Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Typical schedule risk analysis starts with the activity that is impacted
by risks
– Estimates the 3-point estimate for optimistic, most likely and
pessimistic duration
– Creates a probability distribution for activity duration
– Performs Monte Carlo simulation
What causes the most overall schedule risk? These questions are
answered in the 3-point estimate approach by looking to the impacted
activities:
– Sensitivity to activity durations
– Criticality of activity durations
Can tell which activities are crucial, but not directly which
risks are driving
Makes poor use of the Risk Register that is usually available
Cannot decompose the overall schedule risk into its
components BY RISK
– Ability to assign the risk to its specific risk drivers helps with
communication of risk causes and risk mitigation
Drive the schedule risk by the risks already analyzed in the Risk
Register – Root Causes
For each risk, specify:
– Probability it will occur
– Impact on time if it does
– Activities it will affect
Starting with the risks themselves gives us benefits
– Links qualitative analysis to the quantitative analysis
– Estimates the impact of specific risks for prioritized mitigation purposes
– Correlations between activities happen automatically – never have to
guess at these coefficients again, never get impossible matrices
65% 104
Cumulative Frequency
60% 103
250
55% 102
Plan.
Hits
50% 101
200
Probability is
45% 101
40% 100
30% 99
25% 98
100
20% 97
15% 96
50
10% 95
5% 94
0 0% 90
90 95 100 105 110 115
Distribution (start of interval)
Spike
Entire Plan : Duration Entire Plan : Duration
100% 130 100% 114
contains
3500
85% 118 85% 101
40% of
1800
Cumulative Frequency
2500
probability
60% 110 60% 100
1200
55% 109 55% 100
Hits
Hits
50% 107 2000 50% 100
1000
45% 106 45% 100
5% 100 5% 97
0 0% 100 0 0% 90
100 105 110 115 120 125 130 90 95 100 105 110 115
Distribution (start of interval) Distribution (start of interval)
Risk 1 1.2 factor Risk 2 1.05 factor Use (1.2 x 1.05 = 1.26)
Factor, multiply the two
If these two risks are series, they can not be
recovered simultaneously
85% 124
220
80% 123
Risks in
70% 119
180
65% 118
series, P80
Cumulative Frequency
160 60% 117
is 123 days
55% 116
140
Hits
50% 115
40% 112
100
35% 111
80 30% 110
25% 109
60
20% 108
40 15% 106
10% 104
20
5% 102
0 0% 92
100 110 120 130 140
Distribution (start of interval)
95% 125
85% 121
80% 119
300
75% 118
70% 117
Cumulative Frequency
60% 115
55% 114
Risks in
Hits
200
50% 113
45% 112
is 119 days
35% 111
30% 110
20% 108
15% 107
50
10% 106
5% 105
0 0% 100
100 105 110 115 120 125 130
Distribution (start of interval)
90% 119
1600
[60% x 50% =
Cumulative Frequency
60% 107
50% 103
days is picked
40% 100
35% 100
600
occur.
25% 100
400
20% 100
15% 100
200
10% 99
5% 96
0 0% 90
90 100 110 120 130 140
Distribution (start of interval)
80% 113
range of 100%, it
1800
75% 111
70% 110
Cumulative Frequency
1400 60% 107
100 days
55% 105
Hits
45% 101
1000
40% 100
35% 100
800
30% 100
20% 100
400
15% 100
10% 100
200
5% 100
0 0% 100
100 105 110 115 120 125 130
Distribution (start of interval)
Activity 1 Activity 2
Correlation = 100%
Risk 3: Risk Probability = Risk 1: Risk Probability = .5, Risk 2: Risk Probability =
.25, Range .95, 1.05, 1.15 .45,
Range .8, .95, 1.05 Range 1.0, 1.10, 1.20
Activity 1 Activity 2
Correlation = 37%
Risk 1 is more
important since it
affects both Activity
A and Activity B
Risk
Risk
“Burn Rate” per day Time Independent Costs
Schedule Risk
Time-Dependent
Costs Project
Cost Risk
© 2014 Hulett & Associates, LLC
23
Use a Case Study to Illustrate the
Integration of Cost and Schedule Risk
Case Study is a simplified schedule of an off-shore gas
production project including approval process, drilling,
fabrication of the jacket and the topsides (modules),
installation of same, and commissioning. Use Risk Drivers
approach
Results include:
– Schedule risk and cost risk histograms and cumulative distributions
– Prioritizing risks to time and to cost
– Scatter diagram of cost and time
– Probabilistic cash flow
95% 05 Jul 16
700
90% 28 Jun 16
650
85% 23 Jun 16
550
75% 15 Jun 16 Baseline schedule date is
500
70% 13 Jun 16
20MAR16
P-80 is 19JUN16
65% 10 Jun 16
Cumulative Frequency
55% 04 Jun 16
400
Hits
50% 01 Jun 16
350
45% 30 May 16
35% 25 May 16
250
30% 22 May 16
200
25% 19 May 16
15% 12 May 16
100
10% 07 May 16
50
5% 29 Apr 16
0 0% 31 Mar 16
27 Apr 16 16 Jun 16 05 Aug 16
Distribution (start of interval)
90% $1,514,498.07
80% $1,509,587.33
700
75% $1,507,756.29 Baseline cost is $1,473 million
70% $1,506,215.40
Cost at the P-80 is $1,509
million
65% $1,504,792.58
600
60% $1,503,339.04
Cumulative Frequency
55% $1,501,853.33
500
Hits
50% $1,500,395.02
45% $1,498,929.53
400
40% $1,497,468.96
35% $1,496,002.91
300
30% $1,494,469.13
25% $1,492,865.71
200
20% $1,491,069.27
15% $1,488,845.49
5% $1,482,293.69
0 0% $1,465,837.51
$1,470,000.00 $1,480,000.00 $1,490,000.00 $1,500,000.00 $1,510,000.00 $1,520,000.00 $1,530,000.00
Distribution (start of interval)
These data are derived during in-depth interviews with project participants and
others. The interviews focus on the Risk Register risks that are designated “high
risk” for time and cost. Use Primavera risk Analysis Risk Factor capability
© 2014 Hulett & Associates, LLC
32
Assignment of Risk Drivers to Activities
Risk Driver Activity Assignment
Schedule Maturity X X X X X X X
95% 14 Mar 17
80% 06 Jan 17
300
75% 24 Dec 16
Inherent
250 65% 30 Nov 16
60% 20 Nov 16
Cumulative Frequency
uncertainty was 200
55% 13 Nov 16
Hits
19JUN16
50% 04 Nov 16
45% 26 Oct 16
40% 17 Oct 16
150
30% 29 Sep 16
9.5 months
15% 22 Aug 16
50
10% 31 Jul 16
5% 02 Jul 16
0 0% 22 Apr 16
27 Apr 16 05 Aug 16 13 Nov 16 21 Feb 17 01 Jun 17
Distribution (start of interval)
Duration to
85% 2214
300
80% 2198
1,020 days
250 70% 2172
65% 2161
60% 2151
Cumulative Frequency
200 55% 2144
Hits
50% 2135
45% 2126
150
40% 2117
35% 2108
30% 2099
100
25% 2088
20% 2076
15% 2061
50
10% 2039
5% 2010
0 0% 1939
2000 2100 2200 2300 2400
Distribution (start of interval)
The order of risks is the best order at each step in this table. However, because of
the schedule’s structure some “Days Saved” values show inversion.
© 2014 Hulett & Associates, LLC
38
Picture of
Taking Risks out in Priority Order
100%
90%
Variation:91 Variation:7
Variation:5 Variation:96 Variation:40 Variation:51
80%
70%
Cumulative Probability
60%
50%
40%
30%
Variation:58 Variation:3
Variation:5
Variation:19 Variation:35 Variation:50
20%
10%
0%
Mar 16 10 May 16 29 Jun 16 18 Aug 16 07 Oct 16 26 Nov 16 15 Jan 17 06 Mar 17 25 Apr 17 14 Jun 17
$ millions
80% $1,735,644.11
uncertainty P-80 is
300
70% $1,707,918.39
$1,509 million
65% $1,695,182.86
Cumulative Frequency
55% $1,676,312.18
50% $1,666,546.42
200
P-80 Cost
45% $1,655,388.88
40% $1,645,807.52
25% $1,612,911.88
100
20% $1,599,905.70
15% $1,585,976.57
50
10% $1,567,102.71
5% $1,541,499.20
0 0% $1,449,663.64
$1,500,000.00 $1,600,000.00 $1,700,000.00 $1,800,000.00 $1,900,000.00
Distribution (start of interval)
40% of the risk to cost comes from risk to schedule, common finding
90%
Variation:$36,405.11
Variation:$1,591.31
Variation:$2,545.46
Variation:$5,243.00
Variation:$6,183.49
Variation:$24,925.51 Variation:$73,651.85 Variation:$54,652.75 Variation:$57,033.29
80%
70%
Cumulative Probability
60%
50%
40%
30%
Variation:$17,479.27
Variation:$1,236.17
Variation:$596.69
Variation:$1,643.69
Variation:$3,382.76
Variation:$9,374.08
Variation:$19,916.13
Variation:$33,986.87 Variation:$39,083.92
20%
10%
0%
$1,500,000.00 $1,550,000.00 $1,600,000.00 $1,650,000.00 $1,700,000.00 $1,750,000.00 $1,800,000.00 $1,850,000.00 $1,900,000.00
82%
11% 7%
$1,900,000.00
$1,850,000.00
$1,800,000.00
$1,750,000.00
82%
Entire Plan: Cost
$1,741,677.83
$1,700,000.00
$1,650,000.00
$1,600,000.00
PLAN $1,550,000.00
$1,500,000.00
Scheduled P80
2,000,000
1,800,000
1,600,000
Cumulative
terministic Cost: $1,473,445.00
1,400,000
1,200,000
Monthly Cash
Flow
Cumulative
Deterministic Finish: 20 Mar 16
- P-80
1,000,000
800,000
- Planned
600,000
400,000
200,000
0
13 Jan 13 23 Apr 13 01 Aug 13 09 Nov 13 17 Feb 14 28 May 14 05 Sep 14 14 Dec 14 24 Mar 15 02 Jul 15 10 Oct 15 18 Jan 16 27 Apr 16 05 Aug 16 13 Nov 16 21 Feb 17 01 Jun 17
Time
Spending $35 million for Engineers’ salary is assessed to reduce the probability of this risk
from 85% to 20%. Because the schedule slippage is 53 days less than before, there is $21
million we do not need to reserve and so the net cost impact of the mitigation at the P-80 is
offset by $21 million, for a net cost of $14 million. 48
© 2014 Hulett & Associates, LLC
NASA Joint Confidence Level (JCL) defined
$58,000,000 9% 12%
$56,000,000
$54,000,000
Joint time-cost
$52,000,000
probability = 70%
$50,000,000
$48,000,000
Entire Plan: Cost
$46,000,000 79%
$46,103,883
$44,000,000
$42,000,000
$40,000,000
$38,000,000
$36,000,000
$34,000,000