PROYECTO:
CLIENTE: ARSAL TOTAL PRECIO DE VENTA $1,824.25
LUGAR: SAN SALVADOR
FECHA: 4/18/2007 MANO DE OBRA MATERIALES
PRESENTA: PROYECT DE EL SALVADOR Indirectos: Utilidad Indirectos: Utilidad
1.25 0.7 1.2 0.8
ITEM DESCRIPCION Cant. Unid. PU PU SUB-TOTAL P.UNIT. P.UNIT. SUB-TOTAL TOTAL P.UNIT. P.UNIT. SUB-TOTAL TOTAL TOTAL
Instalac. Suministro Directo MO VENTA MO MO MAT VENTA MAT MAT X PARTIDA
PLAN DE OFERTA
SUB PROYECTO 1
INSTALACION DE SENSOR DE NIVEL Y
SENSOR DE TEMPERATURA EN
1.00 TANQUE TOTAL MO $1,164.25 TOTAL MAT $660.00 $1,824.25
1.10 MATERIALES Y EQUIPOS MATERIAL INSTALADO $348.41 COSTO DE MAT. $660.00
1.11 Sensor LUC-M10 1 c/u $ - $ 100.00 $100.00 $0.00 $0.00 $0.00 $120.00 $150.00 $150.00
1.12 Sensor de temperatura 1 c/u $0.00 $ 90.00 $90.00 $0.00 $0.00 $0.00 $108.00 $135.00 $135.00
1.13 Display DA-5 1 c/u $0.00 $ 250.00 $250.00 $0.00 $0.00 $0.00 $300.00 $375.00 $375.00
1.14 Contactor para controlar electro valvulas 3 c/u $0.00 $ 35.00 $105.00 $0.00 $0.00 $0.00 $42.00 $52.50 $157.50
1.15 Zelio logic 1 c/u $0.00 $ 125.00 $125.00 $0.00 $0.00 $0.00 $150.00 $187.50 $187.50
1.16 Caja para instalar contactores 1 c/u $0.00 $ 75.00 $75.00 $0.00 $0.00 $0.00 $90.00 $112.50 $112.50
1.17 Transformador de control 24 Vdc 1 c/u $0.00 $ 40.00 $40.00 $0.00 $0.00 $0.00 $48.00 $60.00 $60.00
1.18 Manetas, Luz Piloto, riel din, borneras 1 sg $0.00 $ 45.00 $45.00 $0.00 $0.00 $0.00 $54.00 $67.50 $67.50
1.19 Tsj 4x20 25 ml $0.00 $ 0.60 $15.00 $0.00 $0.00 $0.00 $0.72 $0.90 $22.50
1.20 Canalizado de cable de control 20 ml $3.50 $70.00 $4.38 $6.26 $125.20 $0.00 $0.00 $0.00
1.21 Termopozo 1 sg $125.00 $125.00 $156.25 $223.21 $223.21 $0.00 $0.00 $0.00
SUB-TOTALES COSTO TOTAL DIRECTO $1,496.88 TOTAL MANO DE OBRA $1,164.25 TOTAL MATERIALES $660.00 $1,824.25
Mano de obra Directa $651.98 Materiales Directo $440.00 $1,216.17
GRAN TOTAL PRECIO DE VENTA $1,824.25 Diferencia $512.27 Diferencia $220.00 $608.08
IVA 13% $237.15 Ganancia $279.42 Ganancia $110.00 $0.00
Precio con IVA $2,061.40 43% 25%
GANANCIA $389.42 .
PROYECTO:
CLIENTE: ARSAL
LUGAR: SAN SALVADOR
FECHA:
PRESENTA: PROYECT DE EL SALVADOR
15,962.19