Road Pavement Construction

Quantity
Item Amount as per
Description of Items Unit as per Rate
No. BOQ
BOQ

SECTION R-4 EARTH WORK FOR ROADS

R-4.1 Structural excavation in common soil for


pavements and curb / stone edging, etc. including
disposal of surplus material, upto any lead within
the Site complete as per Specifications and as
directed by the Engineer.
M3 24,587 423 10,400,301

R-4.2 Make embankment as per lines, grades and levels


shown in drawings and as per Specifications
including cost of excavation, haulage, filling,
placing, compacting mechanically in layers not
exceeding 150mm thick depth to 95% maximum
modified AASHTO dry density, (Min. C.B.R = 7%)
including preparation of sub grade complete in all
respect.

a) With soil type A-4 from outside upto any lead


and lift.
M3 15,850 400 6,340,000

R-4.3 Provide and fill sand approved by the Engineer,


under pavement, parking areas and walkway, etc.,
including cost of material, transportation, placing,
and compacting 95% modified AASHTO dry
density complete as per Specification.

M3 3,610 706 2,548,660

SECTION R-5 SUB-BASE COURSE

R-5.1 Provide and lay granular subbase course of


crushed stone of approved quality and grade,
including cost of materials, transportation, placing,
mixing, spreading, watering, and compaction to
required depth, side slope and grade to achieve
98% maximum modified AASHTO dry density (Min.
CBR = 50%) complete as per Specifications.

M3 1,626 2,825 4,593,450


SECTION R-6 WATER BOUND MACADAM BASE
COURSE

R-6.1 Provide and lay water Bound Macadam base


course of crushed stone of approved quality and
grade, including cost of materials, transportation,
placing, mixing, spreading, watering and
compaction to required depth, side slope and
grade to achieve 100% maximum modified
AASHTO dry density (Min. CBR = 80%) as per
Specifications.
M3 50 3,532 176,600

SECTION R-21 CEMENT CONCRETE


PAVEMENT
R-21.1 Provide and lay reinforced cement concrete of min.
3000 psi cylinder strength at 28 days in pavement
etc. including mixing, placing, compacting,
finishing, formwork, curing etc. complete as per
drawings and Specifications but excluding the cost
of reinforcement.
M3 1,805 12,000 21,660,000

R-21.2 Provide and lay lean concrete under pavement,


parking areas and walkways, etc., using crush
stone as coarse aggregate including formwork and
its removal, leveling, compacting and curing etc.,
complete in all respects as per drawings and
Specifications.

a) PCC (1:4:8) M3 835 8,000 6,680,000

SECTION R-24 REINFORCING STEEL WORK

R-24.1 Provide and fix reinforcement of steel bars


including cutting, placing bending and binding as
per drawings and Specifications.

Reinforcing bars of Grade 60 (60,000 psi). Tonne 145 115,000 16,675,000

SECTION R-31 PAVEMENT MARKING

R-31.1 Provide and paint using reflective road quality paint


of appproved ICI make manufacturer's,
Specifications and as directed by the Engineer.

a) On Curb Stone M2 150 430 64,500

SECTION R-35 PRE-CAST CONCRETE PAVING


BLOCK
R-35.1 Provide and lay 50mm thick concrete tuff pavers of
7000 psi cube strength at 28 days, local made
approved manufacturers for parking areas and
walkways etc., laid on 20mm thick 1:3 cement sand
mortar bed under coat including grouting with 1:3
cement sand mortar and with matching colour
pigment complete as shown in drawings, and as
approved by the Engineer.

M2 8,125 890 7,231,250

R-35.2 Ditto items above R-11 but 80mm thick concrete


tuff paver of 7000 psi cube strength at 28 days.
M2 500 1,076 538,000

R-35.3 Provide and lay precast concrete edge / curb


stone fixed in cement sand mortar 1:3 and
embedded in 1:2:4 concrete base including
fabrication, formowrk, curing etc. complete in
accordance with sizes, lines and levels shown in
the drawings and as per Specifications.

a) Edge Stone (150mm x 300mm) Rm 575 600 345,000


b) Edge Stone (150mm x 350mm) Rm 975 630 614,250
c) Curb Stone (150mm x 450mm) Rm 575 785 451,375

MISCELLANEOUS

M-1 Providing and laying contraction joints in concrete


pavement including 6 x 12mm sealant (Sika Flex-
68TF) as per drawings and Specifications.
RM 2,850 336 957,600

M-2 Provide and lay expansion joint in pavement


including 16 x 20mm sealant (Sika Flex-68TF) and
25mm premoulded expansion joint filler complete
as per drawings and Specifications. RM 475 400 190,000

M-3 Provide and lay in position set of mild steel pipe 16


SWG M.S. caps 275mm long and 20mm dia
M.S.smooth dowel bars at 550mm c/c, 550mm
long, partly oiled and painted in expansion joints of
concrete pavement as per drawings and
Specifications. No. 880 150 132,000

M-4 Provide and fix back-up rod of approved quality


behind sealer in expansion joint complete as per
drawings and as per details and sample approved
by the Engineer. RM 475 30 14,250

Total C/o to Summary of Cost: 79,612,236