Está en la página 1de 8

IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 52, NO.

3, MAY/JUNE 2016 1945

Optimal Energy Management in an Industrial Plant


Using On-Site Generation and Demand Scheduling
Moein Choobineh, Student Member, IEEE, and Salman Mohagheghi, Senior Member, IEEE

Abstract—Fierce global competition and reduced profit margins Pi Workstation i rated power, i.e., power consumed
are forcing many manufacturing plants to maximize their opera- by workstation i when working at full capacity
tional efficiency. This includes the consumption of energy across (kW).
the plant as well as the inventory buildup. To reduce the cost of
energy purchased from the electric utility, the plant operator may P b,max Battery capacity (kW).
use the available on-site generation or reschedule the operation of Pts Power available from solar resource at time
one or more workstations so that the plant is less heavily opera- period t (kW).
tional during peak-load hours when the price of electricity is high. P u,max Maximum power available from the utility (kW).
All this must be done while considering the interdependencies rtb Revenue from selling battery power to the utility
between various workstations as well as the target production level
(and possible penalties in case it is not met). These factors turn the at time period t ($/kWh).
energy management problem into a constrained optimization one rtDR Revenue from participating in demand response
where the operational constraints of the workstations, the capacity (DR) at time period t ($/kWh).
limits of available energy resources, and the financial information rts Revenue from selling solar power to the utility at
are all taken into account. Developing such a solution is the focus of time period t ($/kWh).
this current paper. A nonlinear mixed-integer optimization prob-
lem is formulated here that tries to optimize the performance of SOCb,max Maximum acceptable state of charge (SOC) for
an industrial plant subject to the above operational and techni- battery.
cal constraints. The problem is solved for two scenarios, when the SOCb,min Minimum acceptable SOC for battery.
reverse power injection by the plant is allowed and when it is not. t Time index.
I des Desired production level of the plant (number of
Index Terms—Demand response (DR), demand scheduling, dis-
tributed energy resources (DERs), energy management, energy units, volume, or weight produced); this can be
storage, factory automation, industrial plant operation. viewed as the postprocess inventory of the final
workstation.
vij Binary parameter indicating whether workstation
N OMENCLATURE i is directly supplied from workstation j, i.e.,
Parameters uses its product (= 1: if i is connected to j, 0:
cbt Cost of power provided by the battery at time otherwise).
period t ($/kWh). αi Factor relating the number of
cut Cost of power provided by the utility at time units/volume/weight produced by workstation i
period t ($/kWh). to the power consumed by it
i, j Workstation index. (number of units/kW, m3 /kW, or kg/kW).
Iimax Maximum acceptable postprocess inventory for δ Battery discharge rate (p.u.).
workstation i (number of units, volume, and η b,c Charging efficiency for battery.
weight). η b,d Discharging efficiency for battery.
Iimin Minimum acceptable postprocess inventory for π Penalty due to unfulfilled order
workstation i (number of units, volume, and ($/unit, $/m3 , $/kg).
weight). ρ Revenue of end product ($/unit, $/m3 , $/kg).
n Number of workstations, and the index for the
last workstation that produces the final product. Variables
Ii,t Postprocess inventory at the output of
Manuscript received June 22, 2015; accepted November 3, 2015. Date of workstation i at time period t (number of units,
publication December 22, 2015; date of current version May 18, 2016. Paper volume, and weight).
2015-ESC-0457, presented at the 2015 IEEE Industry Applications Society Ptb,c Power provided to charge the battery at time
Annual Meeting, Addision, TX, USA, October 18–22, and approved for pub- period t (kW).
lication in the IEEE T RANSACTIONS ON I NDUSTRY A PPLICATIONS by the
Energy Systems Committee of the IEEE Industry Applications Society. Ptb,d Power discharged by the battery at time period
The authors are with the Electrical Engineering and Computer Science t (kW).
Department, Colorado School of Mines, Golden, CO 80401 USA (e-mail: Ptb,p Battery power provided to the plant at time
mchoobin@mines.edu; smohaghe@mines.edu).
period t (kW).
Color versions of one or more of the figures in this paper are available online
at http://ieeexplore.ieee.org. Ptb,u Battery power sold to the utility at time period
Digital Object Identifier 10.1109/TIA.2015.2511094 t (kW).
0093-9994 © 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
1946 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 52, NO. 3, MAY/JUNE 2016

Pts,b PV power provided to charge the battery at the utility during peak-load hours when the utility may be fac-
time period t (kW). ing shortage of supply. This changes the notion of power flow
Pts,p PV power provided to the plant at time period t from the traditional unidirectional scheme (i.e., from the utility
(kW). to the load) to one that allows a bidirectional exchange of power
Pts,u PV power sold to the utility at time period t between the utility and the plant. Plant energy management sys-
(kW). tem (EMS) would then have to determine the most economical
Ptu,b Utility power provided to the battery at time and efficient course of action at each point in time.
period t (kW). In addition to on-site DER, plant operators can take advan-
Ptu,p Utility power provided to the plant at time tage of demand scheduling to increase the efficiency of the
period t (kW). plant. Here, the objective is to schedule the operation times of
SOCbt SOC of battery at time period t. various workstations in order to minimize energy consumption,
ub,c Binary variable indicating that the battery is wasted labor, and/or wasted materials. In the literature, different
t
being charged at time period t (= 1 : charged, objective functions have been defined for real-time schedul-
0: not being charged). ing of loads in an industrial plant. El-Metwally et al. [7] used
ub,d Binary variable indicating that the battery is actions such as demand shifting and peak shaving to improve
t
being discharged at time period the load factor of the plant. Others have tried to optimally allo-
t(= 1 : discharged, 0: not being discharged). cate resources to loads [8], [9]. For instance, Subramanian et al.
ui,t Integer variable indicating the operational level [8] modeled deferrable loads as tasks with attributes such as
of workstation i at time period t, arrival time, departure time, and energy requirements, and pro-
ui,t ∈ 0, . . . , 4 which is used to indicate posed algorithms for resource allocation to these tasks based
operation at 0%, 25%, 50%, 75%, and 100% of on their energy needs and/or deadlines. Matching the overall
rated capacity, respectively. load profile with a specific target load profile has also been
u∗i,t Integer variable indicating the operational level defined as an objective for load shifting [10]. From a differ-
of workstation i at time period t under nominal ent aspect, Dobrin et al. [11] combined offline scheduling and
operation (i.e., no DR). fixed-priority scheduling to achieve flexibility while coping
β Unfulfilled orders; shortage in production level with complex timings of different tasks. Industrial load schedul-
of the last workstation compared to the desired ing has also been addressed with the goal of minimizing the
level (number of units, m3 , kg). total cost of energy [12], [13].
In addition to demand scheduling, DR is becoming an impor-
tant feature of the modern power and energy systems [14]. DR
can be initiated by the utility in the form of demand reduction
signals/commands, or can be initiated by the plant itself, i.e.,
I. I NTRODUCTION
in the form of capacity relief to be sold to the utility. It is a

E NERGY efficiency is an integral part of the operation


of an industrial plant. Ideally, the plant operator would
like to maximize the production level (and hence the revenues
voluntary form of load shedding that is performed in exchange
for financial incentives. Even though much of focus in DR is
on the residential and commercial sectors, many utilities are
gained) while minimizing the energy consumption, the inter- gaining more interest in engaging the industrial sector in this
ruption in production, the material waste, and the inventory opportunity. This is mostly due to the potentially large amount
buildup, to name a few. These may at times behave as contra- of congestion relief that could be made available through these
dictory objective functions in a sense that optimizing one could customers. In many utilities, industrial loads account for around
result in suboptimal solutions for one or more others. As such, 2%–10% of the total number of customers, but consume up to
optimal operation of the plant requires solving a comprehensive 70%–80% of the total power generated by the utility [15], [16].
multiobjective optimization model that takes various elements To determine the effect of demand scheduling on the opera-
into account. tion of an industrial plant, different constraints will have to be
Many researchers have focused on using on-site distributed considered. One of the most critical constraints is the inven-
energy resources (DERs) to improve the reliability of the plant, tory buildup across the plant, which is directly translated into
while reducing the operational costs [1]–[4]. These DER units wasted material. Naturally, demand scheduling can cause an
can shield the plant from unexpected loss of service or power increase in the work-in-process inventory. In order to determine
quality issues originated on the utility side [5]. In the most the capital value of this inventory buildup, the products can be
general case, DERs can be distributed generation (DG) units divided into three different categories: A, B, and C [17]. The
or energy storage systems (ESSs). The former can be further products in the A category have the highest value in the orga-
classified as dispatchable units, e.g., diesel engines that can fol- nization. The B category also consists of important products,
low generation set-point commands, or nondispatchable ones, but is less strictly monitored. And the third category C is rel-
e.g., solar and small scale wind turbines that typically oper- atively less important than the other two; although, it usually
ate based on maximum power point tracking (MPPT) [6]. In has larger quantities. This categorization can facilitate the selec-
either case, the power available through these units can be tion of workstations for demand curtailment [18]. Another set
used to supplement the power purchased from the utility dur- of constraints that should be considered prior to implementa-
ing the hours of peak energy prices or to sell power back to tion of demand scheduling relates to the characteristics of the
CHOOBINEH AND MOHAGHEGHI: OPTIMAL ENERGY MANAGEMENT IN AN INDUSTRIAL PLANT 1947

workstations. These may include the capacity of the worksta-


tion (products processed per unit of time), the layout of the
workstations (series or parallel), and the number and skill lev-
els of crew members working on the workstation. For instance,
shifting the operation of a workstation in a series layout to a
later time may have more adverse effects on the plant operation
than in a parallel layout [19]. Likewise, rescheduling a worksta-
tion with a large number of specifically trained skilled workers
can lead to wasted labor.
Finally, demand curtailment could be considered as an alter-
native. Intelligent load shedding in an industrial plant has been
addressed using priority ranking of the loads [7], expert sys-
tems [20], [21], and neural networks [22]. Also, solutions have
been proposed for demand conservation through demand side
management (DSM) techniques [23].
The objective of this paper is to devise a solution for optimal
energy management in an industrial plant using all poten-
tial resources of energy. To achieve this, the solution will
take advantage of any available on-site generation, as well as
scheduling of different workstations. The ultimate objective is
to maximize the financial profits by the plant while the target Fig. 1. Schematic diagram of the proposed solution.
production is met as closely as possible and the operational con-
straints are all maintained. A case study is presented using a and a battery system as energy storage. Naturally, other types
simplified layout for a vehicle cockpit assembly plant in order of DER units can be added without changing the nature of the
to demonstrate the applicability of the proposed methodology. problem.

B. Problem Formulation
II. P ROPOSED M ETHODOLOGY
The objective function of the optimization problem can be
A. Overall Scheme expressed as follows:
Fig. 1 illustrates the schematic diagram of the proposed solu- ⎧ T

⎪ ρ t=1 un,t αn P4n − π · β
tion for energy management. The energy management module ⎪
⎪ T T

⎪ b b,u s s,u
needs access to the plant configuration and the layout of the ⎨+ t=1 rt Pt + t=1 rt Pt 
T n ∗
workstations. This information is needed in order to model Max + t=1 rtDR i=1 4 (ui,t − ui,t ) +
Pi
(1)

⎪ T u u,b
the interdependencies between the workstations. Financial data ⎪
⎪− t=1 ct (Pt + Pt )
u,p


are also necessary, and could be provided by the plant opera- ⎩ T b b,p
− t=1 ct (Pt + Ptb,u )
tor as well as the electric utility. These may include the cost
of purchasing electricity from the utility, revenue from poten- where the first row represents the profit made due to plant’s
tial injection of power into the utility’s network, revenue from production and the possible penalty due to failure in meeting
participation in DR, and the O&M cost of using the on-site the target production level, the second row represents the rev-
generation and storage. Other relevant information could be enue from selling battery power and solar power to the electric
the profit gained from selling each unit of final product (unit, utility, the third row represents the revenue due to participating
weight, or volume), and the possible penalties due to failure to in the DR program and is nonzero only if the plant reduces its
fulfill the desired production. It is also crucial for the module to consumption compared to the nominal operation, the fourth row
receive updated data from the field. These could be the genera- is the cost of purchasing power from the utility, and the last row
tion status of the plant energy resources, the charge/discharge indicates the operational cost of discharging the battery power
status of the ESS, the inventory buildup status at the output either to provide power to the utility or to the plant. This is a
of each individual workstation, and suchlike. This information constrained optimization problem that is solved subject to the
can be obtained from the remote terminal units (RTUs) that are following constraints.
installed across the plant working as a communication gateway 1) Power balance for the workstations: This constraint
to the industrial automation system. ensures that the power provided to the plant from vari-
Upon receiving all necessary information, the energy man- ous resources is sufficient for running the workstations at
agement module determines the most cost-effective operation the intended capacities
schedule by solving an optimization problem. This output will n Pi
be provided to the plant operator who then decides whether or ∀t : Ptu,p + Ptb,p + Pts,p = ui,t . (2)
i=1 4
not to implement it.
In Section II-B, without loss of generality, it has been 2) Power balance for the power available from PV: The
assumed that the plant has a PV panel as the generation resource power available from this resource may be used to
1948 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 52, NO. 3, MAY/JUNE 2016

supply the workstations, charge the battery, or sell to the 7) Postprocess inventory constraints: These indicate the
utility accumulation of postprocess inventory based on the inter-
relationships between workstations. In addition, individ-
∀t : Pts,u + Pts,p + Pts,b = Pts . (3)
ual workstations will have upper and lower limits for the
3) Upper limit for the power available from the utility: The acceptable amount of postprocess inventory. A nonzero
power that can be purchased from the electric utility may value for I min moves the process further away from a just-
be constrained by the physical limitations of the feeder in-time (JIT) manufacturing strategy. It should be noted
supplying the plant (e.g., rating of the distribution line, that depending on the units defined for the output of each
rating of the transformer, etc.) or due to the existing product, one can consider the postprocess inventory to be
contract with the utility a discrete or a continuous variable
∀t : Ptu,p + Ptu,b ≤ P u,max . (4) Pi
n
Pj
∀(i, t) : Ii,t = Ii,t−1 + αi ui,t − αj uj,t vji
4) Battery operational constraints: Constraints (5) and (6) 4 4
j=1,=i
indicate that the battery can be charged by the power (13)
available through the utility or the PV resource, and its
discharge power can be used to supply the workstations ∀(i, t) : Iimin ≤ Ii,t ≤ Iimax . (14)
or to sell power to the utility. In addition, the discharge
8) Unfulfilled orders: Ideally, the plant manager would like
power of the battery is limited by its capacity [see (7)].
to meet the target production level. However, to allow
The battery can be either charging or discharging at any
the plant to take advantage of selling power to the util-
point in time, but not both [see (8)]. Constraint (9) pro-
ity, DR, and/or demand shifting, this constraint is relaxed.
vides an equality constraint for the SOC of the battery,
Of course, the shortage in meeting the demand leads to
and (10) expresses the desired range for the SOC of the
penalties, as indicated in the objective function
battery
T Pn
∀t : Pts,b + Ptu,b = ub,c
t Pt
b,c
(5) αn un,t = I des − β (15)
t=1 4
∀t : Ptb,p + Ptb,u = ub,d
t Pt
b,d
(6) β ≥ 0. (16)
∀t : Ptb,p + Ptb,u ≤ P b,max (7)
9) Non-negativity and integrality constraints
∀t : ub,c b,d
t + ut ≤ 1 (8)
⎧ ∀t : Ptb,p , Ptb,u , Pts,b , Pts,p , Pts,u , Ptu,b , Ptu,p ≥ 0 (17)

⎨(1 − δ) · SOCt−1
b
∀(i, t) : ui,t ∈ {0, 1, 2, 3, 4} (18)
∀t:SOCt = +ut (Pt η /P b,max )
b b,c b,c b,c
(9)

⎩ b,d b,d b,d b,max ∀(i, t) : Ii,t ≥ 0 (19)
−ut (Pt /η P )
∀t : ub,c b,d
t , ut ∈ {0, 1}. (20)
∀t : SOCb,min ≤ SOCbt ≤ SOCb,max . (10)
5) Reverse power flow: It has been assumed here that the
plant can either purchase power from the utility or sell III. C ASE S TUDY
power to the utility, but not both at the same time. In order The proposed methodology is applied to a simplified version
to ensure both conditions do not occur simultaneously, of an industrial manufacturing plant for luxury vehicle cock-
(11) has been added as an additional constraint. It should pit assembly [18]. The schematic diagram of the plant layout
be noted that all power terms in (11) are non-negative is illustrated in Fig. 2. The plant consists of multiple worksta-
∀t : (Ptb,u + Pts,u ) · (Ptu,b + Ptu,p ) = 0. (11) tions that are arranged in series. The problem is solved under
two scenarios: 1) the utility does not allow the plant to inject
6) Workstation interdependencies: In a series configuration, power back into the utility’s network and 2) reverse power flow
if workstation i depends on workstation j’s product (i.e., is allowed. The problem is solved for 10 one-hour time steps,
if vij = 1), then at any point in time, its production level assuming a workday starting from 8:00 A . M . to 6:00 P. M. It is
would be limited by how much product workstation j has solved using the LINDO solver in the GAMS software.
produced until that time, and how much of it has been
consumed by workstation i during the previous time steps
(see Section V-A for a general discussion on this issue). A. Input Data
This constraint allows for modeling demand shifting to a Workstation data and battery data are provided in Tables I
later time if necessary, i.e., dynamic demand scheduling and II. The forecasted solar power available at the plant is
α i Pi assumed to be following the diagram in Fig. 3. It is assumed
∀(i, τ ) : ui,τ

4
that the maximum power that can be delivered to the plant by

τ −1 the utility is 650 kW. This can be a limitation enforced by the
α j Pj α j Pj α i Pi
≤ vij uj,τ + uj,t − ui,t . transformer or the feeder supplying the plant.
4 4 4
t=0 It is also assumed that the desired number of vehicle cockpits
(12) to be manufactured by the plant is 30. Each unit will be sold at
CHOOBINEH AND MOHAGHEGHI: OPTIMAL ENERGY MANAGEMENT IN AN INDUSTRIAL PLANT 1949

Fig. 3. Forecasted solar power available at the plant.

Fig. 2. Schematic diagram of the luxury vehicle cockpit assembly line. The
external input inventory for the workstations is not considered here.

TABLE I
BATTERY DATA

TABLE II
W ORKSTATION DATA

Fig. 4. Cost of energy resources and revenue from selling power to utility.

B. Case Study 1: No Reverse Power Flow


In this case study, the plant is not allowed to sell power back
to the utility; therefore, any excess power must be used for inter-
nal consumption or to charge the battery. To find the optimal
schedule, (1) is solved subject to (2)–(20), where the following
constraint is also added to ensure reverse power flow does not
occur
a price of $30 000. The cost of each unfulfilled order to the
plant is $2000. Also, it has been assumed that at the start of the ∀t : Ptb,u = Pts,u = 0. (21)
day, all workstations, except for the final one, have an initial
postprocess inventory of 10 units. Figs. 5 and 6 illustrate the results. It can be seen that the
Fig. 4 illustrates the cost and revenue of power exchanges. energy management module uses the solar power to charge the
These values are used for demonstration purposes only. battery, to then use it at hour 7 when the price of electricity is
Changing the numbers may change the output of the problem, higher. The workstations are used throughout the day, although
but does not affect its structure. It can be seen that the cost with heavier loading during the times of lower electricity rates
of electricity purchased from the utility follows a critical peak (hours 1–6).
pricing (CPP) scheme, whereas the revenue obtained from sell-
ing power to the utility follows a two-peak model. The utility
C. Case Study 2: With Reverse Power Flow
buys power at higher rates during the peak-load hours; however,
during low load conditions, it purchases power at a lower rate Here, the plant is allowed to sell power back to the utility.
than what it charges the customers. The cost of power provided To find the optimal dispatch, (1) is solved subject to (2)–(20).
by the battery is assumed to be a constant 0.07$/kWh, as it Figs. 7 and 8 illustrate the results. It can be seen that under
relates to the loss of life of battery due to each additional charge energy buyback scenario, the energy management module shifts
and discharge cycle. No cost is assumed for the PV panel. all the loads to the early hours. From hour 7 onwards, the plant
1950 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 52, NO. 3, MAY/JUNE 2016

Fig. 5. Power provided by various generation resources under case study 1. Fig. 7. Power provided by various generation resources under case study 2.

Fig. 8. Operational statuses of the workstations under case study 2.


Fig. 6. Operational statuses of the workstations under case study 1.
TABLE III
P LANT P RODUCTION DATA

starts selling all its available power from the battery and the PV
to the utility. This is expected since the power selling revenue
is very high during this period. This also helps the utility since
the load of the plant is taken off its network during peak-load
conditions.
Table III lists the total number of units processed by the last
workstation, which indicates the final product manufactured by
the plant. It can be seen that in both case studies, the plant ends
up manufacturing 15 units; however, with reverse power flow D. Case Study 3: Reverse Power Flow and DR
allowed, the energy management module pushes most of the In the final case study, it has been assumed that the plant is
production to the early hours. The total revenue gained by the allowed to participate in a DR program with the utility. Upon
plant (for selling the product and, if applicable, selling power reducing the overall energy consumption compared to the nor-
to the utility) along with the costs to the plant (due to unful- mal operation (case study 1 or 2), the plant receives a revenue
filled orders and cost of purchasing electricity) is also listed. [see (1)]. For demonstration purposes, the revenue from DR
The difference in the revenue in the two cases is in part related rtDR is assumed to be 125% of rts and rtb .
to the power sold to the utility. It should be noted that the dif- It should be noted here that DR can be implemented and ver-
ference between the target production (30) and final production ified in variety of ways [14]. Here, it has been assumed that the
(15) is mostly determined based on the cost of producing each plant seeks ways to reduce its demand from nominal operation
additional unit and the penalties due to each unfulfilled order. (no DR) and upon finding the appropriate operation schedule,
Variations in the cost of electricity, the profit gained from each will reduce its consumption and notify the utility. How to verify
unit, and/or the penalties for production shortage could change that the plant has in fact reduced its demand and how to identify
the final production. the nominal (no DR) consumption for comparison are issues
CHOOBINEH AND MOHAGHEGHI: OPTIMAL ENERGY MANAGEMENT IN AN INDUSTRIAL PLANT 1951

TABLE IV
P LANT P RODUCTION DATA

Table IV lists the corresponding plant production data. For


better comparison, the results when no reverse power flow is
allowed have also been reported.

IV. P RACTICAL C ONSIDERATIONS


Fig. 9. Power provided by various generation resources under case study 3. A. Workstation Configurations
A series configuration was assumed in this paper for demon-
stration purposes. However, many plants have more compli-
cated layouts in which a workstation i may use the products of
more than one workstation. Here, the production level of work-
station i would depend on the amount of products available
from those workstations j ∈ Ji , and would naturally be limited
by the amount of product of the workstation with the low-
est available postprocess inventory. Mathematically, this can be
expressed as
α i Pi
∀(i, τ ) : ui,τ
4


τ −1 
α j Pj α j Pj α i Pi
≤ min vij uj,τ + uj,t − ui,t .
Fig. 10. Operational statuses of the workstations under case study 3. j∈Ji 4 t=0
4 4
(25)
that are determined by the bilateral contract between the utility
Clearly, the nonlinear constraint (25) can be rewritten as
and the plant. However, this aspect falls outside the scope of our
multiple linear inequality constraints, one for each j ∈ Ji .
current work and it has simply been assumed that the plant is
financially incentivized for any demand reduction with respect
to the nominal (no DR) operation. B. Solar Data
To model the nonlinear term in the third row of (1), the
following reformulation has been applied: Throughout the simulations in this paper, it was assumed
  that solar data are known in advance and can be forecasted
n Pi ∗ with accuracy. During days that are heavily windy and cloudy,
∀t : (ui,t − ui,t )
i=1 4 the accuracy of solar power forecast reduces. In this case, the
+
  energy management module may be forced to resolve the opti-
n Pi ∗ st (st + 1)
= (ui,t − ui,t ) (22) mization problem as soon as it is determined that the available
i=1 4 2
solar power at a future time step is different from what assumed
subject to the additional constraints earlier.
 
n Pi ∗
∀t : (ui,t − ui,t ) · st > 0 (23) V. C ONCLUDING R EMARKS
i=1 4

∀t : st ∈ {−1, 0, + 1}. (24) A solution was proposed in this paper for optimal energy
management across a manufacturing plant. It was assumed that
Figs. 9 and 10 summarize the results. Comparing Figs. 9 and the plant could take advantage of on-site generation, demand
7 shows that the energy management module takes advantage scheduling, and DR in order to maximize its profits. A non-
of both revenue options: selling power back to the utility and linear mixed-integer optimization problem was formulated that
reducing demand. Hence, workstation schedules are arranged balances the losses due to failure to meet the target produc-
around the time when the incentives from DR or reverse power tion level with the revenues gained from selling power back
flow are low. to the utility and participating in DR. Several case studies were
1952 IEEE TRANSACTIONS ON INDUSTRY APPLICATIONS, VOL. 52, NO. 3, MAY/JUNE 2016

presented with and without DR, and with and without the pos- [17] Y. Chen, K. W. Li, and S. F. Liu, “A comparative study on multicriteria
sibility to inject excess on-site generation back into the utility’s ABC analysis in inventory management,” in Proc. IEEE Int. Conf. Man
Mach. Cybern., Singapore, Oct. 2008, pp. 3280–3285.
network. [18] S. Mohagheghi and N. Raji, “Intelligent demand response scheme for
energy management of industrial systems,” in Proc. IEEE Ind. Appl. Soc.
(IAS) Annu. Meeting, Las Vegas, NV, USA, Oct. 2012, pp. 1–9.
R EFERENCES [19] S. Ghosh and R. J. Gagnon, “A comprehensive literature review and anal-
ysis of the design, balancing and scheduling of assembly systems,” Int. J.
[1] K. P. Papalexandri, E. N. Pistikopoulos, and B. Kalitventzeff, “Modelling Prod. Res., vol. 27, no. 4, pp. 637–670, 1989.
and optimization aspects in energy management and plant operation with [20] B. Delfino et al., “Operation and management of the electric system for
variable energy demands-application to industrial problems,” Comput. industrial plants: An expert system prototype for load-shedding operator
Chem. Eng., vol. 22, no. 9, pp. 1319–1333, 1998. assistance,” in Proc. IEEE Ind. Appl. Soc. (IAS) Annu. Meeting, Rome,
[2] L. Merkert, I. Harjunkoski, A. Isaksson, S. Synevirta, A. Saarela, and Italy, Aug. 2000, pp. 3260–3268.
G. Sand, “Scheduling and energy industrial challenges and opportuni- [21] F. Shokooh et al., “An intelligent load shedding system application in
ties,” Comput. Chem. Eng., vol. 72, pp. 183–198, 2015. a large industrial facility,” in Proc. IEEE Ind. Appl. Soc. (IAS) Annu.
[3] D. Q. Hung, N. Mithulananthan, and R. Bansal, “An optimal investment Meeting, Oct. 2005, pp. 417–425.
planning framework for multiple distributed generation units in industrial [22] C. T. Hsu, H. J. Chuang, and C. S. Chen, “Artificial neural network based
distribution systems,” Appl. Energy, vol. 124, no. 1, pp. 62–72, 2014. adaptive load shedding for an industrial cogeneration facility,” in Proc.
[4] R. M. Ciric and N. Rajakovic, “A new composite index of reliability of IEEE Ind. Appl. Soc. (IAS) Annu. Meeting, Oct. 2008, pp. 1–8.
supply in the industrial systems with distributed generation,” Int. J. Elect. [23] H. P. Inamdar and R. P. Hasabe, “IT based energy management through
Power Energy Syst., vol. 44, no. 1, pp. 824–831, 2013. demand side in the industrial sector,” in Proc. Int. Conf. Control Autom.
[5] T. Ackermann, G. Andersson, and L. Söder, “Distributed generation: A Commun. Energy Conserv., Jun. 2009, pp. 1–7.
definition,” Elect. Power Syst. Res., vol. 57, pp. 195–204, 2001.
[6] F. A. Farret and M. G. Simões, Integration of Alternative Sources of
Energy. Hoboken, NJ, USA: Wiley, 2006.
[7] M. M. El-Metwally, M. S. El-Sobki, H. A. Attia, and S. A. Wahdan, Moein Choobineh (S’15) was born in Mashhad, Iran.
“Priority ranking of industrial loads and application of demand side He received the B.Sc. degree in electrical engineer-
management technique,” in Proc. Int. Middle East Power Syst. Conf., ing from Ferdowsi University of Mashhad, Mashhad,
El-Minia, Egypt, Dec. 2006, pp. 341–346. Iran, in 2008, and the M.Sc. degree in power sys-
[8] A. Subramanian, M. Garcia, A. Domínguez-García, D. Callaway, tem engineering from Iran University of Science and
K. Poolla, and P. Varaiya, “Real-time scheduling of deferrable electric Technology, Tehran, Iran, in 2011. He is currently
loads,” in Proc. Amer. Control Conf., Montreal, QC, Canada, Jun. 2012, working toward the Ph.D. degree in electrical engi-
pp. 3643–3650. neering at the Colorado School of Mines, Golden,
[9] M. L. Della Vedova and T. Facchinetti, “Real-time scheduling for indus- CO, USA.
trial load management,” in Proc. IEEE Int. Energy Conf. Exhib., Florence, His research interests include power system opera-
Italy, Sep. 2012, pp. 707–713. tion under extreme events, energy management opti-
[10] G. O’Brien and R. Rajagopal, “A method for automatically scheduling mization, network restoration, microgrids, and electrical asset management.
notified deferrable loads,” in Proc. Amer. Control Conf., Washington, DC,
USA, Jun. 2013, pp. 5087–5092.
[11] R. Dobrin, G. Fohler, and P. Puschner, “Translating off-line schedules
into task attributes for fixed priority scheduling,” in Proc. IEEE Real-Time
Syst. Symp., London, U.K., Dec. 2001, pp. 225–234.
[12] K. Collins, M. Mallick, G. Volpe, and W. G. Morsi, “Smart energy moni-
toring and management system for industrial applications,” in Proc. IEEE
Elect. Power Energy Conf., London, ON, Canada, Oct. 2012, pp. 92–97.
[13] S. Bahrami, F. Khazaeli, and M. Parniani, “Industrial load scheduling Salman Mohagheghi (S’99–M’07–SM’14) received
in smart power grids,” in Proc. Int. Conf. Elect. Distrib., Stockholm, the B.Eng. degree from the University of Tehran,
Sweden, Jun. 2013, pp. 1–4. Tehran, Iran, in 1999, the M.Sc. degree from Sharif
[14] S. Mohagheghi, J. Stoupis, Z. Wang, Z. Li, and H. Kazemzadeh, University of Technology, Tehran, Iran, in 2001,
“Demand response architecture—Integration into the distribution man- and the Ph.D. degree from Georgia Institute of
agement system,” in Proc. 1st IEEE Int. Conf. Smart Grid Commun., Technology, Atlanta, GA, USA, in 2006, all in elec-
Gaithersburg, MD, USA, Oct. 2010, pp. 501–506. trical engineering.
[15] J. G. Roos and I. E. Lane, “Industrial power demand response analysis Currently, he is an Assistant Professor with
for one-part real-time pricing,” IEEE Trans. Power Syst., vol. 13, no. 1, the Electrical Engineering and Computer Science
pp. 159–164, Feb. 1998. Department, Colorado School of Mines, Golden, CO,
[16] Y. Tang, F. Xu, and L. Chen, “Research into possibility of smart industrial USA. Prior to that, he was a Senior R&D Engineer
load participating into demand response to supply the power system,” with the ABB Corporate Research Center, Raleigh, NC, USA. His research
in Proc. China Int. Conf. Electr. Distrib., Nanjing, China, Sep. 2010, interests include situational awareness, power system management under uncer-
pp. 1–5. tainties, communication networks in power systems, and automation systems.

También podría gustarte