ITEM DESCRIPCION UND METRADO PRECIO S/. PARCIAL S/.

22 AL 31 DE DIC 1 AL 31 DE ENE 1 AL 28 DE FEBR 1 AL 31 DE MAR 1 AL 30 DE ABR


Metrado S/. % Metrado S/. % Metrado S/. % Metrado S/. % Metrado S/. %
01 PAVIMENTACION
01.01 OBRAS PRELIMINARES
01.01.01 ALQUILER DE ALMACEN,GUARDIANIA Y RESIDENCIA mes 6.00 501.19 3,007.14 1.00 501.19 16.67 1.00 501.19 16.67 1.00 501.19 16.67 1.00 501.19 16.67 1.00 501.19 16.67
01.01.02 MOVILIZACION Y DESMOVIMLIZACION DE EQUIPOS Y MAQUINARIA glb 1.00 25750.83 25,750.83 0.40 10,300.33 40.00 0.10 2,575.08 10.00
01.01.03 CARTEL DE IDENTIFICACION DE OBRA 3.60 x 7.20 und 1.00 594.70 594.70 1.00 594.70 100.00
01.01.04 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA m2 30762.37 0.96 29,531.88 24,628.64 23,643.49 80.06
01.01.05 TRANQUERAS DE MADERA EN OBRA und 17.00 67.53 1,148.01 10.00 675.30 58.82 7.00 472.71 41.18
01.02 MOVIMIENTO DE TIERRAS
01.02.01 RETIRO DE ADOQUINADO EXISTENTE m2 350.68 4.53 1,588.58 350.68 1,588.58 100.00
01.02.02 CORTE DE TERRENO EN MATERIAL COMPACTOCON MAQUINARIA TRACTOR m3 18291.09 4.93 90,175.07 6,811.79 33,582.12 37.24 4199.32 20,702.65 22.96 3148.80 15,523.58 17.21
01.02.03 TRANSPORTE DE MATERIAL EXCEDENTE CON CARGUIO m3 22863.86 4.60 105,173.76 5249.16 24,146.14 22.96 3836.00 17,645.60 16.78
01.03 PAVIMENTOS
01.03.01 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 30,762.37 3.30 101,515.82 8,514.73 28,098.61 27.68 9131.98 30,135.53 29.69 3375.74 11,139.94 10.97 2205.73 7,278.91 7.17 2205.73 7,278.91 7.17
01.03.02 SUB-RASANTE E: 0.20 MTS m3 6152.47 35.71 219,704.70 448.47 16,014.86 7.29 1884.50 67,295.50 30.63 1822.53 65,082.55 29.62 441.15 15,753.47 7.17 441.15 15,753.47 7.17
01.03.03 SUB-BASE E: 0.20 MTS m3 6152.47 42.30 260,249.48 2333.27 98,697.32 37.92 1351.40 57,164.22 21.97 912.27 38,589.02 14.83 912.27 38,589.02 14.83
01.03.04 PAVIMENTO RIGIDO CONCRETO f'c = 210 kg/cm2 DOSIFICADO m3 6152.47 308.77 1,899,698.16 321.08 99,139.87 5.22 1068.42 329,896.04 17.37 1068.42 329,896.04 17.37
01.03.05 PAVIMENTO RIGIDO ENCOFRADO Y DESENCOFRADO m2 2,312.79 22.66 52,407.82 126.27 2,861.28 5.46 413.87 9,378.29 17.89 413.87 9,378.29 17.89
01.03.06 ACERO DE REFUERZO fy=4,200 kg/cm2 EN PAVIMENTO RIGIDO kg 14,709.42 3.00 44,128.26 651.78 1,955.34 4.43 2557.64 7,672.92 17.39 2557.64 7,672.92 17.39
01.03.07 JUNTA ASFALTICA EN PAVIMENTO RIGIDO m 11,563.97 1.59 18,386.71
02 VEREDAS
02.01 OBRAS PROVISIONALES
02.01.01 TRAZO Y REPLANTEO EN VEREDAS m2 6880.44 0.87 5,985.98 1,527.72 1,329.12 22.20 166.53 144.88 2.42 1021.65 888.84 14.85 1021.65 888.84 14.85
02.02 MOVIMIENTO DE TIERRAS
02.02.01 EXCAVACION SUPERFICIAL DE TERRENO PARA VEREDAS m3 1720.11 22.42 38,564.87 381.93 8,562.87 22.20 655.08 14,686.89 38.08 238.48 5,346.72 13.86 173.46 3,888.97 10.08 173.46 3,888.97 10.08
02.02.02 ELIMINACION Y TRANSPORTE DE MATERIAL EXCEDENTE CON CARGUIO m3 2150.14 4.60 9,890.64 477.41 2,196.09 22.20 818.85 3,766.71 38.08 298.10 1,371.26 13.86 259.71 1,194.67 12.08 259.71 1,194.67 12.08
02.02.03 RELLENO MANUAL CON MATERIAL DE PRESTAMO m3 688.04 54.50 37,498.18 212.89 11,602.51 30.94 16.65 907.43 2.42 182.93 9,969.69 26.59 182.93 9,969.69 26.59
02.02.04 NIVELADO Y COMPACTADO CON EQUIPO m2 6,880.44 2.62 18,026.75 1132.06 2,966.00 16.45 977.69 2,561.55 14.21 1950.14 5,109.37 28.34 1950.14 5,109.37 28.34
02.03 OBRAS DE CONCRETO SIMPLE
02.03.01 VEREDAS ENCOFRADO Y DESENCOFRADO m2 851.10 23.33 19,856.16 44.60 1,040.52 5.24 144.56 3,372.58 16.99 145.63 3,397.55 17.11 145.63 3,397.55 17.11
02.03.02 VEREDAS CONCRETO SIMPLE f'c= 175 kg/cm2 E-0.10 CM,DOSIFICADO,INCLUYE m3 688.04 282.23 194,185.53 58.05 16,383.45 8.44 133.34 37,632.55 19.38 142.63 40,254.46 20.73 142.63 40,254.46 20.73
ACABADOS
02.03.03 VEREDAS SARDINEL ENCOFRADO Y DESENCOFRADO m2 3,280.47 21.98 72,104.73 312.21 6,862.38 9.52 615.18 13,521.66 18.75 716.16 15,741.20 21.83 716.16 15,741.20 21.83
02.03.04 VEREDAS SARDINEL COCRETO SIMPLE f'c = 175 kg/cm2, DOSIFICADO, INCLUYE m3 246.03 282.10 69,405.06 23.42 6,606.78 9.52 46.14 13,016.09 18.75 53.71 15,151.59 21.83 53.71 15,151.59 21.83
ACABADOS
02.03.05 VEREDAS SARDINEL JUNTA ASFALTICA m 1171.60 5.93 6,947.59
04 SEÑALIZACION
04.01 PINTADO EN SARDINELES DE VEREDAS m 7,099.05 5.17 36,702.09
0402 PINTADO EN PAVIMENTOS m2 1,243.50 4.59 5,707.67
04.02 SEÑALIZACION VERTICAL und 6.00 261.63 1,569.78
06 VARIOS
06.01 NIVELACION DE BUZONES EN GENERAL und 57.00 174.36 9,938.52 6.00 1,046.16 10.53 10.00 1,743.60 17.54 10.00 1,743.60 17.54
06.02 LIMPIEZA FINAL DE OBRA m2 30762.37 1.64 50,450.29
07 FLETE TERRESTRE
07.01 FLETE TERRESTRE CIUDAD DE JULIACA- CRUCERO (LUGAR DE OBRA) glb 1.00 148562.93 148,562.93 0.01 1,485.63 1.00 0.01 1,485.63 1.00 0.03 4,456.89 3.00 0.16 23,770.07 16.00 0.16 23,770.07 16.00

COSTO DIRECTO 3,578,457.69 126,984.32 309,926.98 355,979.92 530,179.84 530,179.84


8% 286,276.62 10,158.75 24,794.16 28,478.39 42,414.39 42,414.39
GASTOS GENERALES
7% 250,492.04 8,888.90 21,694.89 24,918.59 37,112.59 37,112.59
UTILIDAD
SUB TOTAL 4,115,226.34 146,031.97 356,416.03 409,376.90 609,706.82 609,706.82
18% 740,740.74 26,285.75 64,154.89 73,687.84 109,747.23 109,747.23
IGV
3.5% 144,032.92 4,444.45 10,847.44 12,459.30 18,556.29 18,556.29
GASTOS DE SUPERVISION
TOTAL PORCENTAJE RESPECTO AL COSTO DIRECTO % 100.00 3.54% 8.63% 9.91% 14.76% 14.76%
PRESUPUESTO TOTAL 5,000,000.0 176,762.2 431,418.4 495,524.0 738,010.3 738,010.3