Documentos de Académico
Documentos de Profesional
Documentos de Cultura
INTRUDUCTION
In the case of options analysis, comparisons made between two possible options. The first, called Project A, and
the second, called Project B.
What we did in Project A was to find cost information on a specific team dedicated to the sale of the same, then
we plated the problem Where would be best to install the plant in Mexico or else where. For Project A was
decided to install it on the DF being preferred install it here.
Project B, it was decided that using the same equipment prices would undertake the project. However, here the
plant would be installed outside the City in Toluca, adding to this, the cost of transportation to that state that
Project A made the assumption that there was no cost for the home advantage.
PLANT LOCATION
EQUIPMENT LIST
CONCEPT
Biodigester Tank
Macerator Tank
Pre-Feeder Tank
Bomb
Conveyor of screw
Light Plant
Filters
Biogas Tank
LP Tank
screener
Press Filter
Rotatory Drier
Baler
Conveyor of Band
Pipeline Costs
PLANT DATA
• Function of the plant: Production of compost from urban organic solid residues
• Type of process: Aerobic degradation of organic waste to produce a product like humus, and fine particles
stabilized.
FINANCIAL ANALYSIS
The following analysis has a margin of error of + / - 30%
Project A
USD Inversion
Total
Raw Material capacity (inlet) Ground costs Egineering* Equipment** Construction***
tons/day
10 75000 27090 606300 438600 1146990
20 150000 28380 1006200 632100 1816680
40 300000 30960 1806000 1019100 3156060
60 450000 33540 2605800 1406100 4495440
80 650000 34830 3005700 1599600 5290130
160 1200000 43860 5805000 2954100 $10,002,960
General Values
CONCEPT VALUE
INVESTMENT COST -$10,002,960.00
ANNUAL SALES $ 5,064,241.00
ANNUAL COSTS -$2,779,038.00
NET EARNINGS $2,852,203.00
TIR 15%
VPN $252,184.32
TREMA 14%
Proyecto B
Inversion
USD Total
Raw Material capacity (inlet)
tons/day Ground costs Egineering* Equipment** Construction***
10 32300 27090 606300 438600 1104290
20 64500 28380 1006200 632100 1731180
40 128900 30960 1806000 1019100 2984960
60 193200 33540 2605800 1406100 4238640
80 257600 34830 3005700 1599600 4897730
160 515313 43860 5805000 2954100 9318273
rATE NPV
2% $7,210,894.43
TIR 3% $6,414,114.48
$8,000,000.00
4% $5,681,812.39
5% $5,008,028.66
$6,000,000.00 6% $4,387,426.82
$4,000,000.00 7% $3,815,221.28
8% $3,287,114.44
$2,000,000.00 9% $2,799,241.46
$0.00 10% $2,348,121.97
0% 5% 10% 15% 20% 11% $1,930,617.56
($2,000,000.00)
12% $1,543,894.48
13% $1,185,390.71
14% $852,786.95
TIR 17% 15% $543,981.05
VPN $257,065.28 16% $257,065.28
TREMA 16% 17% -$9,693.72
18% -$257,872.70
CONCEPT VALUE
INVESTMENT COST -$9,318,273.00
ANNUAL SALES $ 5,064,241.00
ANNUAL COSTS -$2,779,038.00
NET EARNINGS $2,285,203.00
Analyzing both proposals, Project VAN B offers May 1, so it would be the way to go, since the difference
is in the cost of the land while in the DF costs almost double that of Toluca and even adding
transportation costs, it is still much cheaper in Toluca.
Therefore, our proposal is a RSO treatment plant of the City for the production of bio-gas and compost located
in Toluca, State of Mexico, with an investment of $9, 318,273.00 dollars.