Activated Sludge Waste Water Treatment Calculations - S.I.

units

2. Aeration Tank Operation Calculations

Inputs Calculations

Prim. Effl. Flow Rate, Qo = 38,000 m3/d Recycle Activated


Sludge Flow Rate, Qr = 13,680 m3/d
Prim. Effl. BOD, So = 150 g/m3

Waste Activated Sludge


Prim. Effl. TSS, Xo = 200 g/m3 Flow Rate, Qw = 271 m3/d

Waste/recycle activated Aeration tank F:M = 0.33


sludge SS conc., Xw = 7,000 g/m3 (kg BOD/day/kg MLVSS)

Aeration tank vol., V = 11,400 m3

Aeration tank MLSS, X = 2000 g/m3

% volatile MLSS, %Vol = 75%

Sludge ret. time, SRT = 12 days

Equations used for Calculations:

Qr = Qo(X - Xo)/(Xw - X)

Qw = (V*X)/(SRT*Xw)

F:M = (So*Qo)/(%Vol*X*VMG)