the
potential of having the biggest impact on whether the design reliability can be
achieved or not. Also, data derived from QM activities, required as evidence of
Co
qualification and/or reliability assurance, is required.
Description For each system, subsystem and component, as appropriate, the expected service
conditions shall be considered in order that historical data available is shown to
be relevant. A review of relevant reliability data is required during the Execute
nt
stage to provide approximate figures for the potential reliability that may be
achieved by the selected design.
Description The BP MPcp requires that all technology options as defined in the Technology
Plan are resolved by Execute and the results are supported by an implementation
Un
plan inclusive of technical, financial and schedule risk mitigation plans. A review
of the current qualification status (TRL) of each component of each package is
required at the start of the Execute stage. This activity should address any
changes such as operating environment, technology, architecture, manufacturing
process, materials, etc. since previous projects.
Execute
Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
Define stage project technical risk categorisation D1
Project and package risks I.2
Package R&M goals and requirements E2
Co
Requirements for safety critical hardware I.4
Qualification status of each major component in the system Ι.6
Output A statement of technical risk category, with justification, for each major
component.
d
Resources The technical risk categorisation should be agreed between BP and the contractor
package engineers with the support of the reliability specialist and other relevant M M M M Effort
le
technical experts.
E2 Update Package Reliability and Maintainability Goals and Requirements
l
ro
Task Goal Review/update package R&M goals and requirements in response to supplier’s
R&M activities and design improvements.
H H M L Importance
Description Review and update package R&M goals and requirements once package R2
nt
Execute
Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Review the Reliability Plan produced at Define. Make an updated assessment of R3
the level of effort considered necessary to achieve the R&M goals and
requirements, the qualification requirements and QM requirements.
Update the detailed Reliability Plan for the Execute stage including which
reliability activities are required, when they are required and what resources are
required to facilitate these activities. These activities should include (but not be
limited to) the following:
• FMECA (for reliability and qualification)
• TRAP (Levels 1 & 2)
• FTA/RBD at system and sub-system level (for reliability and qualification
as appropriate) and updating of the RAM Model
• Development and implementation of testing programme to demonstrate
reliability
Input Project technical risk categorisation E1
R&M goals and requirements E2
Quality Management I.3
py
Define stage Reliability Plan D3
Qualification Plan E10
Output An updated Reliability Plan.
Co
Resources The plan should be defined by the project Reliability Lead together with a
reliability specialist in negotiation with the project manager and the BP and H M L VL Effort
contractor package engineers.
E10 Update Qualification Plan for all Packages
d
Task Goal Update the activities required to demonstrate qualification for each package. H H M L Importance
le
Description Update the qualification matrix for all equipment and identify the qualification
testing and associated acceptance criteria required during Execute for each R10
package.
l
Ι.6
ro
Resources The Qualification Plan should be developed in conjunction with the Reliability
H M L VL Effort
Lead and relevant suppliers and specialists.
Un
Execute
Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Identify and evaluate package and component failure modes that will cause R6
production outages through a FMECA.
Considering the failure logic within each package, assess the probability of
package failure modes using RBDs or FTA. This should also address interface
and installation failure modes and should recognise the impact or failure through
the system.
Assess the importance of the various components to the failure modes
Perform CCFA to identify items vulnerable to common cause failures.
Define Specific, Measurable, Achievable, Realistic and Time-Bound (SMART)
Mitigation actions.
Investigate the design of the system and packages and identify any further
technical risks to be managed through the TRAP Level 1 process
Towards the end of detailed design, investigate the design of critical packages
and components and identify any further technical risks to be managed through
the TRAP Level 2 process.
py
Update Define stage RAM analysis to represent full equipment scope and system
architecture using verified data relevant to supplied equipment.
Input Project technical risk categorisation E1
Co
Lessons Learned I.1
R&M goals and requirements E2
RAM analysis from Define stage D6
Reliability value analysis from Define stage D5
d
Reliability data I.5
Output Report results of each activity as evidence of required mitigations to ensure
le
reliability achievement. Once actions are closed out they should be reported in
the Reliability Assurance Document. For technical risk category D, the output
l
Resources RAM analysis should be carried out by a reliability specialist with direct
review/input from the project team. Other reliability analysis should be carried
VH H M L Effort
out by all relevant members of the project team (BP, contractors and suppliers)
nt
Execute
Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
R&M goals and requirements E2
Reliability Plan for Execute E3
Qualification Plan for Execute
Co
E10
Detailed reliability analysis E6
Lessons learned from previous projects I.1
Output List of closed out reliability mitigations and corrective actions implemented
during design to be included in the Reliability Assurance Document.
d
Resources The package design should be managed for reliability achievement by the
le
package manager with verification carried out by the Reliability Lead with M M L VL Effort
support from a reliability specialist.
l
ro
nt
co
Un
Execute
Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
be initiated where they are deemed necessary.
Link to FRACAS (Failure Reporting And Corrective Action System) Information
on the defects and loss of quality shall be recorded in the suppliers FRACAS
Co
system. R10
Input Project technical risk categorisation E1
R&M goals and requirements E2
Reliability Plan for Execute E3
d
Qualification Plan for Execute E10
Detailed reliability analysis E6
le
Lessons learned from previous projects I.1
Quality Management I.3
l
ro
Output List of closed out reliability mitigations and corrective actions implemented
during manufacture and assembly to be included in the Reliability
Assurance Document.
nt
Resources The package manufacture should be managed for reliability achievement by the
package manager with verification carried out by the Reliability Lead with M M L VL Effort
support from a reliability specialist.
co
Un
Execute
Technical
Execute Engineering & Procurement Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Reliability/qualification tests planned and defined during Define & Execute shall R10
be implemented as the manufacturing and assembly proceeds. The majority of
qualification is testing performed in Execute but long lead items may need testing
in Define.
Based on the qualification requirements identified through the use of qualification
matrices during Define and further requirements identified during FMECA /
TRAP processes, perform traditional qualification tests and, where appropriate,
Accelerated Life tests and stress-screening tests.
Investigate failed or defective parts and submit to the Failure Reporting
System. Results of successful tests shall be assessed and submitted as a
contribution to the Reliability Assurance Document.
Use the results from FAT and SIT to further demonstrate appropriate
qualification.
Input Lessons learned from previous projects I.1
Quality Management I.3
py
Reliability data I.5
Project/package technical risk categorisation E1
R&M goals and requirements E2
Co
Reliability Plan for Execute E3
Qualification Plan for Execute E10
Detailed reliability analysis E6
Output Reports of qualification tests carried out and any particular findings from the tests
d
that shall be addressed. These should be referenced in the Reliability Assurance
Document.
le
Resources The qualification programme should be managed for reliability achievement by
the package manager with verification carried out by the Reliability Lead with VH H M VL Effort
l
evidence that the system and package design has been designed, manufactured H H M L Importance
and tested to achieve required reliability.
Description Review RAD format for the project. Within the RAD: R4
co
• Describe the technical risk categories for each package and major
component providing background information and evidence to support the
category selected.
Un
Execute
Goal Produce an operating asset consistent with scope, cost, schedule and operability requirements.
Manage construction and handover to ensure that the project achieves its cost, schedule and
Activities
operability goals.
Define, evaluate and implement tests and procedures as required by the Reliability Plan. Prepare the
Reliability Reliability Assurance Document for handover to demonstrate that all reliability activities have been
Input carried out and that all equipment and systems and procedures are verified against R&M
requirements.
py
Co
Update Reliability Plan Update Qualification
including Testing & Plan
Procedure Validation
C3 C10
d
le
Testing
C10
nt
Complete Reliability
co
Execute
Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
Description The QM activities at Execute have the potential of having the biggest impact on
whether the design reliability can be achieved or not. The Reliability Tasks
therefore shall address the QM requirements. This is particularly important
Co
during assembly, construction and in testing. Also, data derived from QM
activities, required as evidence of qualification and/or reliability assurance, shall
be sought.
for functionality and operability and in terms of specification for reliability and
acceptance testing.
Description A review of reliability data associated with historical failures arising from
installation and commissioning activities is required during the Execute stage to
co
Description The BP MPcp requires that the design intent is rigorously controlled through
procurement and construction, with the application of new technology tested and
operational implications reflected in commissioning and start-up plans. The
current qualification status (TRL) of each component of each package together
with details of any remaining qualification testing is required at hand over from
the manufacturer to the installation team.
Execute
Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
Technical risk categorisation of project specific novel installation equipment D1
Project and package risks I.2
Package R&M goals and requirements E2
Co
Requirements for safety critical hardware I.4
Qualification status of each major component in the system I.6
Output A statement of technical risk category, with justification, for each procedure.
Resources The technical risk categorisation should be agreed between BP and the contractor
d
with the support of the reliability specialist and other relevant technical experts VL VL VL VL Effort
including engineers responsible for installation, testing, etc.
le
C2 Update R&M and Construction Task Goals and Requirements
Task Goal Review/update R&M and construction Reliability Task requirements in response
l
H H M L Importance
ro
Execute
Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Review the Reliability Plan. Make an updated assessment of the level of effort R3
considered necessary to achieve the R&M goals and requirements, the
qualification requirements and QM requirements.
Update the detailed Reliability Plan for this part of the Execute stage including
which reliability activities are be required, when they are be required and what
resources are required to facilitate these activities. These activities should
include (but not be limited to) the following:
• Process FMECA
• Procedure Operation Risk Analysis
• FTA, ETA as required by FMECA and Operation Risk Analysis
• Procedure Testing/Simulation
• Confirmation and implementation of reliability testing programme to
demonstrate reliability
• The definition and responsibilities of the Reliability Team shall reflect the
transferred responsibility following delivery of the equipment to the
construction and installation teams.
py
Input Project technical risk categorisation C1
R&M goals and requirements C2
Quality Management I.3
Co
Execute stage Reliability Plan E3
Qualification Plan C10
Output An updated Reliability Plan
Resources The plan should be defined by the project Reliability Lead together with a
d
reliability specialist in negotiation with the project manager and the BP and L L VL VL Effort
contractor package engineers.
le
C10 Update Qualification Plan
l
Task Goal Update the activities required to demonstrate qualification for each package H H M L Importance
ro
Description Update the qualification matrix for all equipment and identify the remaining
qualification testing and associated acceptance criteria that are required before R10
installation and handover to operations.
nt
Resources The Qualification Plan should be developed in conjunction with the Reliability
L L VL VL Effort
Lead and relevant suppliers and specialists.
Execute
Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
R&M goals and requirements C2
Reliability Plan for Execute C3
Qualification Plan for Execute C10
Co
Detailed reliability analysis E6
Output Reports of tests carried out and any particular findings from the tests that require
addressing. These should be referenced in the Reliability Assurance Document.
Resources The qualification programme should be managed for reliability achievement by
d
the contractor Execute project team with verification carried out by the VH H M VL Effort
Reliability Lead with support from the reliability specialist as appropriate.
le
C4 Complete Reliability Assurance for Start-up
Task Goal Complete the Reliability Assurance Document (RAD) to provide assurance and
l
H H M L
ro
evidence that the system and packages have been built and tested to achieve Importance
required reliability.
Description Review Reliability Assurance Document for the project. R4
nt
• Update the R&M goals and requirements for construction activities and
testing procedures
• Present results of the procedure testing carried out including demonstration
Un
Execute
Technical
Execute Construction & Handover Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Record reliability failures and good practices during the project stage up to the
point of package or system handover to operations. R9
All data shall be collected to meet the requirements of GP 78-26.
Key lessons shall also be retrieved and fed back into future projects via BP
Project Lessons Learned processes defined within the BP MPcp Knowledge
Management Process and recorded in the ETP shared learning library.
Corrective actions shall also be recorded and shall be based on a failure analysis
conducted, where appropriate, with the equipment suppliers to understand the
technical and root causes of failure.
Input Information concerning:
• Failures,
• Near misses,
• Good practices
Output Reliability Data
Lessons learned
Resources Data should be collected by the contractor Execute team and fed to BP corporate
H H M VL Effort
py
reliability data management function.
Co
d
l le
ro
nt
co
Un
Execute
Goal Evaluate asset to ensure performance to specifications and maximum return to shareholders.
Support and evaluate the project end result over a one-year initial operating period and through the
Activities
life of the field.
Monitoring of technical performance, compare with assumptions and feedback results and lessons
Reliability learned. Investigate options for reliability improvements when replacing items at scheduled
Input maintenance or through failure. Treat major modifications as new projects and follow reliability
principles and practices.
Operate Reliability
Plan
O3
py
Collection, Analysis &
Validation of Reliability
Co
Data
O9 d
Qualification of Design Reliability Analysis of Reliability Value
le
Improvements Design Improvements Analysis of Design
O10 O6 Improvements
l
O5
ro
nt
O4
Un
Operate
Technical
Operate Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
Description It is essential that the higher risks associated with safety critical equipment are
accounted for in the Operate Reliability Tasks to optimise functionality and
operability and to manage any required reliability improvements for the
Co
equipment. A review of the Operate Reliability Tasks needed as part of Safety
Management requirements is therefore required.
performance of the plant and component systems through operations against the
Basis of Design. This shall involve feedback with appropriate technology groups
and other projects. In addition, during the Operate stage equipment may need to
co
Operate
Technical
Operate Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
Description Ascertain from the R&M goals and requirements the general level of effort R3
considered beneficial to achieve the required reliability and production
availability.
Ascertain QM and safety management requirements.
Outline a practical plan for reliability for the Operate stage including:
• The reliability activities required
• When they are required within the Operate project schedule
• The reliability leadership and organisation for Operate stage
• What resources are required to facilitate these activities
Outline procedures for data collection both for feedback to future projects and to
provide evidence for regulatory authorities in line with GP 78-26
Outline procedures for investigating and reporting failures
Outline procedures for replacing equipment with identical or improved
components following failure or at scheduled replacement including the
reliability analysis/assessment that is required to support the decision
Input Project RAD C4
py
Lessons learned from previous projects and operations I.1
Quality Management I.3
Safety management I.4
Co
Output Reliability Plan for Operate
Resources The plan should be outlined by the project Reliability Lead together with a
M L L VL Effort
reliability specialist in negotiation with the project manager.
O9 Collection, Analysis & Validation of Reliability Data
d
Task Goal To validate predicted reliability against experience, to demonstrate performance
H H M L Importance
le
to regulatory authorities and to provide data for future analysis and design.
Description All data shall be collected to meet the requirements of GP 78-26.
Set up systems and procedures to ensure data is collected and collated R9
l
ro
• operation
• monitoring
• inspection
co
Operate
Technical
Operate Task Descriptions Risk Ref
Category
Quantitative Qualitative Unnecessary A B C D Appendix
py
for all replacement hardware
Input Project RAM model E6
Lessons learned during this and other projects I.1
Co
Reliability data I.5
Output Risk assessment for hardware replacement
Resources Detailed reliability analysis should be performed by a Reliability Specialist L L VL VL Effort
d
O5 Reliability Value Analysis of Design Improvement
le
Task Goal To ascertain the value of replacing hardware (either at scheduled replacement or
following failure) with components having improved reliability.
H H M L Importance
Description Update previous detailed RAM Analysis and Reliability Value Analysis to
l
evidence that the system continues to achieve the required reliability and
production availability. Demonstrate that replacement hardware has been
H H M L Importance
Operate
BP Terms
py
MPcp Major Projects common process
PHSER Project, Health, Safety and Environmental Review
Co
RAD Reliability Assurance Document
RM Reliability and Maintenance
SCE Safety Critical Equipment
d
SMART Specific, Measurable, Achievable, Realistic and Time-Bound
le
SOR Statement of Requirements
l
ro
TA Technical Authority
TRAP Technical Risk Assurance Process
nt
Industry Terms
Un
Glossary
py
MTBF Mean Time Between Failure
MTTF Mean Time To Failure, (average value of the times to failure)
Co
NPV Net Present Value
OPEX Operating Expenditure over the operational life of a development
OREDA Offshore Reliability Database
d
le
QM Quality Management
QMS Quality Management System
l
ro
Glossary
The list of codes and standards given below is offered for high level guidance and may not be all inclusive. It is important to ensure
that more detailed equipment and procedure specific codes and standards are identified and complied with as may be necessary.
py
ISO 9000-4/IEC-60300 [14]
Norsok standard Z-016 [7]
International Reliability
DNV-RP-A203 [9]
API RP 17 – N [6]
IEC-60605-3 [15]
OLF GL 70 [13]
Standards
Technical Risk
9 9
ro
R1
Categorisation
Defining R&M goals
R2 9 9 9 9 9 9 9 9
nt
and requirements
R3 Reliability Planning 9 9 9 9 9
co
R4 Reliability Assurance 9 9 9 9 9 9 9 9 9
Reliability Value
9 9 9
Un
R5
Analysis
Reliability Analysis and
R6
Modelling 9 9 9 9 9 9
Design and Manufacture
R7
for Reliability 9 9 9 9 9 9 9 9
Contractor and Supplier
R8 Selection and 9 9 9
Contracting
Reliability Data
R9
Collection 9 9 9 9 9 9
Reliability Qualification
R10
Activities 9 9 9 9 9 9 9 9
Link to Standards
[2] BP GP 78-03, Guidance on Practice for Achieving Reliability in Subsea Projects, July 2006
[3] BP GP 78-04, Guidance on Practice for Reliability Techniques for Subsea Projects, July 2006
[4] BP GP 78-06, Guidance on Practice for Subsea Prototype Qualification Procedure, July 2006
[5] BP GP 78-26, Guidance on Practice for Subsea Reliability & Maintenance Data Collection
[6] API RP 17N “Recommended Practice “Subsea Production System Reliability & Technical Risk Management”
[7] Norsok standard Z-016: "Regularity management and reliability technology", Rev. 1, Dec. 1998.
[8] Standards Australia and Standards New Zealand AS/NZS 4360:1999, "Risk Management".
py
[10] ISO 9001:2000, “Quality Management Systems”
Co
[11] ISO/TS 29001:2003: Petroleum, petrochemical and natural gas industries -- Sector-specific quality
management systems -- Requirements for product and service supply organizations
d
[12] ISO 14224 Petroleum and gas industries - Collection and exchange of reliability and maintenance data for
equipment.
le
[13] Norwegian Oil Industry Association Guideline OLF GL 70, "Guidelines for the application of IEC 61508 and
l
ro
IEC 61511 in the petroleum activities on the continental shelf", Feb. 2001.
nt
[16] IEC 61508/61511 Functional safety of electrical/electronic/programmable electronic safety related systems,
Un
part 1-7.
[17] ISO/DIS 20815 Petroleum, petrochemical and natural gas industries – Production assurance and reliability
management, 2005
[18] ISO 15663 Petroleum and natural gas industries – Life cycle costing
[19] ISO 13628 Petroleum and natural gas industries – Design and operation of subsea production systems
References
Aberdeen Sunbury
Zander Bruce zander.bruce@uk.bp.com Andy Bennett andy.bennett@uk.bp.com
Keith Williams keith.williams2@uk.bp.com David Brookes david.brookes@uk.bp.com
Steve Burchell steve.burchell@uk.bp.com
Houston
Craig Duell craig.duell@uk.bp.com
Tom Ames tom.ames@bp.com
Alan Edwards alan.edwards@uk.bp.com
Bill Broman william.broman@bp.com
Kevin Muller kevin.muller@uk.bp.com
Mike Byrd michael.byrd@bp.com
Andy Sworn andy.sworn@uk.bp.com
Barbara Fagan barbara.fagan@bp.com
Paul Tooms paul.tooms@uk.bp.com
Ray Fleming ray.fleming@bp.com
Geoff Vine geoff.vine@uk.bp.com
py
Gary Harrison gary.harrison@bp.com
Mark Worsley mark.worsley@uk.bp.com
Cathal Kelly cathal.kelly@bp.com
Co
Christopher Lindsey-Curran chris.l-c@bp.com
Mark Siegmund mark.siegmund@bp.com
Trevor Smith trevor.smith@bp.com
d
Norway
le
Eiliv Janssen eiliv.janssen@no.bp.com
l
ro
nt
co
External Consultants
Liz Garry e.garry@boreasconsultants.com
Un