Está en la página 1de 6

Optimized design and maintenance for Low Voltage MCCs.

How to improve the performance of a Low Voltage Motor Control Centre.

Hans Meulenbroek Peter Freeman André Muileboom Jan Verstraten


Eaton Industries Shell Global Solutions Exxon Mobil Dow
Hengelo Rijswijk Rotterdam Terneuzen
The Netherlands The Netherlands The Netherlands The Netherlands

Abstract – In this paper the authors share their views on


which best practices in design, operation and
maintenance provide the optimum solution to maintaining
the performance of low voltage (LV) Motor Control
Centres (MCCs).

Aspects to be covered during design, operation and


maintenance window are:
A. Causes of MCC failures
B. Prevention of MCC failures
C. Maintenance strategies
D. Life expectation and Life extension
E. LV MCC specifications
F. Safety

Index Terms — LV Motor Control Centre.

Figure 1 : typical single line: MV switchboard 11kV / transformers / LV


I. INTRODUCTION swithchboard 415V / LV MCCs

Motor Control Centres are used for control of motors


and are in use for more than 50 years. For the LV Motors in the process industries are, in most cases,
Petrochemical industries most customers require MCCs three-phase induction motors. Each motor requires a
with a design life beyond 25 years. In practice customers motor starter.
are using MCCs until system parts become obsolete and
servicing is impossible. The motor starters are grouped in a LV MCC. The MCC
interfaces with the operators (signal lamps, meters),
During service life of an LV MCC, users are confronted interfaces with the process control equipment (for
with initial erection, commissioning, modifications, failures, automated process control) and offers a safe environment
maintenance, changes to operating windows and finally to personnel and equipment in case of abnormal
obsolescence of the LV MCC. conditions (faults).
Obsolescence is usually the trigger for replacement of
the old LV MCC and the specification of the new LV MCC.

Application of a proper maintenance and operation


program will result in a safe and cost effective use of the
LV MCC. In addition, a robust design is key enabler to
achieving a higher level of safety and reliability.

Figure 1 shows a typical HV/LV single line with MCCs


that are fed from a LV Switchboard. The LV MCC has an
incoming circuit breaker or switch disconnector, outgoing
feeders and motor starters.

The choice for the type of incomer may depend on the


size of the MCC and the requirements regarding Figure 2 : sub-station with LV MCCs
containment in case of incidents with internal arcing. The
policy should be chosen in favor of the lowest let through
energy with regard to safety of operating personnel.
II. POSSIBLE CAUSES OF MCC FAILURES III. HOW TO PREVENT MCC FAILURES

Most MCC failures occur after poor maintenance or The basic principles to avoid failures are the same ones
improper modifications. Fewer failures are due to original as you would apply to your car:
design or aging of the LV MCC.
1. Do it right first time.
Some examples of short-circuit failures (including Good quality lasts longer
internal arcing) during maintenance or when performing
2. Do not repair what is not broken
modifications:
Often a failure occurs when you leave the
1. Frequent racking in/out of starters and circuit garage
breakers 3. Do not touch what is working well
2. Poor workmanship Only replace when ageing is involved,
3. Modifications, not per design e.g. tyres, oil (only about 14% of failures
4. Poor commissioning relates to ageing).
5. Poor maintenance.
6. Operating outside design envelope These principles are included in the equipment
7. inadequate control of engineering changes strategies for LV MCCs to achieve high reliability,
availability and safety figures.
Ad 1. FREQUENT RACKING IN/OUT
To eliminate failures it is necessary to consider all
Starters and circuit breakers are designed for a limited phases of the MCC selection, installation and operation:
number of racking operations. Racking out for every 1. Selection of vendors
isolation can exceed this limit after a number of years 2. LV MCC specification
service. 3. Installation and commissioning
4. Personnel and training
Ad 2. POOR WORKMANSHIP
5. Ambient conditions and operating window
Loose connections, open or incorrectly closed covers 6. Preventive maintenance plan
(typically with missing screws/bolts) or worse 7. Management of change
unintentionally left parts or tools while re-commissioning 8. Repair standards
the switchgear.
Ad 1. SELECTION OF VENDORS
Ad 3. MODIFICATIONS NOT PER DESIGN
Vendors should be evaluated for the ability to meet the
Increases in load and/or increases of short circuit current. customer’s requirements. The selected vendors should
Changes in protective relay co-ordination. have at least successful track record in similar projects.
Typically this should include at least three recent
Ad 4. POOR COMMISSIONING examples.

Incorrect setting of protective relays. Ad 2. LV MCC SPECIFICATION

Ad 5. POOR MAINTENANCE The LV MCC specification should include the following


information:
Maintenance intervals are too long. Incorrect selection of • Short circuit rating
replacement components. • Arc flash prevention and arc flash containment
requirements (IEC-TR-61641 criteria 1-7)
Ad 6. INADEQUATE CONTROL OF ENGINEERING • Load flow conditions
CHANGES • Diversity factors
• Type 2 coordination for contactors
Overloads or number of starts exceeding design • Ambient conditions
capability.
• Type of MCC following IEC61439 (or equivalent),
including separation of compartments
• Number of times starters must be able to be
withdrawn
Maintenance tasks and design change procedures
should be adequate to avoid above mentioned failures. • Foreseen preventive maintenance interval
• Protection scheme,
• Ability to do on-line maintenance on starters
• Redundancy requirements
• Site or company specific requirements as IP
requirements, personnel competencies, locking-
interlocking, grounding facilities, minimum
maintenance intervals for the various components,
etc.
• Required Factory and Site Acceptance Tests.
Ad 3. INSTALLATION AND COMMISSIONING
IV. MAINTENANCE STRATEGIES
Ensure that installation is in line with vendor
requirements. Ad 6. MAINTENANCE
The installation contractor should be familiar with make
and type of the LV MCC. Visual inspections are a key element in the
Ensure that all penetrations are closed. Especially maintenance strategy. Often abnormalities can be
unused cable entries, as ingress of foreign object, sensed by simply looking, smelling, or touching (after
rodents, moisture etc. are known causes for MCC's proving dead). In addition there are quantitative
failures. measurements such as comparison of load current of
Ensure that all main protective relays are tested with starter against its nominal rating, examination of counters
primary injection. Primary injection checks current showing the number of operations and hot spots (IR
transformer orientation and all the wiring, which can be scans) in cable compartments.
missed if only secondary injection testing is carried out. A more detailed inspection should be performed every
When the equipment is in use tests of protective relays Turn Around (typical interval 4-6 years), where starters
using secondary injection will be sufficient as no changes require a visual inspection and stabs are greased. The
in the LV MCC wiring or CT connections are expected. visual inspection should include looking for signs of
Ensure that maintenance personnel are involved during overheating, cracks, dust, condensation and similar
the installation works. Maximum benefit is gained if they abnormalities. The starter isolator (if fitted) is a safety item
are present during commissioning, ideally assisting the and should also be checked for correct operation.
commissioning engineer so they are involved and get an As the incoming circuit breakers or switches are
in depth understanding of the equipment. generally only accessible during Turn Arounds, an
For future reference and bench marking the test reports inspection of their mechanical parts is recommended.
should be available for maintenance personnel and site Every 10-12 years a check on busbar and cable
engineering. connections should be performed, e.g. by checking
torques. Checking torques more frequently will overstress
the connections and will introduce potential failures. An
alternative is low ohmic impedance testing of the busbar
systems.
Thermo-graphics can be a valuable tool to address hot
spots in a LV MCC. Undoubtedly valid for cable
compartments, where easy access helps to make a
proper inspection. Opening of live starters or feeders
requires safety precautions.

The majority of components do not fail by aging.


Components fail by overload (overheating), poor
workmanship at installation and repairs. Maintenance will
not avoid failures when the equipment is operating
outside its operating envelope or if the failures are caused
Figure 3 : MCC commissioning by poor workmanship.
Some components, such as air circuit breakers, require
Ad 4. PERSONNEL AND TRAINING a regular greasing of mechanical parts. Current thinking is
that the best lubricant material is fluorosilicone. Tests are
Maintenance personnel should be involved in an early ongoing to prove these greases can be effective for up to
stage of the project. This will achieve a proper 15 years. Until the evidence is available, it is sensible to
understanding of the capabilities and limitations of the LV adopt a cautious approach to re-greasing intervals,
MCC (see also Ad 3). especially for heavily loaded breakers.
A maintenance plan should be available and As failures of protective relays are not apparent during
electricians should be trained in the operation and normal operation, these devices should be tested every 5-
maintenance of the LV MCC. 10 years. Except where used to protect Exe motors,
conventional thermal overload relays of starters do not
Ad 5. AMBIENT CONDITIONS AND OPERATING require testing, as the probability and the consequence of
WINDOW failure are normally low. However verification that the
overload settings are still correct for the motor full load
Ambient conditions shall comply with equipment current should be carried out. It is not unknown for these
specifications. Any change in ambient conditions should settings to be altered in service, especially if there are
be covered by management of change procedure. problems starting a motor due to the thermal device
The operating window sets: tripping.
1. The minimum and maximum load of a LV Contactors should only need inspecting when the duty
MCC. requires frequent starting. In many instances it is more
2. The diversity factor of the LV MCC and panels cost effective in such applications to replace contactors
3. Minimum and maximum ambient before failure rather than wait until an actual failure
temperatures, humidity conditions. occurs.
Again any changes in operating window should be
covered by management of change procedure. Capturing the history of maintenance, modifications and
repair can be essential in problem solving. The bench
mark should be the commissioning reports (FAT and such a system could be useful in identifying those drives
SAT). which are under the greatest stress from loading or
numbers of operations, hence those which deserve closer
Ad 7. MANAGEMENT OF CHANGE attention during Turn Around inspections.
Although it is outside the scope of this article, there are
A management of change procedure is essential for a other areas where intelligence can be made to work
reliable and safe operation of the LV MCC. harder by including monitoring of the motor as well as the
Any replacement which is not "like for like" should be starter.
subject to an engineering assessment. There are many A system combining both switchgear and motor
examples where even minor changes led to component monitoring with reliable indications would be a great step
failure or a failure to operate as intended. forward in allowing targeted and condition based
Any change in load should be reviewed as to whether maintenance rather than being mainly time based.
the change still fits within the operating window of the LV Currently such capabilities are only available from
MCC. If the knowledge to make this assessment is not limited number of vendors. Users should encourage their
available at site, then the original manufacturer should be preferred vendors to consider how they can apply
consulted to confirm loading will still be acceptable leverage from the presence of intelligence in the
Note that changes can also be procedural changes or a compartment to aid early identification of developing faults
change to the preventive maintenance interval. Both so there is a competitive market for this type of
should fall under the management of change process. technology.

Ad 8. REPAIR STANDARDS V. LIFE EXPECTATION AND LIFE EXTENSION

Repairs or modifications should only be done by skilled An MCC reaches its end of life when spare parts are
personnel, usually from the manufacturer. not available and servicing is either impossible or
Modifications should follow the site management of prohibitively expensive. Typically it is when the mean time
change procedure. to repair becomes unacceptably long that action is forced
Prior to a repair the cause of failure should be upon the user.
addressed. The repair/modification should avoid a re- Provided that this condition is recognized, the low
occurrence of the failure. A root cause analysis of a failure failure rate normally experienced with LV MCC’s allows
might highlight the need to make multiple modifications sufficient time for alternatives for switches, circuit
not only on the directly affected LV MCC but also similar breakers, contactors and protective devices to be
switchgear elsewhere on the site. identified. However if attention is not paid to the
availability of spares, then it is possible to be caught out
and suffer extended outages or loss of service from a
FUTURE DEVELOPMENTS compartment.
With proper maintenance the copper, cabinets and
The introduction of intelligent motor protection relays insulation materials should remain in good condition and
offers the possibility of providing additional on-line do not suffer from age related defect mechanisms.
monitoring of the status of starters through trending However this statement is subject to caveats regarding
temperature rises and giving an alarm when these exceed heat and environment. Extended operation at or close to
expected values. Although an absolute temperature value the nominal rating of equipment will mean that the
may be used as an alarm, this assumes the starter is fully equipment will run “hot” and insulation may well start to
loaded. To pick up deterioration in more lightly loaded degrade once the design lifetime is exceeded. Similarly a
starters it would be necessary for an alarm to be raised simple mechanism such as rust due to extended
when temperature exceeds the normal steady state value, operation in a high humidity environment can fatally
which may well be below the maximum permitted weaken parts of the MCC structure forcing its
temperature in a lightly loaded cubicle. Any such system replacement.
should be capable of being set up to detect such changes As long as the function of the MCC does not change
as well as if the temperature exceeds the maximum significantly and the level of safety of the original design
permitted. is acceptable, the MCC can last at least for another
It is unrealistic to expect maintenance staff to be able to decade after the official obsolescence declaration.
closely monitor the performance of hundred’s of starters Also upgrades can be considered, as more modern
across a plant. So it is important that, in addition to the components tend to be smaller and functionality
measurements themselves, there is software capable of increased.
applying an intelligent filter to the output which only raises
alarms where they are real.
In fact it is the combination of the ability to measure
additional information about starter performance, together
with the ability to identify real problem areas, which will
make this technology really useful. In addition to heat or
voltage drops, other aspects such as number of times a
starter is withdrawn, numbers of starts / abnormal
numbers of starts per hour, number of contactor
operations or increasing levels of earth leakage current
before a trip value is reached, could be included in the
monitoring programme.
Even where alarm conditions have not been reached,
Upgrade examples, installed at various petrochemical included, a higher safety, reliability and availability level
sites are: will be achieved.

1. Arc flash detection and quenching. Detection


takes 2 milliseconds, following by a 35 VI. SAFETY
milliseconds of tripping the incoming or
upstream circuit breaker. Quenching of an arc Overall safety level will be improved by reducing the
with a quenching device takes 3 milliseconds. number of maintenance interventions. Maintenance
2. Very Early Smoke Detection Apparatus to detect intervals for starters are 5-6 years. Maintenance intervals
hot spots and fire in an early stage. This can be for circuit breakers can be 10-20 years.
detection in the LV MCC (per panel) or room Applying modern PPE for arc flash protection and
detection. protection against electric shock will further reduce risk.
3. Starter temperature monitoring Arc flash detection and quenching will reduce the
4. Replacement of fuses by circuit breakers when impact in case of an arc and reduce the arc flash energy
an isolating device is not available levels to low values. A reduction with 90% to 98% is
5. Microprocessor type relays replacing thermal easily to achieve.
overload relays. Early detection of evolving failures with VESDA
6. Insulation of cable connections systems and thermo-graphics will avoid risk full situations
7. IR windows for hot spot detection during maintenance activities.
Improving maintenance procedures and management
of change will be the final step in achieving a maximum
safety level.

VII. CONCLUSIONS

MCCs in the Petrochemical segment have to be safe


and reliable. They are an important part of the chain of
electrical supply from the supply source to the end
consumer.

The improvement of the performance of a MCC starts


when specifying the MCC.

Vendor selection is an important part of the pre-order


stage. End-customers and engineers have to invest time
Figure 4 : LV MCC Arc flash quenching device
and effort to satisfy themselves that the vendors asked to
quote will provide the right level of quality the application
calls for.
Also on the environmental side upgrades can be
considered, such as: Only when the specifications are in line with the actual
1. HVAC installation use of the equipment and only when the vendor has
2. Fire detection (VESDA) provided the end-customer with what he wants and
3. Water leakage prevention expects, can you start with a MCC that is fit for purpose
4. Insulating matting on floors and that will perform well under the predicted
5. PPE in substations, as arc flash suits, face circumstances.
shields, voltage rated gloves
6. Update documentation and drawings, as this is However it is the personnel that use, operate, maintain
often neglected. Include load flow, protective and modify the MCC that can have an even greater
relay coordination and arc flash energy impact on its performance.
calculations.
7. Training of electricians and engineers The users need to be trained, they need correct
working instructions and up-to-date as-built
These types of replacements or upgrades extends the documentation to be able to fulfill their role properly and to
life time of an MCC and increases the safety level to an minimise the chance of creating failures. Vendor’s
acceptable degree. In turn this avoids a costly designs should build in “passive safety measures” that
replacement of an MCC in the always too short Turn help to prevent failures to occur.
Around period.
An important part of the performance of a MCC is
However caution needs to be adopted in assuming that determined by the maintenance strategies. It will always
such works will achieve the same levels of safety as a be difficult to find the right balance between use for
modern LV MCC. If the original design does not include production and availability for maintenance.
the level of segregation, insulation and separation called
for in a modern board, it is unlikely that it can be retro- Good preparation for the maintenance works will help
fitted with such features cost effectively. to limit the time needed for performance improving
maintenance to a minimum.
Still, when above mentioned recommendations are
In the future we hope there will be improved status VIII. REFERENCES
information available from the boards themselves through
condition monitoring but there will always be a need to PCIC PAPER BA-27 : Imcs versus conventional mcc -
combine this with traditional approaches and skills. are the benefits realised in practice?

Vendors have to understand and plan in their


design/support that users will look for extended lifetimes IX. VITA
for LV MCC’s. This has significant implications for
retention of documentation and knowledge as well as the Authors:
need to provide upgrade paths for previous ranges of
equipment. Hans Meulenbroek, B.Sc

After a long life time (exceeding 1,5 – 2 times the Graduated in 1985 from the HTS Hilversum, the
nominal design life time) the MCC will reach the End of Netherlands with a bachelor degree (ing.) in Electrical
Lifetime condition. Now it all starts all over again with Engineering specialization Telecommunications. From
specifying the right replacement material. 1987 he worked for Rossmark Watertreatment as a
process automation engineer and later he managed the
process automation department. In 1997 he joint Eaton
Electric in the role of application engineer/SCADA
specialist. After changing positions to Project Manager
and Export Customer Support Manager his current
position is Product Manager being responsible for the
marketing of LV MCC and Motor Management Systems.

Peter Freeman C.Eng MIEE

Graduated from Imperial College London with bachelor


degree (Hons) in electrical engineering in 1975. Joined
Courtaulds Ltd and worked at various Viscose Rayon
plants until 1981. Join Shell in 1981 and has worked at
variety of refinery and E&P locations in various
engineering design and maintenance roles. Currently
working for Shell Global Solutions Electrical Engineering
section based in The Hague, with specific responsibilities
in areas of Switchgear and Maintenance/Commissioning.

Ing. André Muileboom

Graduated in 1977 from HTS Rotterdam, The


Netherlands with a bachelor degree (ing.) in Electrical
Power Engineering.
He joined DSBV, an architect and engineering office, as
electrical/instrument engineer. In 1979 working for De
Hoop-Groenpol as marine electrical engineer, specialized
in large LV switchgear and MCC's and ship electrical
power systems.
In 1985 he joined ExxonMobil Chemicals, where he
covered various positions as site electrical/instrument
engineer, project engineer and reliability engineer. Since
2005 he is working for Core Engineering, the ExxonMobil
Chemical global engineering department.

Jan Verstraten, B.Sc

Graduated from HTS Hilversum. Currently a Sr. electrical


specialist, he has worked for Dow Benelux BV in
Terneuzen since 1990, in various departments:
Maintenance central E&I, Maintenance Technology
Department and Powerplant. Since 2004 he has held the
post of Installation Responsible Person for Dow in the
Netherlands, Electrical SME for Dow in Benelux, UK &
Scandinavia and Electrical Safety and Reliability auditor.
Member of: NEC 623.

También podría gustarte