Está en la página 1de 53

Integrated Cost – Schedule Risk Analysis

Using the Risk Driver Approach

Qatar PMI Meeting


February 19, 2014

David T. Hulett, Ph.D.


Hulett & Associates, LLC

© 2014 Hulett & Associates, LLC


1
The Traditional 3-point
Estimate of Activity Duration Uncertainty

 Typical schedule risk analysis starts with the activity that is impacted
by risks
– Estimates the 3-point estimate for optimistic, most likely and
pessimistic duration
– Creates a probability distribution for activity duration
– Performs Monte Carlo simulation
 What causes the most overall schedule risk? These questions are
answered in the 3-point estimate approach by looking to the impacted
activities:
– Sensitivity to activity durations
– Criticality of activity durations

© 2014 Hulett & Associates, LLC


2
Some Problems with Traditional Approach

 Can tell which activities are crucial, but not directly which
risks are driving
 Makes poor use of the Risk Register that is usually available
 Cannot decompose the overall schedule risk into its
components BY RISK
– Ability to assign the risk to its specific risk drivers helps with
communication of risk causes and risk mitigation

© 2014 Hulett & Associates, LLC


3
Risk Drivers: Start with the Risks Themselves

 Drive the schedule risk by the risks already analyzed in the Risk
Register – Root Causes
 For each risk, specify:
– Probability it will occur
– Impact on time if it does
– Activities it will affect
 Starting with the risks themselves gives us benefits
– Links qualitative analysis to the quantitative analysis
– Estimates the impact of specific risks for prioritized mitigation purposes
– Correlations between activities happen automatically – never have to
guess at these coefficients again, never get impossible matrices

© 2014 Hulett & Associates, LLC


4
Simple Example of Risk Register Risks

 Use the Risk Factors feature in Pertmaster 8.7


– A few other simulation packages have this capability
 Collect probability and impact data on risks
 Load the risks
 Assign risks to schedule activities

© 2014 Hulett & Associates, LLC


5
Risk Factors Mechanics (1)

 The risk factor is assigned to one or several activities,


affecting their durations by a multiplicative factor
– E.g., the factor may be .90 for optimistic, 1.0 for most likely and
1.25 for pessimistic
– These factors multiply the schedule durations of the activities to
which they are assigned
 Risks can be assigned to one or more activities
 Activity durations can be influenced by one or more risks

© 2014 Hulett & Associates, LLC


6
Risk Factors Mechanics (2)

 Risk Factors are assigned a probability of occurring on any


iteration.
– When the risk occurs, the factor used is chosen at random from
the 3-point estimate and operates on all activities to which it is
assigned
– When not occurring on an iteration the risk factor takes the value
1.0, a neutral value
 When an activity is influenced by more than one risk, their
factors are multiplied together, if they happen, on any
iteration if they are specified to be in series

© 2014 Hulett & Associates, LLC


7
Risk Factor
Probability is 100%, Factor can be + or -

Entire Plan : Duration


100% 115

Here the For the examples


95% 111
400
90% 109

Ranges are we use an activity


85% 108
350
80% 106

based on 75% 105


with 100 days in
deviations + the schedule
300 70% 104

65% 104

and – from the

Cumulative Frequency
60% 103
250
55% 102

Plan.
Hits

50% 101
200

Probability is
45% 101

40% 100

100% 150 35% 99

30% 99

25% 98
100
20% 97

15% 96
50
10% 95

5% 94

0 0% 90
90 95 100 105 110 115
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


8
Assigning a Probability Less than 100%

 The essence of a “risk” is its uncertainty in two dimensions:


– Uncertainty of its occurrence, specified by a probability
– Uncertainty of its impact, specified by a range of durations
 If the risk may or may not occur, we specify the probability
that it will occur
– The risk occurs and affects the activities it is assigned to on X% of
the iterations, chosen at random, the multiplicative factor used is
chosen at random from the range of data input by the user
– On (1 – X)% of the iterations, Factor takes 1.0 value

© 2014 Hulett & Associates, LLC


9
Assigning a Probability Less than 100%

Spike
Entire Plan : Duration Entire Plan : Duration
100% 130 100% 114

95% 123 95% 107


Spike
contains
2000

90% 120 90% 104

contains
3500
85% 118 85% 101

40% of
1800

80% 116 80% 100

1600 75% 114 3000 75% 100


70% of
the 70% 113 70% 100

1400 65% 111 65% 100


the
probability Cumulative Frequency

Cumulative Frequency
2500

probability
60% 110 60% 100

1200
55% 109 55% 100
Hits

Hits
50% 107 2000 50% 100
1000
45% 106 45% 100

40% 103 40% 100


800 1500
35% 100 35% 100

30% 100 30% 100


600
25% 100 1000 25% 100

20% 100 20% 100


400

15% 100 15% 100


500
200 10% 100 10% 99

5% 100 5% 97

0 0% 100 0 0% 90
100 105 110 115 120 125 130 90 95 100 105 110 115
Distribution (start of interval) Distribution (start of interval)

© 2014 Hulett & Associates, LLC


10
Assigning
More than One Risk to an Activity

 If more than one risk is acting on an activity, the resulting


ranges are the multiplication of the percentages
 This is reality – an activity is often affected by multiple risks
 Two cases are shown next:
– When both risks are 100% likely to occur
– When both risks are < 100% likely to occur
 In each case, the computer simulation creates the
uncertainty range on an activity’s duration – it is not
estimated

© 2014 Hulett & Associates, LLC


11
Parallel and Series Risks – Additive – used
with Risk Register
Risk 1 20 days
20 days for risk recovery
Risk 2 12 days

If these two risks are parallel, they can be recovered


simultaneously

Risk 1 20 days Risk 2 12 days 32 days for risk recovery

If these two risks are series, they can not be


recovered simultaneously so the duration is longer

© 2014 Hulett & Associates, LLC


12
Parallel and Series Risks – Multiplicative –
Used with Risk Drivers (RiskFactors)
Risk 1 1.2 factor Use 1.2 Factor, the
Risk 2 1.05 factor largest factor only

If these two risks are parallel, they can be recovered


simultaneously

Risk 1 1.2 factor Risk 2 1.05 factor Use (1.2 x 1.05 = 1.26)
Factor, multiply the two
If these two risks are series, they can not be
recovered simultaneously

© 2014 Hulett & Associates, LLC


13
Two Risks affect One Activity using Factors that
Occur 100% - placed in Series

Entire Plan : Duration


100% 146
260
95% 131

240 90% 127

85% 124
220
80% 123

200 75% 121

Risks in
70% 119
180
65% 118

series, P80

Cumulative Frequency
160 60% 117

is 123 days
55% 116
140
Hits

50% 115

120 45% 114

40% 112
100
35% 111

80 30% 110

25% 109
60
20% 108

40 15% 106

10% 104
20
5% 102

0 0% 92
100 110 120 130 140
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


14
Two Risks affect One Activity using
Factors that Occur 100% - in Parallel
Entire Plan : Duration
100% 130

95% 125

350 90% 122

85% 121

80% 119
300
75% 118

70% 117

250 65% 116

Cumulative Frequency
60% 115

55% 114

Risks in
Hits

200
50% 113

45% 112

parallel, P80 150


40% 111

is 119 days
35% 111

30% 110

100 25% 109

20% 108

15% 107
50
10% 106

5% 105

0 0% 100
100 105 110 115 120 125 130
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


15
Two Risks with Less than 100% Probability
Affecting one Activity – Risks in Series

Entire Plan : Duration


1800 100% 144

The spike at 100


95% 123

90% 119
1600

days represents (1) 85% 116

the likelihood that


80% 114
1400
75% 112

neither risk occurs


70% 110
1200
65% 108

[60% x 50% =

Cumulative Frequency
60% 107

30%] plus (2) the


1000 55% 105
Hits

50% 103

chance that 100 800 45% 101

days is picked
40% 100

35% 100
600

when one or both 30% 100

occur.
25% 100
400
20% 100

15% 100

200
10% 99

5% 96

0 0% 90
90 100 110 120 130 140
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


16
Two Risks with Less than 100% Probability
Affecting one Activity – Risks in Parallel
Entire Plan : Duration
100% 130

With one risk’s


95% 122
2200
90% 118

having a minimum 2000 85% 115

80% 113

range of 100%, it
1800
75% 111

70% 110

cannot be less than


1600
65% 109

Cumulative Frequency
1400 60% 107

100 days
55% 105
Hits

1200 50% 103

45% 101
1000
40% 100

35% 100
800

30% 100

600 25% 100

20% 100
400
15% 100

10% 100
200
5% 100

0 0% 100
100 105 110 115 120 125 130
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


17
Risk Factors Model How Correlation Occurs
Coefficients are Calculated (1)
Risk 1: Risk Probability = .5,
Range .95, 1.05, 1.15

Activity 1 Activity 2

Correlation = 100%

© 2014 Hulett & Associates, LLC


18
Scatter showing 100% Correlation

© 2014 Hulett & Associates, LLC


19
Risk Factors Model How Correlation Occurs
Coefficients are Calculated (2)

Risk 3: Risk Probability = Risk 1: Risk Probability = .5, Risk 2: Risk Probability =
.25, Range .95, 1.05, 1.15 .45,
Range .8, .95, 1.05 Range 1.0, 1.10, 1.20

Activity 1 Activity 2

Correlation = 37%

Correlation is modeled as it is caused in the project


Correlation coefficients are generated, not guessed

© 2014 Hulett & Associates, LLC


20
Scatter showing 37% Correlation

© 2014 Hulett & Associates, LLC


21
Sensitivity to the Risk Factors

Risk 1 is more
important since it
affects both Activity
A and Activity B

© 2014 Hulett & Associates, LLC


22
Integrated Cost and Schedule
Risk Analysis

Risk

Project Schedule Cost Risk

Risk
“Burn Rate” per day Time Independent Costs
Schedule Risk

Time-Dependent
Costs Project
Cost Risk
© 2014 Hulett & Associates, LLC
23
Use a Case Study to Illustrate the
Integration of Cost and Schedule Risk
 Case Study is a simplified schedule of an off-shore gas
production project including approval process, drilling,
fabrication of the jacket and the topsides (modules),
installation of same, and commissioning. Use Risk Drivers
approach
 Results include:
– Schedule risk and cost risk histograms and cumulative distributions
– Prioritizing risks to time and to cost
– Scatter diagram of cost and time
– Probabilistic cash flow

© 2014 Hulett & Associates, LLC


24
How the Impact Ranges work on Different
Resources to show Cost Risk (1)

 The resources are either time dependent or time independent


 Time Dependent resources such as labor and rented
equipment (barges, tower cranes) vary according to:
– Schedule risk multiplied by the burn rate per day
– Burn rate is uncertain if the risk exhibits a range
 So time dependent resources’ costs vary:
– By the duration uncertainty even if the burn rate is fixed
– By the uncertain burn rate even if durations are fixed
– By both uncertain duration and uncertain burn rate, a cross-product

© 2014 Hulett & Associates, LLC


25
How the Impact Ranges work on Different
Resources to show Cost Risk (2)

 Time-independent resources such as procured raw


materials and equipment, perhaps some subcontracts
 The total estimated cost is varied by the range on a risk with
its probability
 Time independent resources’ costs:
– May vary even if the duration of Fab and Deliver activities is fixed
– If they have no cost impact ranges they do not vary even if Fab
and Deliver activities’ durations are variable

© 2014 Hulett & Associates, LLC


26
Offshore Gas Production: Integrating
Schedule and Cost Risk Analysis

© 2014 Hulett & Associates, LLC


27
Resources and Cost
Total Project = $1,473 million

Resources are added to the


activities
PMT = Project Management
Team
Detail = Detailed Engineering
PROC = Procurement
FAB = Fabrication
DRILL = Drilling
INST = Installation
HUC = Hook-Up and
Commissioning

We could have LOE costs such as


PMT placed on a hammock in PRA

© 2014 Hulett & Associates, LLC


28
Inherent Variation and
Duration Estimating Uncertainty
The estimate is that durations
are underestimated
The range, on all activities, is
95% – 105% - 115% of the
estimated duration, indicating
some bias in the assumptions
and / or estimating
Different activity types could
have different reference ranges
for their inherent variation
Inherent variation is not
susceptible to risk mitigation – it
is always with us and must be
recognized

© 2014 Hulett & Associates, LLC


29
Schedule Risk with Inherent uncertainty
Offshore Gas Production Project
Entire Plan : Finish Date
100% 05 Aug 16

95% 05 Jul 16
700

90% 28 Jun 16
650
85% 23 Jun 16

600 80% 19 Jun 16

550
75% 15 Jun 16 Baseline schedule date is
500
70% 13 Jun 16
20MAR16
P-80 is 19JUN16
65% 10 Jun 16

450 60% 07 Jun 16

Cumulative Frequency
55% 04 Jun 16
400
Hits

50% 01 Jun 16
350
45% 30 May 16

300 40% 27 May 16

35% 25 May 16
250

30% 22 May 16

200
25% 19 May 16

150 20% 16 May 16

15% 12 May 16
100

10% 07 May 16

50
5% 29 Apr 16

0 0% 31 Mar 16
27 Apr 16 16 Jun 16 05 Aug 16
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


30
Cost Risk with Inherent Uncertainty
Offshore Gas Production Project
Entire Plan : Cost
100% $1,534,415.98

900 95% $1,518,027.49

90% $1,514,498.07

800 85% $1,511,661.44

80% $1,509,587.33

700
75% $1,507,756.29 Baseline cost is $1,473 million
70% $1,506,215.40
Cost at the P-80 is $1,509
million
65% $1,504,792.58
600

60% $1,503,339.04

Cumulative Frequency
55% $1,501,853.33
500
Hits

50% $1,500,395.02

45% $1,498,929.53
400
40% $1,497,468.96

35% $1,496,002.91

300
30% $1,494,469.13

25% $1,492,865.71

200
20% $1,491,069.27

15% $1,488,845.49

100 10% $1,486,309.87

5% $1,482,293.69

0 0% $1,465,837.51
$1,470,000.00 $1,480,000.00 $1,490,000.00 $1,500,000.00 $1,510,000.00 $1,520,000.00 $1,530,000.00
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


31
Risk Drivers Used
Schedule Cost Impact
Impact Ranges Ranges
Schedule Impact Ranges Cost Impact Ranges
Most Most
Risk Name Min Max Min Max Probability
Likely Likely
Company's Engineers may vary in
1 90% 110% 130% 95% 100% 110% 85%
Experience
2 MTO, Specs may not be ready for ITB 100% 105% 125% 100% 105% 110% 60%
3 May have trouble interfacing phases 100% 110% 120% 90% 105% 115% 40%
Subsea conditions may not be as
4 95% 100% 115% 95% 100% 110% 20%
expected
5 LLE suppliers may be busy 80% 95% 110% 95% 105% 115% 20%
Quality engineers at Fabricators may be
6 100% 100% 100% 100% 105% 110% 60%
inexperienced
Scope growth may be greater than
7 105% 110% 125% 100% 105% 110% 60%
expected
HUC resources may not be as
8 100% 115% 130% 95% 105% 115% 20%
experienced as needed

These data are derived during in-depth interviews with project participants and
others. The interviews focus on the Risk Register risks that are designated “high
risk” for time and cost. Use Primavera risk Analysis Risk Factor capability
© 2014 Hulett & Associates, LLC
32
Assignment of Risk Drivers to Activities
Risk Driver Activity Assignment

DETAIL FAB PROC INSTAL HUC DRILL PMT APPROVAL

Market Costs for Bulks/Equipment


X X X X
Volatile
Experienced HUC resources availability X

Company's Engineers' experience X X X X X X X X

Schedule Maturity X X X X X X X

MTO, Specifications may not be ready ITB X X X

Problems interfacing Phases X X X X

Cost Estimate inaccurate / immature X X X X X X X

Fabricators and Suppliers may be busy X X


Quality engineers may be scarce @ FAB,
X X
Suppliers
Scope Growth may be more than
X X
expected
© 2014 Hulett & Associates, LLC
33
Some Risks are Parallel and Some Series

If several risks are assigned to any task we


may put some in parallel (can be recovered
simultaneously) and some in series (recovery
will take all resources so cannot be recovered
simultaneously with other risks)
In this case, risks 6 and 7 have been placed in
series

© 2014 Hulett & Associates, LLC


34
Schedule Risk Analysis Results
Schedule Risk Analysis
Date Results for First Gas
Baseline Date 20-Mar-16
Risk Analysis Results P-5 P-50 P-80 P-95
2-Jul-16 4-Nov-16 6-Jan-17 14-Mar-17
Months from Baseline 3.4 7.5 9.6 11.8
Duration Results To First Gas
Days
Baseline Duration 1,906
Risk Analysis Results P-5 P-50 P-80 P-95
2,010 2,135 2,198 2,265
Percentage from Baseline 5% 12% 15% 19%

© 2014 Hulett & Associates, LLC


35
Risks and Inherent Uncertainty
Completion Date – First Gas
Offshore Gas Production Project
000005 - First Gas : Finish Date

First Gas 100% 19 Jul 17

95% 14 Mar 17

Baseline Date = 350 90% 14 Feb 17

20MAR16 85% 22 Jan 17

80% 06 Jan 17
300
75% 24 Dec 16

Date with 70% 11 Dec 16

Inherent
250 65% 30 Nov 16

60% 20 Nov 16

Cumulative Frequency
uncertainty was 200
55% 13 Nov 16
Hits

19JUN16
50% 04 Nov 16

45% 26 Oct 16

40% 17 Oct 16
150

P-80 with all 35% 08 Oct 16

30% 29 Sep 16

risks added is 100 25% 18 Sep 16

6Jan17 20% 06 Sep 16

9.5 months
15% 22 Aug 16
50
10% 31 Jul 16

5% 02 Jul 16

0 0% 22 Apr 16
27 Apr 16 05 Aug 16 13 Nov 16 21 Feb 17 01 Jun 17
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


36
Risks and Inherent Uncertainty
Schedule Duration to First Gas
Offshore Gas Production Project
Entire Plan : Duration
100% 2392
350
95% 2265

Baseline 90% 2237

Duration to
85% 2214
300

80% 2198

First Gas = 75% 2185

1,020 days
250 70% 2172

65% 2161

60% 2151

Cumulative Frequency
200 55% 2144
Hits

50% 2135

45% 2126

150
40% 2117

35% 2108

30% 2099
100
25% 2088

20% 2076

15% 2061
50

10% 2039

5% 2010

0 0% 1939
2000 2100 2200 2300 2400
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


37
Prioritize Risks that Cause Schedule
Contingency to the P-80
Explain the Schedule Contingency to the P-80
P-80 Date Take Risks Out:
Days
All Risks In 6-Jan-17 % of Contingency
Saved
Specific Risks Taken Out in Order
Company's engineers may vary in experience 14-Nov-16 53 18%
MTO, Specs may not be ready for the ITB 5-Oct-16 40 14%
Scope growth may be more than expected 1-Jul-16 96 33%
May have problems interfacing phases 24-Jun-16 7 2%
HUC resources may not be experienced 19-Jun-16 5 2%
Uncertainty
Duration Estimating 20-Mar-16 91 31%
Total Contingency 292 100%

The order of risks is the best order at each step in this table. However, because of
the schedule’s structure some “Days Saved” values show inversion.
© 2014 Hulett & Associates, LLC
38
Picture of
Taking Risks out in Priority Order
100%

90%

Variation:91 Variation:7
Variation:5 Variation:96 Variation:40 Variation:51
80%

70%

Cumulative Probability
60%

50%

40%

30%

Variation:58 Variation:3
Variation:5
Variation:19 Variation:35 Variation:50
20%

10%

0%
Mar 16 10 May 16 29 Jun 16 18 Aug 16 07 Oct 16 26 Nov 16 15 Jan 17 06 Mar 17 25 Apr 17 14 Jun 17

© 2014 Hulett & Associates, LLC


39
Summary Cost Risk Analysis Results

Cost Risk Analysis Total Project

$ millions

Baseline Cost 1,473

P-5 P-50 P-80 P-95

Risk Analysis Results 1,541 1,667 1,736 1,808

Dollars from Baseline 68 194 263 335

Percent from Baseline 5% 13% 18% 23%

© 2014 Hulett & Associates, LLC


40
Where is the Cost Risk – by Resource
Cost Contingency Breakdown by Resource
$ millions
Resource Baseline P-80 % Contingency
Project Management Team 31 43 39%
Engineering 70 96 36%
Installation 57 78 36%
Fabrication 300 399 33%
Hook Up & Commissioning 45 60 32%
Procurement 850 945 11%
Drilling 120 132 10%
TOTAL PROJECT 1,473 1736 18%

Cost Contingency Breakdown by Type of Resource


$ millions
Type Baseline P-80 % Contingency
Materials (Equipment, raw materials) 850 945 11%
Labor (including rented equipment) 623 797 28%

© 2014 Hulett & Associates, LLC


41
Risks and Inherent Uncertainty
Cost Risk Analysis Results
Offshore Gas Production Project
Entire Plan : Cost
100% $1,945,224.66

Baseline Cost $1,473 400


95% $1,808,124.77

million 90% $1,776,809.05

350 85% $1,752,269.90

80% $1,735,644.11

With inherent 75% $1,719,274.56

uncertainty P-80 is
300
70% $1,707,918.39

$1,509 million
65% $1,695,182.86

250 60% $1,685,944.55

Cumulative Frequency
55% $1,676,312.18

Adding Risk Drivers


Hits

50% $1,666,546.42
200

P-80 Cost
45% $1,655,388.88

40% $1,645,807.52

$1,736 million 150


35% $1,635,534.18

18% contingency 30% $1,624,565.01

25% $1,612,911.88
100

20% $1,599,905.70

15% $1,585,976.57
50
10% $1,567,102.71

5% $1,541,499.20

0 0% $1,449,663.64
$1,500,000.00 $1,600,000.00 $1,700,000.00 $1,800,000.00 $1,900,000.00
Distribution (start of interval)

© 2014 Hulett & Associates, LLC


42
Analysis of the
Sources of Cost Contingency
Source of Cost Contingency at the P-80
Total Cost Contingency
Total Cost All-Risks 1,736
Baseline Cost 1,473 262
Contribution to
Contingency
Take Out all Schedule Risks 1,631 105
Take Out all Cost Risks 1,581 155
Interaction of Cost/Schedule Risks 2
Total Contingency 262

40% of the risk to cost comes from risk to schedule, common finding

© 2014 Hulett & Associates, LLC


43
Priority Risks to Cost
Measured at P-80
Prioritize Risks to Cost at the P-80
$ millions
Total Project, All Risks 1,736
Baseline cost 1,473
$ millions
Take Out Risk Events one at a time: % of total contingency
saved
Scope Growth may be more than expected 1,685 51 19%
Company's Engineers' may be inexperienced 1,624 61 23%
MTO, Specifications may not be ready ITB 1,550 74 28%
Quality engineers may be scarce @ FAB, Suppliers 1,525 25 10%
Problems interfacing Phases 1,519 6 2%
LLE Suppliers may be busy 1,514 5 2%
Experienced HUC resources availability 1,511 3 1%
Subsea conditions may not be as expected 1,509 2 1%
Take out the 3-point estimates
Schedule duration estimate are uncertain 1,473 36 14%
262 100%

© 2014 Hulett & Associates, LLC


44
Graphical Effect of Taking the Risks out
One at a Time in Priority Order
100%

90%

Variation:$36,405.11
Variation:$1,591.31
Variation:$2,545.46
Variation:$5,243.00
Variation:$6,183.49
Variation:$24,925.51 Variation:$73,651.85 Variation:$54,652.75 Variation:$57,033.29
80%

70%

Cumulative Probability
60%

50%

40%

30%

Variation:$17,479.27
Variation:$1,236.17
Variation:$596.69
Variation:$1,643.69
Variation:$3,382.76
Variation:$9,374.08
Variation:$19,916.13
Variation:$33,986.87 Variation:$39,083.92
20%

10%

0%
$1,500,000.00 $1,550,000.00 $1,600,000.00 $1,650,000.00 $1,700,000.00 $1,750,000.00 $1,800,000.00 $1,850,000.00 $1,900,000.00

© 2014 Hulett & Associates, LLC


45
In this case study Cost and Schedule are
Correlated 51%
Offshore Gas Production Project
Deterministic Point Inside both limits Outside both limits

82%

11% 7%

$1,900,000.00

$1,850,000.00

$1,800,000.00

$1,750,000.00
82%
Entire Plan: Cost

$1,741,677.83

$1,700,000.00

$1,650,000.00

$1,600,000.00

PLAN $1,550,000.00

$1,500,000.00

70% 10 Jan 17 11%


$1,450,000.00
27 Apr 16 16 Jun 16 05 Aug 16 24 Sep 16 13 Nov 16 02 Jan 17 21 Feb 17 12 Apr 17 01 Jun 17
Entire Plan: Finish

70% of the risk is in lower-left quadrant

© 2014 Hulett & Associates, LLC


46
Probabilistic Cash Flow
Resource Flow for Cost
Filter: Entire Plan

Scheduled P80

2,000,000

1,800,000

1,600,000

Cumulative
terministic Cost: $1,473,445.00

1,400,000

1,200,000
Monthly Cash
Flow

Cumulative
Deterministic Finish: 20 Mar 16
- P-80
1,000,000

800,000
- Planned
600,000

400,000

200,000

0
13 Jan 13 23 Apr 13 01 Aug 13 09 Nov 13 17 Feb 14 28 May 14 05 Sep 14 14 Dec 14 24 Mar 15 02 Jul 15 10 Oct 15 18 Jan 16 27 Apr 16 05 Aug 16 13 Nov 16 21 Feb 17 01 Jun 17
Time

© 2014 Hulett & Associates, LLC


47
Analysis of a
Risk Mitigation Scenario
Risk Mitigation Scenario Schedule Impact Cost Impact First Project
Probabi Most Most Gas Cost ($
Low High Low High Date million)
lity Likely Likely
Risk to be Mitigated Before Mitigation
Company's Engineers may be 6-Jan-
85% 90% 110% 130% 95% 100% 110% 1,735
inexperienced 17
Proposed Mitigation: Increase Salaries
for company Engineers to competitive
levels
After Mitigation
Company's Engineers may be 14-Nov-
20% 90% 100% 110% 100 105 115 1,714
inexperienced 16
Improvement 53 21
Cost of proposed Mitigation 35
Net Improvement from Mitigation 53 -14

Spending $35 million for Engineers’ salary is assessed to reduce the probability of this risk
from 85% to 20%. Because the schedule slippage is 53 days less than before, there is $21
million we do not need to reserve and so the net cost impact of the mitigation at the P-80 is
offset by $21 million, for a net cost of $14 million. 48
© 2014 Hulett & Associates, LLC
NASA Joint Confidence Level (JCL) defined

For implementation of each major program segment, all space


flight and information technology programs are to be baselined
or rebaselined and budgeted in accordance with the following:
a) There is a 70 percent probability (or a different
probability that is approved by the decision authority) of
achieving the stated life cycle cost and launch schedule
b) Projects are to be baselined or rebaselined and
budgeted at confidence level consistent with the program’s
confidence level

© 2014 Hulett & Associates, LLC


49
JCL is determined by the joint distribution
of cost and schedule

 Integrated cost-schedule simulation is a perfect tool since it


provides a scatter diagram of time and cost pairs that are
consistent scenarios given the plan and the risks
 Find points where time and cost are jointly satisfied at P-70

© 2014 Hulett & Associates, LLC


50
JCL Results are on Indicated Contour Line
79%

$58,000,000 9% 12%

$56,000,000

$54,000,000

Joint time-cost
$52,000,000

probability = 70%
$50,000,000

$48,000,000
Entire Plan: Cost

$46,000,000 79%
$46,103,883

$44,000,000

$42,000,000

$40,000,000

$38,000,000

$36,000,000

$34,000,000

$32,000,000 70% 04 Jan 13 9%

02 Aug 12 21 Sep 12 10 Nov 12 30 Dec 12 18 Feb 13 09 Apr 13 29 May 13


Entire Plan: Finish

Time – Cost correlation is 69%

© 2014 Hulett & Associates, LLC


51
THANK YOU!

© 2014 Hulett & Associates, LLC


52
Integrated Cost – Schedule Risk Analysis
Using the Risk Driver Approach

Qatar PMI Meeting


February 19, 2014

David T. Hulett, Ph.D.


Hulett & Associates, LLC

© 2014 Hulett & Associates, LLC


53

También podría gustarte