Está en la página 1de 65

Draft

797B Commissioning
Guidebook

Version 1
Completed:
May 2007

The controlled copy of this document can be found at:


https://catminer.cat.com/cda/layout?m=58121&x=7

All printed copies of this document are uncontrolled


AUTHOR’S FOREWORD
Between June 2006 and July 2007, Australian Caterpillar dealer Hastings-Deering
commissioned a second fleet of 797B's into their territory. This guidebook documents the
preparation and assembly process for the fleet of thirty-two (32) 797B's.

Planning and procurement for this project began at least ten months prior to
commencement of the first truck assembly. It was decided to document the lessons
learnt so that subsequent 797 sites may benefit accordingly.

This guidebook contains details of tooling, procedures and checklists that have been
developed to meet specific needs. They are included within for the reader’s
consideration. In each case, the local dealer took all required steps to risk assess, test
and certify where applicable. This ensured that all dealer, customer, mine specific, and
local statutory requirements have been met or exceeded. Any user of this guidebook
must also risk assess and take appropriate steps to ensure that all work practices
adopted are safe, efficient and allow adherence to any manufacturers guidelines.

Caterpillar offers this document for informational purposes only. The document contains
information that was developed by and helpful to one dealer, and is not meant to be an
all-inclusive guide for every dealer. Each dealer is, as always, responsible for all
aspects of their business, including all aspects that may impact the health and safety of
employees, visitors and customers, and all aspects of legal compliance. The information
contained in the document does not constitute legal advice. This document is also not a
contract, and nothing in this document is meant to alter or modify any agreement or
contract between Caterpillar and any of its dealers.

Special mention must be made of Hastings Deering Australia for their willingness to
share the information contained within. Thanks to the entire assembly crew and in
particular, we wish to recognize the following contributors to this book:
• John Allison, Site Implementation Manager
• Kevin Borg, Site Leading Hand
• Lyndon Morgan, Site Coordinator

Any specific enquiries regarding this book can be made to Tim Mansfield
tmansfield@cat.com

Hastings Deering Assembly Team in front of the first 797B delivered to the customer

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
1
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Introduction

This Guidebook is intended for those dealers who have received a customer order for
797B’s and are beginning the planning stages for on-site truck assembly and
commissioning.

The Guidebook documents four main phases, namely:


1. Assembly Pad & Resource Planning
2. Assembly Pad Preparation
3. 797B Assembly Process
4. 797B Commissioning Process

The guide aims to:


• Streamline dealer processes & reduce costs to the dealer for 797B assembly site
set-up,
• Improve efficiency of 797B on-site assembly & commissioning,
• Optimise 797B build quality (highest quality to the customer)
• Document Assembly Pad considerations (eg area required per truck, suggested
layout etc),
• Document resources required at site assembly pad, and
• Present some lessons that have been learnt by others

Included is a high-level guide to assist the user in knowing what questions to ask and
what things must be kept in mind. It is not meant to be an all-inclusive guide. It will
provide some information and also direct the reader to sites with more information.
Please contact the local district office for any additional information not covered in this
guidebook.

The Special Instruction for 797B Assembly (REHS1507) should be read in its
entirety by anyone planning for the assembly site and assembly process.

Please note that the Greenfield Guidebook will be a useful document to compliment this
guidebook for a greenfield mine site. Go to:
https://catminer.cat.com/cda/components/securedFile/displaySecuredFileServletJSP?file
Id=351949&languageId=7

In a Greenfield site, many of the preparation phases for the whole site will coincide with
the planning for the truck assembly and commissioning. Here they are considered as
two separate functions.

Generally, where you see a term in italics font, it will be defined further in the Glossary of
Terms.

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
2
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Table Of Contents

AUTHOR’S FOREWORD 1

797B COMMISSIONING PROJECT PROCESS MAP 5

1. ASSEMBLY PAD & RESOURCE PLANNING 6

1.1 DEFINE MANPOWER REQUIREMENTS 7


1.1.1 RECOMMENDED JOB FUNCTIONS 7
1.1.2 TOTAL 797 BUILD TIME 9
1.1.3 NUMBERS OF PERSONNEL 11
1.1.4 PLAN FOR ADDITIONAL LABOUR 12
1.2 DEFINE LIFTING PLAN 13
1.3 DEFINE ASSET REGISTER 15
1.4 DEFINE PERSONNEL TRAINING REQUIREMENTS 16
1.5 DEFINE CONTRACTOR REQUIREMENTS 17
1.6 DEFINE ASSEMBLY PAD PHYSICAL REQUIREMENTS 17
1.6.1 SIZE OF ASSEMBLY PAD & PAD LAYOUT 17
1.6.2 COMPACTION & LEVELING 21
1.7 ENSURING A SAFE WORK PLACE 22

2. PREPARATION FOR TRUCK & COMPONENT ARRIVALS 23

2.1 WORK ORDER STRUCTURE 24


2.1.1 CODING OF DEFECTS FOR WARRANTY CLAIMS: 24
2.2 MINE SPECIFICATION EXTRAS (CUSTOMER ADD-ONS) SUMMARY 24
2.3 PROCUREMENT 25
2.4 ON-SITE PARTS INVENTORY 25

3. 797B ASSEMBLY 26

3.1 STANDARD TRUCK ASSEMBLY 27


3.2 COMPONENT TRACKING DATABASE 28
3.3 ASSEMBLY CHECKLISTS 28
3.4 JOB SAFETY ANALYSIS 28
3.5 ADDITIONAL DEALER DEVELOPED TOOLING 28
3.5.1 FRONT STRUT LIFTING JIG 29
3.5.2 FENDER BRACING SCREW JACKS 30
3.5.3 CHASSIS LIFTING EYES 31

Caterpillar: Confidential Yellow


May 2007, Revision 1. The controlled copy of this document can be found at: 3
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
3.5.5 LHS HOIST PIN ACCESS STAND 34
3.5.6 CHASSIS RAIL ACCESS WORK PLATFORM 35

4 797B COMMISSIONING & CUSTOMER SIGN-OFF 36

4.1 CATERPILLAR COMMISSIONING TEAM 36


4.2 CATERPILLAR COMMISSIONING PROCEDURE 36
4.3 HASTINGS-DEERING COMMISSIONING PROCEDURE 36
4.4 CUSTOMER SIGN-OFF PROCESS 37

5 PROCESS CONTROL SYSTEM 37

APPENDIX 1A ASSEMBLY PAD PREPARATION PROJECT PLAN (EXAMPLE) 38


APPENDIX 1B 797B BASIC WEIGHTS AND DIMENSIONS – QUICK REFERENCE 39
APPENDIX 1C REGISTER OF ASSETS (EXAMPLE) 40
APPENDIX 1D REGISTER OF ASSETS (EXAMPLE) CONTINUED 41
APPENDIX 1E ASSEMBLY PAD LAYOUT (EXAMPLES) 42
APPENDIX 1F: TRUCK BUILD PROJECT PLAN 43
APPENDIX 1G EXAMPLE JOB SAFETY ANALYSIS (JSA) 44
APPENDIX 2A WORK ORDER SEGMENTATION (EXAMPLE) 45
APPENDIX 3A COMPONENT TRACKING DATABASE 47
APPENDIX 3B 797B ASSEMBLY CHECKLIST 48
APPENDIX 3C DEALER FRONT STRUT LIFTING JIG 52
APPENDIX 3D DEALER CHASSIS LIFTING EYES 53
APPENDIX 3E DEALER REAR WHEEL INSTALLATION STAND 54
APPENDIX 4A CATERPILLAR COMMISSIONING PROCEDURE 55
APPENDIX 4B 797B COMMISSIONING PROCEDURE (DEALER VERSION) 56
APPENDIX 4C 797B START-UP CHECK SHEET (DEALER EXAMPLE) 57
APPENDIX 4D 797B CAT COMMISSIONING CHECKLIST 58
APPENDIX 4E 797B DELIVERY CHECKLIST (DEALER EXAMPLE) 62
APPENDIX 5 PROCESS CONTROL SYSTEM 62

GLOSSARY OF TERMS 63

ADDITIONAL REFERENCES 64

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
4
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
797B COMMISSIONING PROJECT PROCESS MAP

The process map in Chart 1 depicts, at a very high-level, the preparation for and performing of
the 797B assembly and commissioning. The section depicted in yellow represents the scope of
this guidebook.

Chart 1: Top Level Process Map showing the scope of this guidebook
(depicted in the yellow shaded area)

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
5
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
1. ASSEMBLY PAD & RESOURCE PLANNING

Chart 2 below provides some of the activities and decisions that need to be considered in
Phase 1 – Assembly Pad & Resource Planning

Phase 1: Assembly Pad & Resource Planning

Customer Dealer Sales Dept Dealer Operations Dept Dealer Engineering Dept Cat Sales Support

Form Dealer implementation team for


797 project. It is recommended that a
Customer order is
797 Implementation Manager be
received for 797B fleet
appointed as early as possible

Cat Product Specialist and


Do we have the
Mining Rep create 797 Build
required customer
No Yes schedule with serial numbers
delivery dates?
and estimated build dates
Desired 797
delivery dates are
submitted by
customer

Is Build Schedule Schedule is reviewed with


accepted by Dlr & factory & dealer until
Yes No consensus reached
Customer?
between all 3 parties

Customer (with Dealer Marketing Dealer Engineering Dept designs,


Dept) works with to determine Mine draws and risk assesses each of the
Spec (over and above Cat standard customer mine spec add-ons (or
build (eg fire suppression etc ….) sources this externally)
797 Delivery Schedule and
Mine Spec summary provided
to Dlr Op’s Dept
Summary of Mine Spec add-
ons created

Determine target 797B Assembly &


Commissioning timeline

Determine number of trucks planned to


be in-process (that is, being
assembled) at any given time

(X3)
(X1)Define (X2)
Define
Manpower Define
Capital
Requirem Lifting
Asset
ents Plan
register

(X5) Define
(X6) Define (X4)
Contractor
Assembly Define
requirements
Pad size, training
and
layout and requireme
tendering
specs nts
process

Chart 2: Basic Process Chart for Assembly Pad & Resource Planning

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
6
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
1.1 DEFINE MANPOWER REQUIREMENTS

1.1.1 Recommended Job Functions

Chart 3 depicts a typical 797B Implementation Team structure (the structure below
depicts Hastings Deering’s team at the Assembly Pad).
The number of personnel will vary depending upon the number of trucks expected on the
assembly sites at any given time. This structure was based on a schedule of 3 trucks in
process on the Assembly Pad at any given time. This was also based upon a single shift
per day.

Chart 3: Implementation Team Structure example


(Based upon 3 trucks in process on the Assembly Pad)

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
7
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Draft

Table 1 below includes a very basic job description for these roles. The dealer should
prepare full and detailed job description for all on-site personnel.

Job Title Primary Functions


Implementation Manager * Provide conduit between all involved parties,
(Service Dept, Sales Depart, Transport Depart,
Customer etc),
* Plan and schedule assemblies as per delivery
plan and contract terms,
* Provide leadership & direction,
* Ensure all dealership and site specific polices and
procedures are adhered to
Site Leading Hand * Provide leadership & direction to workforce.
* Schedule labour requirements,
* Ensure all dealership and site specific polices and
procedures are adhered to
Site Coordinator * Schedule and order all parts required for project
assembly,
* Ensure all registers are kept up to date,
* Ensure all services and supplies are kept in order,
* Ensure all dealership and site specific polices and
procedures are adhered to,
* Provide leadership & direction to workforce
Team Leaders * Provide leadership & direction to work team,
* Ensure all dealership and site specific polices and
procedures are adhered to,
* Carry out trade tasks as required
Boiler Makers
Auto Electricians * Ensure all dealership and site specific polices and
Painter procedures are adhered to,
Fitters * Carry out trade tasks as required
(Employees & subcontractors)

Table 1: Implementation Team Major Job Functions

It would also be recommended to have a specific role to ensure that VIMS payload, RAC
(Road Analysis Control), TKPH Monitor and other software systems are set in
accordance with customer’s wishes and site-specific criteria (such as target payload, tire
TKPH limits, etc). In the eyes of the customer, small problems in these systems after
delivery can cloud all of the positives in the assembly & commissioning process.
Further, ensure there are resources in place to document product defects, parts shortages
etc and report these back to Caterpillar via the appropriate channels.
1.1.2 Total 797 Build Time

Determination of the target build times for each truck, together with the factory shipment
schedule will be used to assess the number of trucks that will be on the Assembly Pad at
any given time. In turn, this allows us to move a step closer to defining site personnel
requirements.

The assembly times indicated below are for the Standard Cat truck as per Special
Instruction REHS-1507. As the mine spec extras differ from site to site, these have been
omitted to allow for easier comparison and benchmarking.

The histogram and box plot in Chart 4 are for representative purposes only. They show
that the first three trucks took a longer time to assemble.
However, as the team gained hands-on experience, processes were embedded, and the
team documented risk assessments during task completions on truck #1, the Cat standard
truck build time settled to an average of around 900 man-hours. This is based upon the
team structure as depicted in Chart 3 and the Cat standard truck is as per REHS-1507.

Chart 4: 797B assembly time analysis depicting


the longer build times for trucks 1,2 & 3

The longer build times on the first 2-3 trucks prompted us to review the potential causes
of the additional time. The main causes may be seemingly obvious and are also captured
in the fishbone analysis in Chart 5.

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
9
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Machine Man
Team was transferred to site JIT for project

No upfront training (not deemed nesessary)


New model in territory
First time in assembly team
for some members No one from GYRV 797 assmebly team was
part of Dawson build team

Ultra-Class size All first time to assemble 797 Mother Nature


OHT
Contractor familiarisation
with tasks
Rain

Determining extras required Individuals haven’t worked


(eg additional sheathing on hoses, together before Heat
relocate hose brackets

Build time for first two


trucks is excessive
Checklists developed during first truck build
No one stop procedural
documentation Build time accuracy.
New tooling
Are hours on correct
Not familiar with all tools W ork order segments?
Body rework
Task risk assessments.
(+10 days for truck 2)
Documenting & verifying JSA’s
Measure
Cat requested Adjustments
Had not yet refined the
REHS1507 process as performed on-site.
Site has progressively modified their process

Material Method

Chart 5: Potential Cause for Additional Assembly Time on first trucks

The potential causes in red are perceived to have had the greatest impact.

With the benefit of hindsight, the two items that the site team believe would have had the
biggest impact on reducing the build times of the first two trucks are:
• Ideally at least two team members (possibly the Team Leaders) would have
visited another site to witness first hand the assembly of at least two 797’s.
• All of the documentation, checklists and data collection tools would have been
formally pulled together in a central location and fully understood by all team
members before the first truck began. In reality, some of this information
awareness and process flow evolved during the first few builds

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
10
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
1.1.3 Numbers of Personnel

It is suggested here that the total number of personnel required at the Assembly Pad will
be dependant upon the number of trucks in process (that is, being built) at any given time.
Refer back to Chart 2

This will be a function of the inter-arrival times of consecutive trucks delivered to site
from the wharf, and the planned Assembly Time for each truck.

Managing the entire project such that there is a relatively constant amount of work (i.e.,
number of trucks) on the assembly pad at any given time will make manpower planning
and rostering far simpler (and lessen the potential burden of having to source additional
labour from the local branch Field Service Department)

Following the process indicated in Chart 2 should produce a build plan something like
shown in Chart 6 below. A different and more detailed version of this can be seen in
Appendix 1F.

Chart 6: Possible Build Plan for 797B Fleet of 20 trucks

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
11
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Viewing the above project plan allows for an informed decision on how many trucks will
or should be in process at any given time on the Assembly Pad.
In this example, we see that at the snapshot of time denoted by ‘A’ there would be 5
chassis’ on the assembly pad, with only a very small overlap between the planned arrival
of Truck 5 and the expected delivery of Truck 1 to the customer.
Likewise, at the time snapshot denoted by ‘B’, there would be 6 chassis’ on site, again
with a few instances of small overlap.
Conversely, at the moments of time denoted by the green arrows ( ), there is expected
to be only 2 or 3 chassis’ on the assembly pad.
It then becomes a dealership decision on the number of resources to commit. That is, do
we set-up human resources, tooling, assembly pad space and so on to cater for assembly
of six (6) trucks as per point ‘B”. In this case, we’d suggest not.
In this actual scenario, the site team elected to set-up for 3 trucks in-assembly-process at
any one time (effectively three build crews managed by the Site Leading Hand, Site
Coordinator and Implementation Manager team – refer to Chart 3). The assembly pad
site did have the luxury of sufficient space for storage of additional chassis’.
Customer delivery expectation and potential late delivery penalties may also influence
the strategy adopted here.

1.1.4 Plan for Additional Labour

For any sizable 797 fleets, there will almost certainly be times when additional labour is
needed during the truck build phase. This may be caused by:
- Additional rework required for a given truck or body
- The team is falling behind the delivery schedule to the customer
- Permanent crew go on annual leave or are on sick-leave

A management plan should be in place with the Field Service Leading hands at the
nearby branches for the supply of additional labour as required.

1.1.5 Create a Project Plan

Development of a detailed project plan as early as possible is critical.

Here we are referring specifically to the project plan for the Assembly Pad & Resource

Planning stage (that is, Section 1 of this guidebook).

Appendix 1A includes an actual project plan that you may wish to use. The project plan

may take on many different and effective formats – this is just one example that already

exists for your use.

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at: 12

https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Draft

1.2 DEFINE LIFTING PLAN

The Lifting Plan adopted for the chassis’, major components and bodies will impact upon
the optimal assembly pad size and layout.

Template 1: Lifting Plan in action

The dealer’s preferred lifting contractor will probably handle this aspect at most
Australian sites.
In this scenario, it is advisable to discuss & provide the REHS1507 Special Instruction
for 797B assembly as well as the build plans to the selected lifting contractor.
They should then be able to create a suitable plan for material handling. The type of
cranes and other lifting gear to be used will also impact upon the required space to be
allocated between chassis’ on the assembly pad. REHS1507 provides a lot of good
information for developing the lift plan.
In the case of this site, the strategy for the commissioning of 32 x 797B’s was based upon
3 units in process at any one time; the lifting contractor’s crew consisted of:
• 1 x Supervisor
• 2 x Crane Drivers
• 1 x Rigger
(Refer also to Chart 3)

For easy reference, Appendix 1B shows some basic 797B component dimensions and
weights.

Below are some photos depicting the execution of the assembly pad lifting plan.
Template 2: Transmission Installation

Template 3: Body Installation using two cranes for easy body alignment

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
14
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
1.3 DEFINE ASSET REGISTER

The Asset Register for any given operation may differ for many reasons. This guidebook
does not intend to provide a definitive list of assets, nor identify mandatory specifications
for any of the individual assets. Rather, we aim to provide a sample asset register that
may be used as a checklist for any dealer to add to, or alter to suit.
The Asset Registers for the project site assembly pad are included in Appendices 1C and
1D
Refer to Special Instruction REHS1507 as it includes information on tooling and other
items that will be required for the truck assembly.

Template 5: ‘Svetruck’ forklift and tyre handler


used at the assembly pad

Make sure to visit this Assembly & Commissioning references page:


https://catminerpreview.cat.com/cda/layout?m=19574&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
15
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
1.4 DEFINE PERSONNEL TRAINING REQUIREMENTS

Training requirements for personnel in the dealer’s 797 Implementation Team will differ

between dealers, between Australian States (and obviously even more so between other

countries).

The list below is intended to provide a starting point for consideration.

At this particular Queensland (Australia) coalmine site, the following training

requirements existed:

Training Implem Leading Site Assembly Contractors


entation Hand & Coordinator Technicians
Manager Team
Leaders
Trade Qualified(1) • • •
Statutory training (2) • • • • •
Passport (Mine • • • • •
Specific) (3)
Mine Specific • • • • •
Inductions (4)
Black coal • • •
competencies
(licenses for plant) (5)
S1, S2, S3 • • •
Supervisory skill
certification (6)
797B specific
training (eg Service Optional
Training) (7)

Table 2: On-Site Training Requirements

(1) Trade Qualified: This refers to the trade qualifications specific to the job being
performed. For example: Auto Electrician qualifications, diesel fitter qualifications etc.
(2) Statutory training: Australian State and Federal governments set certain mandatory
training requirements. These will need to be investigated in each territory where 797’s
are being assembled.
(3) Passport (Generic Mine Induction): The mine owners / operators / State Government
departments have their own specific training requirements before anyone is entitled to
work on site. Successful completion of this training results in a Mine Passport being
issued to that employee.
(4) Mine Specific Induction: The site also has their own mine specific Induction program.

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
16
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
(5) Black coal competencies (licenses for plant): The Queensland Mining Industry
requires that employees successfully complete the Black Coal Competencies before
operating any heavy mobile plant on a coal mine site.
(6) S1, S2, S3– Supervisory skill certification: This course was completed through the
local Queensland Department of TAFE in order to enhance site personnel supervisory
skills (mandatory for supervisors).
(7) 797B specific training: This refers to any formal 797 specific training, whether it be
service training or otherwise.

1.5 DEFINE CONTRACTOR REQUIREMENTS

It is likely that site will utilize the services of local contractors during the set-up,
assembly and commissioning phases of the project. Table 2 above indicates the
minimum training requirements for contractors to work on this site. Hastings-Deering’s
SMP also outlines the safety requirements for contractors on-site. The mine will also
have their site-specific requirements. These must be assessed in their entirety at any site.

At this project site, contractor services included (but were not necessarily limited to):
• Contractors for site set-up (eg electricians, plumbers, fencing contractors etc),
• For fitting Fire Suppression mine spec extra,
• For conducting Sound Tests on the assembled 797B’s,
• Painting,
• Installation and testing of the Minestar (or similar system).

1.6 DEFINE ASSEMBLY PAD PHYSICAL REQUIREMENTS

Here we talk briefly about area required, site layout and compaction of the assembly area.
If suitable space at the assembly pad is limited, then determination of the space required
becomes a critical step. In most on-site assembly pads, space will probably be abundant
and therefore not of great concern.

1.6.1 Size of Assembly Pad & Pad Layout

The size of the pad may be influenced by each of the following:


- Number of trucks on the pad at any given time. This was discussed above in
Section 1.1.3.
- Storage area for any chassis awaiting assembly
- Area dedicated for Parts Layout (note that the assembly Special Instruction
REHS1507 includes a recommended parts layout plan)
- Lifting Plan (as discussed in Section 1.2) will influence the amount of area
required around the chassis and around component storage areas. This may

Caterpillar: Confidential Yellow


May 2007, Revision 1. The controlled copy of this document can be found at: 17
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
vary depending upon the size of cranes, turn circles of forklifts to be used and
so on). The lifting contractor should be able to advise on this
- The chosen pad layout
- Size of buildings and facilities for the crew
- Available space

Appendix 1E includes a basic plan of the assembly pad layout with overall dimensions
included. The photo below shows the layout of the buildings and assembly areas during
the assembly of the first two 797B’s. The site was not limited for space so this allowed
ample area for component storage and for additional chassis’ that arrived later in the
build sequence (refer again to Charts 2 and 6).

Additional storage containers were Assembly Pad Site office, crib


later placed nearer the site offices. Covered area for electrical room & toilets
Refer photo on front cover. work, cab fit-out etc

Bunded area for storage of


No flood lighting was fluids
required as all work was
conducted during the day

Template 6: Initial Assembly Pad Layout depicting the first two trucks in process

In hindsight, if site were to make 3 changes to the assembly site set up, they would have
been:
• Underground services or specific service points. This would have reduced the
need to run cables, electric and air lines over the pad surface. This would
improve safety and also have eliminated the time involved in laying out lines,
marking them with witch’s hats and then packing up the lines afterwards.
• Concrete pads for assembly, as opposed to the compacted dirt and gravel surface.
• Provided shade for employees (temperatures are consistently 35+ degrees C in
summer time, with high levels of UV.)

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
18
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Template 7 below shows the initial orientation of chassis’ on the build pad used for the
first few trucks being assembled. For purposes of lift plan the orientation of chassis’
were changed to be at a 45-degree angle to the assembly pad boundary fences (refer to
Template 8). Consultation with your lifting contractors should allow you to arrive at the
best chassis orientation for your site and material handling gear.

Template 7: Original orientation of trucks on the Assembly Pad

Chassis were initially placed parallel to the boundary fences

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
19
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Template 8: Revised orientation of chassis on Assembly Pad

Orientation was then changed so that chassis are all

at 45-degrees to the boundary fences

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
20
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
1.6.2 Compaction & Leveling

Due to the size and weight of components, material handling equipment, and the

completed 797 trucks, the working surface of the Assembly Pad needs to be compact,

stable and able to reasonably withstand adverse weather conditions. For sites that will

not have concrete working surfaces, there are many different variables (climate, soil type,

crane type etc) that may affect the desirable compaction at a given site. We do not intend

to provide a recommendation here, just an example.

Rather, included below are the soil type and compaction rates that have served well for

Hastings-Deering.

The site’s Mine Planning Department should be able to provide adequate information on

the soil type and advise upon the compaction rates required. The dealer should have

discussed with the customer as to who is responsible for leveling and soil compaction

works.

Assembly Pad site:

A soil testing and building engineering firm was consulted to perform Dynamic Cone

Penetrometer (DCP) testing on the pad. Using the information provided by site on the

weights of components and machines, the report deemed that “the erection pads would be

subjected to a variety of loading configurations requiring maximum pad reaction of

482kPa (allowable bearing capacity). A lesser strength area surrounding the main work

area is required to provide 360 kPa allowable bearing capacity”.

Refer to Appendix 1E for further details of the general site arrangement.

The compacted surface performed very well for the entire build sequence. Conditions at

site are predominantly dry all year round, though heavy rains are experienced

sporadically. The surface handled the water well and tended not to deform. Given that

the work surface was compacted earth and gravel, it held up as well as could have been

expected. Nonetheless, as was noted earlier, the site team believes that a concrete build

surface would have been ideal and justifiable given the 32 truck fleet size. Obviously,

the dealer management would have required a capital expenditure justification for

installing concrete pads from the start of the project. Together with providing an ideal

working surface, concrete assembly areas would have benefited Contamination Control

(CC) procedures also.

Reference: For those who wish to conduct more research into this area, you may find the
following document useful:
QECB9729: Caterpillar Soil and Asphalt Compaction Manual

Caterpillar: Confidential Yellow


May 2007, Revision 1. The controlled copy of this document can be found at: 21
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
1.7 ENSURING A SAFE WORK PLACE

There is nothing more important on the assembly pad than the safety of the employees
and visitors.
Hastings Deering employed the services of an external consulting firm to document a
comprehensive Safety Management Plan (SMP). The SMP is not provided within this
document but shown below is the Table of Contents from the SMP.
1.0 Introduction
1.1 Back ground to Hasting Deering
1.1.2 Milestones
1.2 Site Description
1.3 Scope and Dimensions of Services Provided for this Project
1.4 Rules and Regulations
1.5 General Work Process
2.0 Occupational Health and Safety / Training
2.1 Trained, Safety Conscious Personnel
2.2 Selection, Placement and Training
2.3 Health and Safety Policy
2.4 Rehabilitation
2.5 Assessment of Sub-Contractors
2.6 Safety Disciplinary Procedures
3.0 Responsibilities
3.1 Organisational Structure
3.2 Employee Obligations
3.3 Site Senior Executive Obligations
4.0 Communications and Meetings
5.0 Safety Awareness
5.1 Personal Protective Equipment and Clothing
5.2 Control of Dangerous & Hazardous Substances
5.3 Environmental Controls
5.4 Job Safety Analysis (JSA)
5.5 Standard Operating Procedures and Work Instructions for Tasks
5.6 Fatal Risk Control Protocols
6.0 Design Control
7.0 Verification of OH&S Program

8.0 Reporting, Recording, Investigation & Analysis


8.1 Site Procedures, First Aid, Emergency Procedures and Road Rules
9.0 Evacuation & Emergency Planning
10.0 Control of Documents and Records
11.0 PLAN ACTION LIST
12.0 Risk Management Guide
13.0 Attachment List

An example Job Safety Analysis (JSA) is included in Appendix 1G.

As is documented in the SMP, the dealer shall also be aware of, and abide by any Safe
Operating Procedures (SOP’s) that the mine site has in place.

Refer also to Section 1.4 ‘Define Personnel Training Requirements’

Caterpillar: Confidential Yellow


May 2007, Revision 1. The controlled copy of this document can be found at: 22
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
2. PREPARATION FOR TRUCK & COMPONENT ARRIVALS

Phase 2 of this guidebook looks at preparation of the assembly area in advance of the first
chassis’ and components arriving at site. Chart 7 below is a top-level process map of
items that may need to be considered. As always, there may be many other ways of
achieving the same end results, so you should not feel bound by anything presented
within.

Phase 2: Assembly Pad Preparation

Customer Dealer Parts Dept Dealer Operations Dept Dealer Purchasing Dept Cat

Dealer Implementation team


receive full Mine Spec summary,
Dealer Parts plus Engineering drwaings for all
Inventory for Mine Spec add-ons (as previously This information was
Note: Customer & Dealer site are defined by the customer determined in Phase 1
will negotiate over who is finalised
responsible for co-ordinating
& paying for the schedule of
works required in order to
ready the Assembly Pad for
Work Order system
commencement of work. For
is established for
the purpose of this document
the pending
these functions have been Asset Register as
assembly and
designated as a dealer determined in
commissioning
function. Stage 1
process (refer to
Appendix 2A

Storage Systems for


parts are determined
(eg Racks, Cabinets,
Bins etc…).

Sections 1.1 – 1.6 in Phase 1, together


with other inputs determines:
Size of Parts Storage - Schedule of Works (Project Plan)
Dealer Purchasing Dept
building is determined. It is required to prepare the Assembly Pad
follow Dealer guidelines to
highly likely that this may be for 797B component delivery &
procure all approved Assets
shipping container(s) with assembly. An is provided in Appendix
as determined in Phase 1
cabinets and shelving within. 1A
- Assembly Pad design & layout. Refer
to Appendix 1E

Execute Project Plan of


Assembly Pad to
completion (refer to
Appendix 1A

797B components
ready for delivery
to site

797B Assembly
begins (Phase 3)

Chart 7: Basic Process Chart for

Phase 2: Preparation for Truck & Component Arrivals

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
23
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
2.1 WORK ORDER STRUCTURE

In the instance of Hastings-Deering, the work order administrative functions (as well as
warranty functions) were performed at the local dealer branch store. The assembly pad
fitters completed service sheets and provided these to the Site Leading Hand. These were
then sent on to the local dealer branch for processing.
Appendix 2A shows the Work Order structure used at the project site.

2.1.1 Coding of Defects for Warranty Claims:

Please consult with your dealer Warranty department and Decatur’s commissioning team
to verify the correct coding procedures for any warranty claims.

2.2 MINE SPECIFICATION EXTRAS (CUSTOMER ADD-ONS) SUMMARY

It can be seen in appendix 2A that Mine Spec extras amounted to ~80 segments on each

work order.

As such, it is critical that the tasks to be performed within each of these segments are well

defined, scoped and planned in advance of the first trucks arrival. This may incorporate:

• Customer agreement to the details of the Mine Spec extras plus a sign-off
procedure established with a customer representative
• Engineering Drawings
• Risk Assessments
• Contractor agreements
• Component research and procurement
• JSA (Job Safety Analysis) preparations
• Parts inventory planning and procurement
• Forewarning any engineering firms and suppliers of the quantity and required
dates for all mine extra components. Ensure that they have the planning
capability to cater for your site needs.

Template 9: Mine Spec Extra Engineering Drawings were


compiled into folders and kept in the Leading Hand Office.

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
24
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
2.3 PROCUREMENT

We saw earlier in section 1.1.5 and Appendix 1A an example of the resource project plan
used at the site. Section 1.3 and appendices 1C and 1D provided us with a Register of
Assets.
The procurement of all of these items is critically important to the success of the project
and for site’s ability to meet to delivery deadlines on the first trucks that arrive at site.
Plan well ahead to get quotations and understand lead times. Your dealership may have
set procurement guidelines that need to be considered.
Your site will almost certainly also rely on local engineering firms to fabricate some of
the mine spec extras as per the engineering drawings that have been developed and risk
assessed. Ensure that these engineering shops have adequate forewarning and planning
capability to handle the quantity of raw materials and engineering requirements.

2.4 ON-SITE PARTS INVENTORY

Almost all of the parts required for assembly of the standard Caterpillar spec truck will
arrive at site from the factory. Obviously consumables, PPE (Personal Protective
Equipment) and other required supplies will need to be held in the on–site inventory.
However, the bulk of the onsite inventory will be for the Mine Spec extras.

Template 10 below shows the on-site parts storage for the project:

Template 10: Onsite parts and inventory storage (this is one of two) containers

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
25
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
3. 797B ASSEMBLY

The 797B Field Assembly Special Instruction (REHS1507) is available through SIS
Windows subscription or SISWEB. Paper copies of the instructions can be ordered
through Media Logistics. Procedures and recommendations described in these special
instructions should be followed during assembling and commissioning of the products.

Most of the tools, supplies, equipment and materials required for assembly and
commissioning are listed in the Special Instruction. At the time of negotiations with the
customer, dealers need to be aware of additional cost factors, which may be incurred
during the assembling and commissioning process. If ignored, these cost factors may
negatively affect the bottom line. It is a dealer’s responsibility to evaluate which of the
following factors should be included into a deal:

Crane Rental Cost Lubricants, Oils, Grease and Coolant


Electricity & Lighting Cost Tire Handling
Air Conditioner Service Fire Suppression Installation
Lifting Cables, Slings, Chains Assembly Stands and Jigs
Manpower Transportation Cleaning Materials
Manpower Meal and Lodging Air Compressor
Security Consumables (rags, paint, lock-tite, etc.)
Communication Systems Paint Stripping Tools
Safety Articles Supervisory Staff

Make sure to visit this Assembly & Commissioning references page:


����������� �����������������������������������������������������������������������������������������������

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
26
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
3.1 STANDARD TRUCK ASSEMBLY

The Special Instruction REHS1507 should be read in its entirety by all involved in the
preparation for the assembly process.

Chart 5: 797B High Level Assembly Process

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
27
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Contamination Control (CC) procedures and practices are also paramount during the

assembly process, especially given that assembly is quite likely to take place in the open.

All precautions should be taken to avoid contaminant entry into machine components and

systems.

CatMiner provides some useful resources relative to Contamination Control. Go to:

https://catminer.cat.com/cda/layout?m=3590&x=7

Your local Caterpillar District Office should also be able to provide guidance relating to
CC practices.

3.2 COMPONENT TRACKING DATABASE

In order to manage the health and component life of a new 797 fleet, it is imperative to
have comprehensive component records. Appendix 3A includes an Excel file for
capturing vital component information.

3.3 ASSEMBLY CHECKLISTS

Appendix 3B includes an assembly checklist for use during the 797B Assembly process.

Appendix 4C includes the 797B Start-Up Checklist.

Further, REHS1507 acts as its own form of checklist.

3.4 JOB SAFETY ANALYSIS

Each dealership will also need to create their collection of JSA (Job Safety Analysis)
documents. These will be specific to local site regulations or statutory requirements,
however an example JSA is included in Appendix 1G.

3.5 ADDITIONAL DEALER DEVELOPED TOOLING

The purpose of this section is to show some of the additional tooling built by Hastings-
Deering. These are not essential for the purpose of 797B assembly, but like Hastings-
Deering, you may find them beneficial to the build process.

The dealer and lifting contractor developed the tools that are pictured below. These were
fabricated by site or by third party engineering firms and had the required load testing
and all necessary certifications applied. Any other dealers intending to build their own
specialist tooling should have it properly tested and certified in order to meet all
statutory, local, mine specific and dealer requirements. The tooling below has not been
tested by Caterpillar, nor is available through Caterpillar.

Caterpillar: Confidential Yellow


May 2007, Revision 1. The controlled copy of this document can be found at: 28
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
3.5.1 Front Strut Lifting Jig

This tool is used to install the front struts prior to the fenders being fitted onto the truck

Template 11: Dealer Front Strut Lifting Jig

Refer to Appendix 3C for the engineering print.

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
29
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
3.5.2 Fender Bracing Screw Jacks

These provide support to the fenders during the assembly phase, allowing easier
alignment of associated components. The screw jacks are used during the “Install the
149-3107 Fender Gp” stage of REHS1507. These screw jacks are commonly used in the
construction industry

Template 12: Dealer Fender Support Screw Jacks

Template 13: Dealer Fender Support Screw Jacks and Lift Plan in action

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
30
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
3.5.3 Chassis Lifting Eyes

The chassis lifting eyes were also built locally. Refer to Appendix 3C for the engineering
print.

This insert shows the Caterpillar lifting eyes


Template 14: Dealer Chassis Lifting Eyes in Use

The 797B is shipped with lifting eyes (see insert above) in the pictured locations. The
Caterpillar lifting eyes are used for loading and unloading the chassis from the truck as
depicted in Template 15 below.

Template 15: Chassis removal from transport using supplied lifting eyes.

Taken from REHS1507

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
31
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
When it comes time to raise the front end of the truck for front tyre installation,

REHS1507 provides the photo shown in Template 16 and instructs to ‘Use a suitable

lifting device in order to raise the front of the truck’.

Due to the Mine Spec extras (eg. wider access steps) that are fitted to the machine by this

stage, lifting slings were interfered with (and two were actually cut) when trying to lift in

a manner similar to that depicted in Template 16 below.

The Caterpillar lift eyes from the insert in template 15 were only ever intended to lift the

chassis as shipped from the factory. By the time that the assembly has progressed to the

point of front tyre installation and certain mine extras have also been fitted, these

Caterpillar lift eyes should not be used to raise the chassis (they are not load rated for that

purpose).

Hastings-Deering therefore had the lifting eyes as depicted in Template 15 built and

certified locally.

Template 16: Raising front of truck for front tyre installation as per REHS1507

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
32
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
3.5.4 Rear Wheel Install Stand

Used in preference to jacks when installing rear tyres. Note the wood placed under the

rear tyres in the bottom photo. After rear tyre installation, the front of the truck is raised,

causing the chassis to pivot on these wooden blocks, thus raising the chassis off the stand.

The stand is then removed without having to re-connect the crane to the rear. Refer to

Appendix 3C for the engineering print.

Template 17: Rear Wheel Install Stands

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
33
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
3.5.5 LHS Hoist Pin Access Stand

Due to the narrow access space, this stand fits in beside the fuel tank to allow easy LHS
hoist pin installation. In hindsight, lockable wheels would have been added to the lags of
this stand. The two steps attached to the handrails were included to allow fitters to step
up whilst checking alignment and bore condition.
No engineering drawings exist for this stand so critical dimensions have been included
below.

2000 mm

400 mm

1800 mm

560
mm

Template 18: Allows access beside the Fuel Tank for LHS Hoist Pin Installation

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
34
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
3.5.6 Chassis Rail Access Work Platform

The frame depicted below was built to improve safety and efficiency whilst working on
the chassis rail area.

Template 19: Dealer Chassis Rail Access Platform

Template 20: Dealer Chassis Rail Access Platform in use

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
35
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
4 797B COMMISSIONING & CUSTOMER SIGN-OFF

The 797 Commissioning test is the final assessment of the truck before it is turned over to
the customer. The Commissioning Tool will record system pressures, transmission data,
engine data, etc. The tests are written such that the truck will either pass or fail certain
requirements. In the event of a failed requirement, problem identification and resolution
will occur before the truck is delivered to the customer. The time required to perform this
will depend on the amount of trouble-shooting that is required.

For those unfamiliar with the final commission test report, an actual 797B commissioning
test report can be viewed via the following Catminer link:
https://catminerpreview.cat.com/cda/layout?m=19574&x=7

4.1 CATERPILLAR COMMISSIONING TEAM

Any potential involvement of Caterpillar’s commissioning team should have been


clarified during the sales process with the CGM team. If the commissioning team is to be
involved (even if only for the first few trucks) then minimal planning should be required
for this stage.
The Caterpillar Commissioning team will bring custom commissioning software for the
797B OHT as well as proprietary tooling.

4.2 CATERPILLAR COMMISSIONING PROCEDURE

For those sites that will be commissioning the 797B themselves, the Caterpillar
commissioning procedure may be used. Refer to Appendix 4A. Further, Appendix 4D
includes a Caterpillar Commissioning checklist.

4.3 HASTINGS-DEERING COMMISSIONING PROCEDURE

The Caterpillar Commissioning team traveled to site to commission the initial trucks in
Hastings-Deering. When a dealer commissions these trucks the procedure does differ, as
the tools and software employed are different. A formal Caterpillar Dealer
Commissioning Procedure was not available to Hastings-Deering for the first 797B that
they commissioned alone. For this reason, Hastings-Deering created a process.
You may wish to use elements of this in conjunction with the Caterpillar procedure
described in section 4.2.
For the dealer created procedure, refer to Appendix 4B.
Appendix 4C includes a dealer created Start-Up checklist.

Caterpillar: Confidential Yellow


May 2007, Revision 1. The controlled copy of this document can be found at: 36
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
4.4 CUSTOMER SIGN-OFF PROCESS

Once the commissioning tests have been completed in their entirety and have met all tests
and specifications, the 797B is ready for delivery to the customer.

Your dealer team should have negotiated a set sign off procedure. This may well include
a summary of Commissioning test results and a sign off checklist.

Appendix 4E includes a 797B Delivery Checklist as used at the project site.

The dealer had also agreed to a machine sign-off procedure with the customer that
included the Caterpillar Delivery Service Record [Form 01-085314-09 (3515)] and
results of the commissioning tests.

Note that there is also a commissioning & pre-delivery form available in SISWeb service
forms that may also be used a reference.

5 PROCESS CONTROL SYSTEM

Appendix 5 includes example process control charts and a responsibility chart that may
be useful in planning for 797B’s within your territory and also in managing the assembly
and commissioning process.

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
37
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDICES

APPENDIX 1A ASSEMBLY PAD PREPARATION PROJECT PLAN (EXAMPLE)

The MS Project file for this project plan can be downloading from:

https://catminer.cat.com/cda/layout?m=58121&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
38
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 1B 797B BASIC WEIGHTS AND DIMENSIONS – QUICK REFERENCE

Other sources of details may be found in:


• Caterpillar Performance Handbook
• Via CatMiner at: https://catminer.cat.com/cda/layout?m=30171&x=7
• Assembly Special Instruction REHS1507-03
• 797B Mining Truck – Technical Sales Presentation (part of cornerstone series):
AEXC0643

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
39
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Draft

APPENDIX 1C REGISTER OF ASSETS (EXAMPLE)

Depicted below is an image of the Register of Assets file for the 797B project.

This file, including each of the worksheets indicated below can be downloaded at the

following link:

https://catminer.cat.com/cda/layout?m=58121&x=7
APPENDIX 1D REGISTER OF ASSETS (EXAMPLE) CONTINUED

Further items to consider for assets may be found in the following document.

https://catminer.cat.com/cda/layout?m=58121&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
41
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Draft

APPENDIX 1E ASSEMBLY PAD LAYOUT (EXAMPLES)

Depicted below is an image of the Assembly Pad layout file


https://catminer.cat.com/cda/layout?m=58121&x=7
APPENDIX 1F: TRUCK BUILD PROJECT PLAN

The MS Project file for this project plan can be downloading from:
https://catminer.cat.com/cda/layout?m=58121&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
43
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 1G EXAMPLE JOB SAFETY ANALYSIS (JSA)

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
44
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 2A WORK ORDER SEGMENTATION (EXAMPLE)

Segment Comp Code Description


No1 7000 Assemble Machine
No 2 9288 Travel Expenses
No 3 9004 Hire of Equipment
No 4 7000 Paint Machine
No 5 0116 Sound Test
No 6 0653 Install Labels to Body
No 7 7306 Install Windscreen Washer Bottle
No 8 7338 Install Radio
No 9 7337 Install Two Way Radio
No 10 9276 Install Extended Aerial Mount Post
No 11 9097 Install VIMS Label
No 12 9157 Install Access Lights
No 13 9162 Install Front Access System Lower Stair
No 14 9162 Install Front Access System Upper Stair
No 15 5500 Install Stair Control Group
No 16 9272 Manufacture Cab Walkway Extensions
No 17 7254 Paint Step Edges Yellow
No 18 9013 Paint Jacking and Lifting Points
No 19 7405 Install Jacking Stand Label
No 20 7000 Sign Write Machine
No 21 1382 Install Coxon Radiator Caps
No 22 9501 Identify Test Points
No 23 1435 Relocate Park Brake Switch
No 24 1463 Install Jump Start Receptacle
No 25 9499 Install Ancillary Panel Bumper
No 26 1411 Install Battery Disconnect Lockout
No 27 9499 Install Ancillary Panel Cab
No 28 0651 Electrical Compartment Sealing
No 29 7418 Emergency Shutdown Cab
No 30 7418 Emergency Shutdown Switch Ground Level
No 31 7401 Install Fire Suppression
No 32 7419 Install Fire Extinguisher Deck
No 33 7419 Install Fire Extinguisher Bumper
No 34 7513 Install Quickfill System
No 35 1395 Drain and Refill Coolant
No 36 7540 Install Autolube System
No 37 9503 Identify Sample Point
No 38 7000 Identify Machine
No 39 1408 Electrical Schematic, Wiring & Brackets
No 40 9504 Install Manual
No 41 4305 Install Steering Pin Retaining Strap
No 42 0653 Vehicle Operating Height Label

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
45
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
No 43 9505 Supply Kidney Loop
No 44 7950 Paint Protective Covering
No 45 1073 Install Turbo Heat Shields
No 46 9164 Install Wheel Chocks
No 47 1263 Install Fuel Water Separator
No 48 7405 Engrave Filter Label
No 49 7431 Change VIMS Light Cover
No 50 9194 Install Air Jump Start Hose Reel
No 51 7557 Install Lubrication Data Label
No 52 6129 Install Quickfill Fittings
No 53 7402 Install electrical Air Horn
No 54 7254 Install Emergency Egress
No 55 1431 Install Beacon Lights
No 56 1428 Replace Reversing Lights
No 57 1429 Install Curb Lights
No 58 1429 Move Headlight Clusters
No 59 9264 Remove Fog Lights
No 60 9069 Install Clearance Lights
No 61 1926 Install Telemetry System
No 62 0635 Additional Electrical Component Mounts
No 63 4220 Install Mudflap on Fuel Tank
No 64 4220 Install Mudflap on Hyd Tank
No 65 7950 Paint Cab Floor
No 66 9161 Install Boom Gate
No 67 3024 Install Breather Front Hub
No 68 7319 Additional Mirror RHS
No 69 7319 Additional Mirror LHS
No 70 7950 Install Hyd Site Gauge Guard
No 71 7253 Install Access System Engine Bay
No 72 7254 Install Transmission Access Step
No 73 7187 Install Diff Wiring Guard
No 74 1428 Reversing Light LH Side Cab
No 75 1428 Reversing Light RHS Mirror
No 76 1411 Starter Switch Disconnect Lockout
No 77 7186 Install Cab Splash Deflector
No 78 1372 Install Air Tank Drain
No 79 9112 Install Anti Skid
No 80 7212 Install Bonnet Struts
No 81 6912 Install Lift Point Covers
No 82 9502 Install Rear View Camera
No 83 9098 Supply Missing Parts
No 84 7590 Carryout Delivery Checks

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
46
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 3A COMPONENT TRACKING DATABASE

This file, including each of the worksheets indicated below can be downloaded at the
following link:
https://catminer.cat.com/cda/layout?m=58121&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
47
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 3B 797B ASSEMBLY CHECKLIST

This check-list was developed by the dealer. As there is always a possibility that
specifications may be updated or changed and this document has no formal process for
updating, all spec values have been removed and would need to be added by the dealer
before using this form.

SERIAL NUMBER ________________


START DATE ________________
COMPLETION DATE ________________

__________ Position Chassis on Two Assembly Stands


__________ Position Rax on Assembly Stand behind Chassis
__________
__________ Install Radiator handrails

__________ Clean All Mounting Surfaces for RAX Links

__________ Install RAX Links to Chassis (BOTTOM LINKS FIRST)

__________ Assemble RAX to Chassis (TOP LINKS FIRST)

__________ Install Rear Struts

__________ Torque 24 Collet Bolts ( fill with oil now )

Follow Procedure (add spec here ft. lbs.) USE ANTISEIZE


__________ Install Transmission

Install Main Drive Shaft


__________ Torque Main Drive Shaft Bolts
(add spec here ft. lbs.) ) DRY (check if uncertain of procedure)
__________ Connect Hoses to Transmission & TC

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
48
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
__________ Install Pump Drive Shaft
__________ Torque Pump Drive Shaft Bolts
(add spec here ft. lbs.) DRY
__________ Install Drive Shaft Guards
__________ Connect Rear Brake Lines, Brake Cooler Hoses & Electrical to RAX
__________ Clean Hoist Cylinder Mounting Brackets
__________ Install Hoist Cylinders & Secure to Frame
__________ Torque Hoist Cylinders Bolts
(add spec here ft. lbs.) DRY
__________ Install Hoist Cylinder Hoses
__________ Clean Fuel Tank Mounting Surfaces
__________ Install Fuel Tank
__________ Torque Fuel Tank Frame to Bracket Bolts
(add spec here ft. lbs.) DRY
__________ Torque Fuel Tank Cap Bolts
(add spec here ft. lbs.) DRY
__________ Clean Mounting Surfaces for Front Struts
__________ Install Front Struts
__________ Torque Front Strut Mounting Bolts
Top Bolts (add spec here ft. lbs.) Turn and additional 120 degrees
+/- 5 degrees USE ANTISEIZE
Bottom Bolts (add spec here ft. lbs.) Turn and additional 120 degrees
+/- 5 degrees USE ANTISEIZE

__________ Install Cab Supports ( outriggers )


__________ Torque Cab Support Mounting Bolts
(add spec here ft. lbs.) DRY
Position & Weld RH Platform to Chassis
__________ Measure location for air box mounting brackets
__________ Install Exhaust Tubes
__________ Install Air Box
__________ Install Air Intake Tubes

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
49
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
__________ Clean Steering Mounting Surfaces
__________ Assemble Steering Cylinders & Tie Rods
__________ Torque Steering Cylinder Nuts at Steering BOX
(add spec here ft. lbs.) USE ANTISEIZE
__________ Torque Tie Rod Nuts & Steering Cylinder Nuts at Steering ARM
(add spec here ft. lbs.) USE ANTISEIZE
__________ Install Steering Hoses
__________ Adjust Toe Out (17mm) Align Clamps Horizontal & Tension
__________ Connect Front Brake Lines & Brake Cooler Hoses
__________ Assemble Components to Hydraulic Tank
__________ Clean Mounting Surfaces for Cab Supports
__________ Install Cab Supports
__________ Torque Cab Support Mounting Bolts
(add spec here ft. lbs.) DRY
__________ Prepare Cab (Assemble Components)
__________ Position Cab to Chassis
__________ Torque Cab Mounting Bolts
(add spec here ft. lbs.) DRY
__________ Connect Brake Hoses to Cab
__________ Connect Steering Hoses to Cab
__________ Connect All Electrical to Cab
__________ Install Ladders, Handrails & Mirrors
__________ Assemble Components to Hydraulic Tank
__________
__________ Conduct Pressure Test on Intake System

__________ Install Hoods

__________ Install Batteries

__________ Install Grease Lines

__________ Fill Rear Strut Collet Bearings & RAX Link Collet Bearings with Oil

__________ Fill Truck With Fluids

__________ Top Off Fluids

__________ Check Truck for Hose Rubs & Leaks

DEALER ADDED ATTACHMENTS

__________ Fire Suppression

__________ Radio

__________ GPS

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
50
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
TIRES

__________ Clean Rim Mounting Surfaces & Studs on Wheels


__________ Remove Split Rings from Rear Wheels (Mark Position)
__________ Clean Rims
__________ Install Front Tires & Rims
__________ Install Rear Inside Tires & Rims
__________ Torque (4) Rims to Wheels (Stanley Torque Tool)
(add spec here ft. lbs.) DRY
__________ Re-install Four Split Rings to Rear Wheels (In Proper Position)
__________ Torque Split Rings to Wheel Stations
(add spec here ft. lbs.) DRY
__________ Install Outside Dual Tires & Rims
__________ Torque Outside Dual Rims to Wheels
(add spec here ft. lbs.) DRY

BODY

__________ Assemble Mud Flaps to Body


__________ Assemble Safety Cables to Body

__________ Install Body Decals

__________ Clean Body Pivot Pins & Pivot Bores

__________ Position & Pin Body

__________ Pin Hoist Cylinders

__________ Weld Body Rocker Shoe Brackets to Chassis CrossBeam

__________ Weld Body Guides to Crossbeam

__________ Install Rocker Shoes

__________ Shim Body

__________ Weld Rock Knocker Brackets to Body

__________ Assemble Rock Knockers to Body

__________ Charge Struts with Nitrogen

COMMISSION TRUCK

------END –

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
51
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 3C DEALER FRONT STRUT LIFTING JIG
This file may be down loaded from:
https://catminer.cat.com/cda/layout?m=58121&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
52
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 3D DEALER CHASSIS LIFTING EYES

This file may be downloaded from:


https://catminer.cat.com/cda/layout?m=58121&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
53
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 3E DEALER REAR WHEEL INSTALLATION STAND

This file may be downloaded from:


https://catminer.cat.com/cda/layout?m=58121&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
54
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 4A CATERPILLAR COMMISSIONING PROCEDURE

Further details on the commissioning process can be viewed at the following link:
https://catminerpreview.cat.com/cda/layout?m=19574&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
55
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 4B 797B COMMISSIONING PROCEDURE (DEALER VERSION)

This entire 49-page file depicted below can be downloaded at the following link:
https://catminer.cat.com/cda/layout?m=58121&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
56
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 4C 797B START-UP CHECK SHEET (DEALER EXAMPLE)

Serial Number : Date :


Checks
No Item Checked
1 Air Tank – Fill with Air
2 Coolant Level
3 Differential, Differential Carrier & Final Drive Oil Level
4 Engine Coupling Oil Level
5 Check both Engine Oil Levels
6 Check Fuel System is Primed and no Leaks
7 Hydraulic Oil Level
8 Check all Drive Shafts are Clear of Hoses and Wiring
9 Check Breather Tube Covers are removed
10 Confirm Intake Test has been Carried out on Assembly Check sheet and
remove Dust Covers
11 Check there are no obstacles around Fan
12 Check Front Hub Levels
Start Procedure

No Item Done
1 Crank Engine without starting for 15 seconds without firing to prime pumps
2 Add oil to Hydraulic Tank till reaches Cold Level
3 Crank Engine without starting for 15 seconds without firing to continue to
prime pumps
4 Add oil to Hydraulic Tank till reaches Cold Level & Check Transmission Oil
Level
5 Start Engine Operate at Low Idle for 10 seconds – Check for Leaks
6 Shut Down Engine
7 Add oil to Hydraulic Tank till reaches Cold Level & Check Transmission Oil
Level
8 Start Engine Operate at Low Idle – Check for Leaks
9 Check Steering System operation
10 Check Park Brake & Service Brake Operation
11 Shut Down Engine
12 Add oil to Hydraulic Tank till reaches Cold Level & Check Transmission Oil
Level
13 Check Brake & Steering Accumulator Pressure
14 Set\Check steering Pump Low Pressure Standby 500PSI Hot
15 Check Grease Injectors are working
16 Upstroke Brake Charge Pump with ET
18 Set Dead-band adjustment on Service Brake pedal
19 Bleed Service & Park Brake Circuits
20 Machine Ready to Move ________

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
57
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
APPENDIX 4D 797B CAT COMMISSIONING CHECKLIST

797 Commissioning Procedure Check List

Checked
Description Specification Actual
By
Fluid Level Checks Yes/No

Operators Seat Yes/No

Seat Belt Yes/No

Steering Column Adjustability Yes/No

Battery Power Yes/No

Cab Dome Light Yes/No

VIMS Self Test Yes/No

Windshield Wipers Yes/No

Cigar Lighter Yes/No

Hazard Lights Yes/No

Panel and Running Lights Yes/No

Turn Signal Lights Yes/No

Reverse Lights & Back-up Alarm Yes/No

Fog Lights Yes/No

Ladder Light Yes/No

Engine Compartment Light Yes/No

VIMS Port Check Yes/No

Horn Yes/No

Neutral Start Switch Yes/No

Climate Control Yes/No

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
58
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Ground Level Shutdown Switch Yes/No

Master Engine Module Engine Serial Number

ECM Serial Number

Software Part Number

Front Engine Module Engine Serial Number

ECM Serial Number

Software Part Number

Rear Engine Module Engine Serial Number

ECM Serial Number

Software Part Number

Transmission ECM Part Number

ECM Serial Number

Software Part Number

Chassis Control ECM Part Number

ECM Serial Number

Software Part Number

Brake ECM Part Number

ECM Serial Number

Software Part Number

VIMS ECM Part Number

ECM Serial Number

Software Part Number

Analysis Module ECM Serial Number

Software Part Number

Clear Fault Codes Yes/No

Activate Controls Yes/No

Download VIMS Yes/No

Fuel Tank Attachment Code Yes/No

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
59
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
1580-1620 RPM
Elevated Low Idle
10-15 Min

Transmission Calibration Complete Yes/No

Transmission System Pressure 300-350 PSI

Transmission Clutch #7 Pressure 300-350 PSI

Hoist Calibration Complete Yes/No

Hoist Up Pressure 3350 -3550 PSI

Hoist Down Pressure 500 - 2300 PSI

Body Raise Time 20 - 27 Seconds

Body Lower Time 15 - 21 Seconds

Transmission Neutralizer Test Yes/No

Steering Stand-by Pressure


0 - 500 PSI
@ Low Idle
Steering Cut-In Pressure
3150 - 3350 PSI
@ Low Idle
Steering Cut-Out Pressure
3450 - 3600 PSI
@ Low Idle
Steering Stand-by Pressure
0 - 500 PSI
@ High Idle
Steering Cut-In Pressure
3150 - 3350 PSI
@ High Idle
Steering Cut-Out Pressure
3450 - 3600 PSI
@ High Idle
Truck Steers from Right to Left
Yes/No
While Pressure Drops
115 - 125 PSI
Main Air Pressure
5 Minutes
Brake Stand-by Pressure
0 - 300 PSI
@ Low Idle
Brake Cut-In Pressure
2000 - 2300 PSI
@ Low Idle
Brake Cut-Out Pressure
2950 - 3050 PSI
@ Low Idle

Service Brake Application Pressure 860 - 940 PSI

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
60
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Does Truck Move in 1st Gear at
1500 RPM with Service Brake Yes/No
Applied?
Retarder Brake Application Pressure 650 - 975 PSI

Does Truck Move in 1st Gear at


Yes/No
1500 RPM with Retarder Applied?
Secondary Brake Application
860 - 1050 PSI
Pressure
Does Truck Move in 1st Gear at
1500 RPM with Retarder and Yes/No
Secondary Brake Applied?
Towing Pump Pressure 550 - 750 PSI

Differential Oil Filter


Pump Drive Diverter "OFF", and
Pressure 9 - 55 PSI
Final Drive Bypass "ON"
Final Drive Oil Filter
@ Low Idle
Pressure 4 - 13 PSI

Differential Oil Filter


Pump Drive Diverter "ON", and
Pressure 0 - 2 PSI
Final Drive Bypass "ON"
Final Drive Oil Filter
@ Low Idle
Pressure 0 - 2 PSI

Differential Oil Filter


Pump Drive Diverter "OFF", and
Pressure 13 - 54 PSI
Final Drive Bypass "OFF"
Final Drive Oil Filter
@ Low Idle
Pressure 9 - 72 PSI

Differential Oil Filter


Pump Drive Diverter "OFF", and
Pressure 75 - 158 PSI
Final Drive Bypass "ON"
Final Drive Oil Filter
@ High Idle
Pressure 14 - 29 PSI

Torque Converter Inlet Pressure


15 - 35 PSI
@ Low Idle
Torque Converter Outlet Pressure
10 - 30 PSI
@ Low Idle
Torque Converter Inlet Pressure
90 - 130 PSI
@ High Idle
Torque Converter Outlet Pressure
50 - 90 PSI
@ High Idle
Does Transmission Upshift from 1st
Yes/No
Gear Through 7th gear?
Does Transmission Downshift from
Yes/No
7th Gear Through 1st gear?

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
61
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Fan Calibration Complete Yes/No

Clear Fault Codes Yes/No

Download VIMS Yes/No

Calibrate Payload Yes/No

Set Pay Configuration Yes/No

Reset SMH to "0" Yes/No

APPENDIX 4E 797B DELIVERY CHECKLIST (DEALER EXAMPLE)

Checks
Serial Number : Date :-

No Item Checked
1 Check all Lubricate & Coolant Levels including Fuel
2 Filter Kit ready
3 Have Steering & Brake Accumulators been Checked
4 Check all Points have Grease
5 Check Operation & Maintenance Manual Behind Seat
6 Fire Suppression System is Activated
7 Check Fire Extinguishers have Current Tags
8 Check AM\FM & Mine Radio are Operational
9 Check Height Decal is fitted
10 Config Payload & Turnon Scoreboard Target 347 Metric Tone (PAYCONF)
with Vims connected. Scoreboards are reading 000.
11 Check Cab is Centralised and not Knocking during Commissioning
12 Machine & Cab are Clean & Tidy
13 Check no Brake lines are Rubbing, Front or Rear on Hubs

APPENDIX 5 PROCESS CONTROL SYSTEM

A copy of an example process control plan may be found at:


https://catminer.cat.com/cda/layout?m=58121&x=7

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
62
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.
Draft

GLOSSARY OF TERMS

Assembly Pad:

The name given to the secured area where the 797B trucks are assembled. In this

guidebook, this will include everything enclosed within the security fence (eg office

buildings, shipping containers for storage, the actual assembly surfaces, etc…)

Caterpillar Standard Truck

This describes the truck that would result if built solely as per Special Instruction

REHS1507. Any customer Mine spec extras are not considered part of the Caterpillar

standard truck.

Commissioning Process

Involves the completion of commissioning tests, or the final assessment of the truck

before it is turned over to the customer. The Commissioning Tool will record system

pressures, transmission data, engine data, etc. The tests are written such that the truck will

either pass or fail certain requirements. In the event of a failed requirement, problem

identification and resolution will occur before the truck is delivered to the customer

Contamination Control (CC)

Contamination is anything in the fluid that doesn't belong. The success formula may be

expressed as:

Clean (Facilities + Parts/Components + Fluids + Repair/Assembly Processes) = Clean Machines/Engines = Longer life

So, quite simply, Contamination control is a reliability and durability initiative aimed at

providing superior value to Caterpillar's customers.

Job Safety Analysis (JSA):


A process whereby hazards associated with each step of a job are identified and control
measures are put in place to minimize the risk to personnel, environment and property
(definition courtesy of Hastings-Deering SHEQ form 1021)

Lifting Plan:
Most sites in Australia will utilize a crane contractor to take care of much of the material
handling on-site. REHS1507-03 includes information on how to move the various
components and this special instruction should provide information for the lifting
contractor to develop a Lifting Plan. The Lifting Plan will document the lifting
equipment to be used, how much area is required between truck chassis’, the best
component layout plan (a suggested plan is include in REHS1507-03) and so on.

Mine Spec Extras (Add-Ons):


The standard Caterpillar 797B is as per the assembly special instruction REHS1507-03.
The collection of all additions in excess of this are referred to as the Mine Spec (or mine
spec add-ons).

Safety Management Plan (SMP)


This is a controlled document that applies to the 797B truck assembly by Hastings
Deering. It is the intent of the SMP to document that the persons working on the project
own the process of reviewing and improving the safety management systems of the
project. The SMP aims to ensure compliance with all site specific in regard to
assembling 32 x 797B off-highway trucks.

TAFE:
Technical And Further Education learning providers.

ADDITIONAL REFERENCES

Special Instruction:
REHS1507 797B Off-Highway Truck Assembly Procedure

Catminer:
Commissioning information:
https://catminerpreview.cat.com/cda/layout?m=19574&x=7

Contamination Control information:


https://catminer.cat.com/cda/layout?m=3590&x=7

Other:
Soil preparation (if required):
QECB9729 Caterpillar Soil and Asphalt Compaction Manual

Caterpillar: Confidential Yellow

May 2007, Revision 1. The controlled copy of this document can be found at:
64
https://catminer.cat.com/cda/layout?m=58121&x=7
All printed copies are uncontrolled.

También podría gustarte