FOREWORD
This Well Control Manual has been prepared to document the requirements of KCA DEUTAG with
respect to Well Control Management and assist in the implementation of proper Well Control
practices and procedures.
This document is not a Training Manual (for which the reader is referred to the KCA D EUTAG DART
Well Control Training Manual) and assumes the user has Well Control knowledge to the level of
IWCF or WellCAP. However, where appropriate, some theory and additional information has been
included such that all appropriate background information is included in one reference document.
The Manual has been based on the input from many sources, and has been agreed by
representatives of each Area and the E&M Function and therefore expressly documents KCA
DEUTAG’s mandatory requirements with respect to Well Control, together with additional
recommendations which should be considered for implementation on a local basis.
The manual is not intended to cover all possible well control eventualities and cannot replace sound
judgement based upon a thorough knowledge of well control principles or local knowledge of a
particular set of circumstances.
The custodian of this Manual is Training Department. Any recommendations for changes can be
made via the relevant General Manager to the Head of Training.
Brian Taylor
COO
CONTENTS
1 Responsibilities & Summary of Well Control Requirements .......................................... 6
1.1 Responsibilities ......................................................................................................... 6
1.2 Training Requirements.............................................................................................. 7
1.3 Compliance & Exemption Process ........................................................................... 8
1.4 Summary of Well Control Requirements .................................................................. 8
2 Well and Operational Planning ......................................................................................... 12
2.1 Well Planning .......................................................................................................... 12
2.1.1 General Considerations............................................................................................. 12
2.1.2 Bridging Documents .................................................................................................. 12
2.1.3 H2S Contingency Planning ........................................................................................ 12
2.1.4 Minimum Stock Levels .............................................................................................. 12
2.1.5 Formation Considerations ......................................................................................... 13
2.1.6 Shallow Gas .............................................................................................................. 16
3 Hardware Requirements ................................................................................................... 17
3.1 Kick Detection (Hardware) ...................................................................................... 17
3.2 Diverter Equipment Requirements.......................................................................... 18
3.2.1 Diverter Selection Criteria ......................................................................................... 18
3.2.2 Diverter Line Requirements....................................................................................... 18
3.2.3 Diverter Equipment Specifications ............................................................................ 19
3.3 Diverter Arrangements ............................................................................................ 19
3.4 BOP Equipment Classification and Selection ......................................................... 21
3.5 BOP Arrangements ................................................................................................. 23
3.5.1 BOP 13800 kPa 2000 psi without a Casing Spool .................................................... 23
3.5.2 BOP 20700 kPa 3000 psi 34500 kPa /5000 psi without a Casing Spool ................... 24
3.5.3 BOP 34500 kPa 5000 psi with a Casing Spool (Dual Ram option) ........................... 25
3.5.4 BOP 34500 kPa 5000 psi and/or 69000 kPa 10000 psi with Casing Spool ............... 26
3.5.5 BOP 103500 kPa 15000 psi. ..................................................................................... 27
3.6 Control System Requirements for Surface BOP Stacks ......................................... 28
3.7 BOP Testing requirements ..................................................................................... 28
3.7.1 Pressure Test Criteria. .............................................................................................. 28
3.7.2 Frequency of Testing ................................................................................................ 28
3.7.3 Accumulator and Control System Tests .................................................................... 29
3.8 General Maintenance Requirements for Wellhead and BOP Equipment ............... 29
4 Well Control Principles ..................................................................................................... 31
4.1 Barrier Policy........................................................................................................... 31
4.2 Primary Well Control ............................................................................................... 31
4.3 Secondary Well Control .......................................................................................... 31
4.4 Tertiary Well Control ............................................................................................... 32
During killing operation, follow the pumping schedule in accordance with the approved Surface BOP
Kill Sheet and Toolpusher's instructions. Record pressures; pump rate, volume pumped, and time.
Compare the actual parameters with the kill graph and if any significant changes alert the
Toolpusher.
Rig Superintendent or Toolpusher:
To maintain full control over the behaviour of the well to prevent blowout from happening. Notify the
Company Representative, the Mud Engineer, the Drilling Engineer and Rig Manager.
Evaluate borehole situation upon presumed influx. Select the most appropriate killing procedure
depending on the type of kick and hole size. Calculate his Surface BOP Kill Sheet and compare it
with the Driller's, the Company Representative's, and / or the Drilling Engineer's to avoid any
mistakes. Be in charge of the killing operation, controlling backpressure and timing.
To communicate with the Company Representative the BOP testing schedule, and the pressures
and intervals.
To instruct the Driller to which pressures the BOP must be tested according to the Drilling Program
and as agreed with the client.
Ensure the BOP manufacturer's engineering data for the specific equipment is readily available.
To be aware of the annular preventer closing pressures to retain wellbore pressure in order to
minimize excessive wear on the packer element particular when reciprocating the drillstring.
Drilling Engineer:
To assist the Toolpusher in evaluating borehole situation, calculate independently IWCF or WellCAP
Surface BOP Kill Sheet and compare same with the Toolpusher's. Assist the Toolpusher during
killing operations.
Rig Manager:
To approve the killing procedure proposed by the Toolpusher and Client.
Country & General Managers:
To assure themselves and the Company that the procedures outlined in this manual are adhered to
for all KCA DEUTAG rigs in his Country/Area.
1.2 Training Requirements
Formal Training & Certification
KCA DEUTAG requires that all personnel are to meet any statutory or contractual requirements
regarding Well Control Training. Where statutory or contractual requirements do not exist, or where
these are lower than KCA DEUTAG’s minimum standards, the KCA DEUTAG minimum training
requirements are as follows:
The following personnel must complete a Company approved Well Control training course (either
IWCF or WellCAP), in accordance with the KCA DEUTAG Training Matrices, and pass the associated
examination at least every 2 years:
Rig Managers
Rig Superintendents (Toolpushers)
Asst Rig Superintendents (Night Toolpushers)
Drillers
For MODU operations the OIM must also have appropriate Well Control Certification.
In many cases Client Contractual requirements will also require Assistant Drillers (and potentially
Derrickmen) to have Well Control certification.
Anybody operating the brake when formation pressures are in communication with the wellbore must
have current well control certification. Anybody operating the brake without well control certification
(only allowable when formation pressures isolated from the wellbore) must be directly supervised by
somebody with current well control certification.
Additional training may be required dependent upon the types of well to be drilled and any local
legislation or contractual requirements.
All crews must be trained ‘on the job’ through the regular use of kick drills which are to be conducted
in accordance with section 5.4 of this document.
1.3 Compliance & Exemption Process
The practices and procedures included in this Manual are minimum requirements and are not to be
reduced to comply with any governmental or Client requirements. The well control practices must,
however, be adjusted accordingly to comply with any more rigorous local regulations of either the
relevant local authorities or the Operator. Any changes or selection of alternatives to be used in a
well control situation must be documented in the Bridging Document.
Whilst the Manual dictates certain mandatory requirements, in other areas options or a preferred
procedure may be mentioned. In these cases the detailed local knowledge and expertise is to be
taken into account in determining which course of action will be instigated.
In this document the following terms are used to express a course of action:
“May” indicates one possible cause of action
“Should” indicates a preferred course of action
“Must” indicates a mandatory course of action (and is the equivalent of “shall”)
It is a requirement that all relevant KCA DEUTAG personnel must know of and comply with the
Company’s approved well control Standard and Procedures as included in this manual. It is the
responsibility of the Senior KCA DEUTAG Representative to assure implementation of the appropriate
Well Control practices and procedures.
If, for any reason, a mandatory requirement of this manual is deemed not appropriate for particular
circumstances a dispensation in accordance with the Operations Standards Dispensation Process
(CW-ALL00-DW-OP-ST-0002), is required from the Country Manager, after appropriate risk analysis
and justification.
Chemical Stocks
Sufficient stocks of barite, chemicals and associated additives must be on 2.1.4
location to allow for the weighting up of the mud system by 0.5 ppg (60
3 3
kg/m ) on development wells or 1 ppg (120 kg/m ) for exploration wells.
For offshore rigs and land rigs where logistics preclude a readily available
supply of cement, enough cement must be onsite to enable the setting of a
500 ft (150 m) cement plug in open hole.
Kick Tolerance
3 3
For kick tolerances of between 25 bbl (4m ) and 50 bbl (8m ) the Operations 2.1.5.6
Manager must be informed and any additional precautions implemented as
3
advised. For kick tolerances of below 25 bbl (4m ) the Country Manager
must be advised.
BOP Arrangements
Adequate redundancy must be in place in keeping with the equipment 3.5
specifications, the well programme and emergency contingencies.
Shear rams installed must be capable of shearing the pipe in use. If they 3.4, 3.5, 3.8
cannot they must only be used as blind rams with a notice to that effect
posted on the drillfloor and the Country Manager must also be informed.
Correct BOP equipment must always be installed on the well, be operational 3.5
and in an arrangement suitable for the specific application
Automatic MAASP controls must be disabled. 2.1.5.5
BOP Testing
BOP Testing must be undertaken under the direct supervision of the Rig 3.7.1
BOP Maintenance
Routine BOP maintenance must be undertaken in accordance with this 3.8
manual, approved PMRs, and at the specified frequency of the approved
PMRs
All BOP equipment is to be overhauled every 5 years
Manufacturers BOP manual requirements are to be followed. No
modifications, welding or cutting of any BOP equipment is to be made
without Manufacturers and/or E&Ms written consent. OEM spares must be
used unless a dispensation has been agreed with E&M function
Barrier Policy
During any well operations after surface casing is set a minimum of two 4.1
independent barriers must be in place. If the primary barrier is lost then a
second barrier must be in place,. When only one barrier remains, normal
operations will cease until a second barrier can be re-established.
Drilling Procedures
The hole must be kept full of mud of the agreed density at all times 4
The relevant personnel must understand and be experienced in the use of 4,
the rig’s specific equipment.
All drilling personnel must be constantly alert and able to respond quickly 4, 4.5.6,
should danger signs occur
A drillpipe back pressure valve must be installed while drilling and opening 4.2
hole until the first 1000ft (300m) of hole has been cased
The Rig Supt or Asst Rig Supt (Toolpusher or Night Toolpusher) must be on 4.5.2
the drillfloor for the first 10 stands of any trip to witness the commencement
of tripping operations and until he is confident that the hole is taking the
correct volume of fluid.
During drilling operations a fully opening string valve, plus a non-return valve 5.1.1
5. Pump mud slowly using a high pressure, low volume pump until the pressure builds up to
approximately half the anticipated maximum surface pressure.
a. Pump small volume to flush out all the lines and circulate mud all the way around;
b. Open the HCR valve on the choke line and close the valve directly upstream of the
choke,
c. Close the remote controlled choke,
d. Close the pipe rams around the drillpipe, and then
e. Close in the lower kelly cock.
f. Open the annulus between the current and the previous casing strings, where
applicable.
6. Pump uniform increments of 0.1 to 0.25 bbl. (15 Litres to 40 Litres) and wait for 2 minutes
or the time required for the pressure to stabilise. Note where low pressures are expected
and the volume is small, i.e. shallow weak formations, plot the pump strokes against the
pressure, this is a far more accurate method than using the displacement tanks which at best
are accurate to 0.25 bbls (40 ltrs).
7. Note and record the cumulative mud volume pumped (strokes), the final pumping and final
static pressure on the Leak-Off Test report as per section 8.6 of this manual.
8. Repeat items (5) and (6) and plot pressure versus cumulative mud volume (strokes) curves
for each increment of pumped volume.
9. Continue this procedure until the trend of the final pumping pressure curve deviates from that
of the final static pressure curve after an appropriate waiting time, or until a predetermined
pressure has been reached.
10. Keep the well closed in for a sufficient time (15 minutes) to verify that a constant pressure
has been obtained.
11. Bleed off the pressure back to the tank of the high pressure pump unit and note and record
the volume of any mud lost to the formation.
12. Check the casing pressure gauge and if zero, open the valve immediately upstream from the
choke and open the choke.
13. If the BHA contains a restriction, such as, mud motor, MWD or a bit with small nozzles, bleed
the well pressure back to the tank of the high pressure pump unit via the annulus, with the
HCR open, through the choke to avoid plugging the small flow areas. Measure the volume of
mud recovered.
14. Open the pipe rams, close the HCR and realign the choke manifold.
Some control panels of remote controlled chokes have an automatic MAASP control which keeps
the MAASP constant as soon it is reached. It is a KCA DEUTAG requirement that such devices
must be disabled.
The maximum casing shoe, or weakest formation pressure, must be used to calculate the MAASP
before any well killing starts.
During well control operations and the influx is below the last casing shoe if the pressures indicate
that MAASP will be exceeded the following options should be considered:
1. Reduce circulation rates to reduce annular pressure losses (and adjust drillpipe pressure
accordingly)
2. Continue with kill procedures and exceed MAASP (in which case there is a risk of formation
breakdown)
3. Continue kill procedures but open choke as needed to limit casing pressure to MAASP (in
which case there is a high risk of an additional influx)
The choice between these options will depend upon the data available regarding formation
permeability, shoe strength etc.
Once the influx has passed the shoe the MAASP will be based on the allowable pressure ratings of
the following:
The Casing burst pressure
Wellhead rating
BOP rating
It is therefore important to know the position of the influx at all times such that the appropriate
analysis can be conducted.
Unless there is a strong reason for not exceeding MAASP and risking breakdown at the shoe,
exceeding MAASP is the preferred option to opening up the well and allowing a further influx.
Prior to considering opening the choke, in order to not exceed MAASP, the following hidden safety
factors should be taken into account:
The formation intake pressure obtained during the leak-off test is usually lower than the
formation breakdown pressure.
The influx is dispersed in the mud and the actual position of the top of the gas is much
higher than the theoretical top of the gas when well killing commences. This means that the
influx will not reach the shoe as one bubble, but part of the influx is already inside the casing
shoe when the theoretical top of the influx should be at the shoe. The actual shoe pressure
is therefore lower than the calculated shoe pressure using the MAASP.
Normally, after closing in a well on a gas kick, the shut in pressures will start to rise (for
nearly the same amount) with a certain speed due to the migration of the gas kick. When
starting to pump the viscosity of the mud mostly is decreasing and the speed of the gas
bubble is, besides the speed of pumping, increasing. This means that the gas bubble can
reach the casing shoe earlier than calculated.
Leak-off tests are usually done in virgin hole. In principle, higher leak-off test results are
obtained with time due to the plastering effect of mud.
3 Hardware Requirements
This section provides KCA DEUTAG’s selection, configuration, testing and maintenance
requirements and recommendations with respect to Kick Detection, Diverter, BOPs and associated
equipment. Only with adequately selected, configured and maintained equipment can well control
situations be adequately mitigated.
If any of the equipment categorised as “must” is inoperable and drilling with BOPs is under way the
Rig Manager must be informed.
All BOPs, choke manifolds, diverters, valves, risers, adapters and spools, hoses and flexible piping,
and associated equipment must have valid certification available at the rig site with copies being held
in the office.
3.1 Kick Detection (Hardware)
The following kick detection equipment is either mandatory or recommended in order to be able to
detect kicks as efficiently as possible.
Actuator
Diverter spool
Diverter line P P Diverter line
V
NR
e
ll lin
Ki
Once the Conductor has been set the recommended conductor string diverter set-ups are shown in
Figure 3-2 below.
The minimum requirement of diverter equipment is shown in Option A. This system is usually
installed when it is highly unlikely to encounter shallow gas, but other factors may cause the well to
flow (i.e. colliding with nearby wells, drilling into formations which have been charged-up at a later
stage, etc.).
Option B may be used as an alternative in case there is not enough space underneath the drill floor
to accommodate Option C.
Option C is used for wells with possible shallow gas and is the preferred diverter set-up.
When a pipe-ram type preventer is included in the diverter system, casing rams should be installed
and function tested prior to running and cementing the surface casing string (see Figure 3-2, Option
C).
NRV
Kill
line
Conductor Conductor Conductor
Casing Casing Casing
String String String
housing housing housing
Well control equipment falls into five basic working pressure classifications:
The following factors are to be considered when selecting Well Control Equipment
1. The equipment must be selected to withstand the maximum anticipated pressures and
temperatures.
2. The BOP stack shall consist of remotely controlled equipment capable to close in the well
with or without pipe in the hole.
3. Welded, flanged or hub connections must be used on all pressure systems, exposed to well
pressure. Threaded connections must not be used for pressures above 2000 psi (13800
kPa) and diameters above 1 inch.
4. When operating in an area where sour service equipment is required the complete high
pressure BOP system must consist of materials resistant to sulphide stress cracking (super
trim).
5. Dedicated kill lines must not be smaller than 2" nominal and should be fitted with two valves
and one NRV (check valve). Choke lines should not be smaller than 3" through bore and the
outer valve of each choke line should be hydraulically operated.
6. During drilling and workover operations the BOP should be equipped with one shear ram
capable of shearing the DP in use and to provide a proper seal. If the shear/blind rams are
unable to shear through the string in the hole then this must be made clear that these rams
are only to be used as blind rams and a notice posted on the drillfloor accordingly. If shear
rams are unable to shear the pipe used the Country Manager must also be informed.
7. As per API 16D, closing systems on surface BOPs must be capable of closing any ram
preventer within 30 seconds. For annular preventers up to 20" the closing time must not
exceed 30 seconds, and 20" and more the time must not exceed 45 seconds.
8. All master and remote operating panel handles should, at all time, be in the full closed or
open position. All four-way valves should be either in the fully open or closed position. They
should not be left in blocked or centre position.
9. All spare operating lines and connections, which are not in use in the system, should be
properly plugged off. The valves should be in open or closed position.
As the requirements vary from different Operating Companies, as does local legislation, a “standard”
BOP configuration does not exist. The BOP configurations shown below illustrate how the five basic
working pressure BOPs should be equipped unless otherwise agreed and documented with the
Operator.
Notes:
1. The manual inner valve for the kill and choke line to be open and the outer (working) valve is
to be closed during drilling operation.
2. The valves on the casing head housing must be closed.
3.5.2 BOP 20700 kPa 3000 psi 34500 kPa /5000 psi without a Casing Spool
Notes:
1. The manual inner valve for the kill and choke line to be open and the outer (working) valve is
to be closed during drilling operations.
2. The valves on the casing head housing must be closed.
3.5.3 BOP 34500 kPa 5000 psi with a Casing Spool (Dual Ram option)
Notes:
1. The manual inner valve for the kill and choke line to be open and the outer (working) valve is
to be closed during drilling operations.
2. The valves on the last set casing spool must be closed.
3. Consideration should, however, be given to deploying a 3 ram stacks as per 3.5.4 below with
a blind or shear rams in the middle cavity. The drilling spool ensures that the tooljoint is
below the shear rams and pipe can be sheared, after being hung of on the lower pipe rams.
Ram to ram stripping can be performed if required between the uppermost and lowermost
rams as it provides sufficient clearance for the tooljoints
3.5.4 BOP 34500 kPa 5000 psi and/or 69000 kPa 10000 psi with Casing Spool
Notes:
1. The manual inner valve for the kill and choke line to be open and the outer (working) valve is
to be closed during drilling operations.
2. The valves on the last set casing spool must be closed.
3. On 3 ram stacks KCAD’s normal standard is to utilise blind or shear rams in the middle
cavity. The drilling spool ensures that the tooljoint is below the shear rams and pipe can be
sheared, after being hung of on the lower pipe rams and ram to ram stripping can be
performed if required between the uppermost and lowermost rams as it provides sufficient
clearance for the tooljoints.
.
Notes:
1. The manual inner valve for the kill and choke line to be open and the outer (working) valve is
to be closed during drilling operations.
2. The valves on the last set casing spool must be closed.
rams. This must be communicated to all appropriate personnel and a notice to that effect
posted on the drillfloor. If the shear rams cannot shear the pipe in use the Country Manager
must be informed. An actual shear test is advised before installation of the BOP stack with
the drillpipe size and grade to be used. To obtain maximum shearing capabilities the
installation of large bore shear bonnets and tandem boosters on the closing side of the BOP
can be considered.
17. Ensure that the manufacturer's BOP manual is followed and no alterations are made without
either Manufacturers or E&M Functional written consent. NEVER weld cut or modify any
BOP equipment.
18. Original Equipment Manufacturer spares must be used unless a dispensation has been
made by E&M Function in accordance with their and GSM relevant Group Standards.
Sufficient consumables and spares stocks are to be held onsite.
the associated warning signs as described in section 5.2 are critical in effectively controlling the
situation via the Secondary Well Control equipment and appropriate well killing procedures.
When primary well control is lost and an influx may occur (kick) the blowout preventer equipment
(BOPs) must then be used to enable the 'kick' to be controlled by one or more of the 'kill procedures',
outlined in this manual.
4.4 Tertiary Well Control
An emergency well control situation exists when both Primary and Secondary Well Control procedures have
been unable to control the influx of fluids into the well, or another unusual well control situation arises
requiring specialist techniques, expertise and/or equipment.
4.5 Causes of kicks
The main causes of kicks and therefore losing Primary Well Control are the following:
1. Failing to fill the hole by controlling the volumes and going in and out properly when tripping
2. Swabbing in a kick while tripping, (moving string too fast). Particularly in situations with
balled up stabilisers and overpull
3. Insufficient mud density
4. Abnormal formation pressures
5. Lost circulation
6. Shallow gas sands
7. Excessive drilling rates in bearing sands
Note: The most common causes of kicks are attributable to items 1 and 2 above.
The mitigation actions required to reduce the potential for kicks in each of the above scenarios is
described below:
This reduction in pressure is called a swabbing or suction effect and it is created in a borehole when
the pipe is pulled out too fast. This reduces the bottom hole pressure on the well section below the
bit. Balled up BHA and tight spots in the open hole section will increase this effects.
If the bottom hole pressure (BHP) is reduced to the extent that the overbalance is lost, the formation
contents will enter the wellbore. The chances of this occurring are much greater when the bit is close
to bottom, therefore extra care must be taken in the initial stages of a round trip.
The dangers in this operation are two-fold and cumulative. The very action of swabbing pulls mud
out of the hole. If formation fluids enter the well bore, they will also displace mud out of the hole.
Bottom hole pressure fluctuations, which could cause a kick, are likely to occur whenever the pipe is
moved in the hole.
The swabbed in kick is particularly hazardous since often a brief swabbing episode is followed by
normal tripping practice.
If the small discrepancy in string displacement volume is not noted, it will probably be overlooked. An
overall influx of gas, for instance, swabbed into an open annulus, may only displace a very short
head of mud.
The net decrease in BHP is small and likely to be well below the normal range of 'trip margin'
overbalance. No further flow of gas will occur into the well and, if the well is shut in, no pressures will
show on either DP or casing gauges since the well is still in balance.
However, gas will slowly migrate up the well and expand as it does so. At first the expansion is very
slow and it is unlikely that any significant flow will be seen at the surface unless the influx is very
large, or very close to surface. The possibility to detect a kick by its expansion will be normally first
given when the gas bubble has reached the middle of the well.
In any event, any gas in the hole will reach the surface eventually. Even if the well does not flow
while tripping out it can flow when the bit is returned to bottom and the gas retained in the hole is
then circulated out.
The greatest swabbing action normally occurs when tripping through freshly drilled hole due to the
filter cake being of little substance and liable to wiped clean by the action of the bit. Swabbing can
also occur in the casing (especially with balled up BHA).
The effects of swabbing or surge pressure are made more serious by:
(a) High pipe speed when pulling out (pressure decrease) or when running in (pressure
increase).
(b) Small clearance between the drill pipe/drill collars/bits and the wall of the hole.
(c) Extreme mud properties - density, viscosity, yield point, gel strength, water loss.
(d) Plugging of the bit nozzles.
(e) Balling up of the bottom hole assembly (bit, stabilisers, etc.).
Of the major causes of kicks i.e. failure to keep the borehole full and swabbing, these are most
important because about 70 % of all blow outs have occurred on round trips.
There is also the possibility that most, or all, of the drillstring will be out of the hole when the kick
situation becomes apparent, which complicates and adds to the risk of the killing procedure.
Preventing kicks under these circumstances requires the Driller and his crew to be always ALERT
AND WATCHFUL. They must know at any time during a trip:
(a) What volume of mud should be in the trip tank and mud pits.
(b) Always maintain the mud flow and mud volume indicating and recording instruments in
good working order.
(c) Constantly monitor the flowline, mud pits, trip tank, indicators and recorders.
Whenever there are signs that the borehole is taking less than the calculated volume of mud, (this
decision can normally be made within the first ten stands pulled),
(d) the drillpipe should immediately be run back into the hole - to bottom, if possible,
(e) the hole circulated clean and a flow check made.
The Rig Supt or Asst Rig Supt (Toolpusher or Night Toolpusher) must be on the drillfloor for the first
10 stands of any trip to witness the commencement of tripping operations and until he is confident
that the hole is taking the correct volume of fluid.
Drilling personnel rely on the Geologist and/or Drilling Engineer and the Mud Logger or Well Logger
to warn them of possible high-pressured formations. This is done via the Drilling Programme from
offset well records. Once drilling commences, it is done on the basis of evidence accumulated as the
well progresses.
For the under compacted formations, since the transition from normal to high pressure formations
usually occurs via a transition zone of which the thickness may or may not be predictable, the
Engineer or Mud Logger can also assist in forecasting the latter by analysing changes which occur in
the drilling variables and by analysing the shape, character, and volume of formation cuttings
throughout this transition zone.
By gradually increasing the mud density prior to reaching an anticipated high-pressure zone, there is
a greater possibility that primary control can be retained should signs of a kick appear.
Generally, whenever a permeable zone containing fluids is pressured above the normal gradient,
then appropriate mud densities should be run.
necessary to divert the flow rather than to shut the well in and risk fracturing the casing shoe with the
possibility of gas coming up around the outside of the well (broaching).
As bottoms up time are very short, the Driller and crews must be very alert to all the early signs of a
kick.
The flow sensor may be the only piece of equipment to give a warning early enough. Pit level gains,
although positive indication, are generally too late to indicate flow in this situation. Swabbing can
easily reduce hydrostatic head.
Also, there may be just sufficient ‘core’ gas, or gas released from the drill chips of the drilled
permeable gas sand, to reduce the ECD (equivalent circulating density) below the formation pore
pressure as the chips are transported to the surface.
There is only one method of attempting to kill a shallow gas kick and that is dynamic killing, which
means that the hole is filled with mud or water in excess to the production rate of the formation. It is
recommended to speed up the pumps to the maximum possible rate.
At first sign of flow, the following action is required:
(a) Open diverter valve and close diverter element.
(b) Pump mud immediately at maximum pump rate and be prepared to abandon the location
(c) If the well continues to flow, pump heavier mud at maximum pump rate (generally 0.12 Kg/l,
1 ppg, 1.175 kPa/m).
It is recommended when drilling in shallow gas areas to have at least the pilot hole content premixed
and ready for pumping.
If the well continues to flow after the heavy mud has been pumped, carry on pumping mud at a
maximum rate. When running out of mud, change over to water. Do NOT reduce the pump speed.
Depending on the severity and type of flow, condition of the diverter equipment and availability of
water, the location may need to be abandoned at this stage.
Due to the complexities of Shallow gas planning and precautions a separate section (Appendix 2)
has been included in this manual.
(b) know the steps to be taken to prevent kicks from becoming blowouts,
(c) are properly and regularly trained and tested,
(d) remain constantly alert for all signs of danger, and develop a sense of, or a feel for, the
onset of a "kick".
(e) Competence assurance.
The rig crew will then be able to respond correctly and automatically whenever a positive sign of a
kick occurs.
The opposite signs (pump pressure increase) may be observed if the mud used is normally
weighted, 9.5 ppg (1140 kg/m3), and a saturated magnesium chloride salt water of 12.5 ppg (1500
kg/m3) is encountered.
5.3.1 Well Fails To Take Correct Volume of Mud When Tripping Out
While pulling out, the amount of mud used to fill the hole between stands must be measured. If it is
less than the volume of steel in the pipe just pulled, it indicates an influx into the well bore from the
that could develop into a kick.
The well should be observed for flow. If the well flows, close it in and prepare to kill it. If it does not,
run back to bottom and circulate bottoms up. If there is no sign of an influx at bottoms up resume the
round trip but take additional care not to swab.
In situations using oil based mud and having a gas kick the danger to reduce bottom hole pressure
while running back to bottom is not so high. However if circulating bottoms up, the gas will come out
of the solution at the bubble point. It should therefore be considered to circulate up halfway then to
close in the well and circulate the rest by using the choke.
In situations using water based mud and having a gas kick, the decision running back to bottom can
become critical. When through passing the gas kick, the height of the kick will increase significantly
and a great loss in bottom hole pressure can occur. Due to this pressure loss, a new kick could enter
the wellbore. Under this circumstances it is absolute necessarily to control the volumes coming out
when tripping back. If there will be any uncertainty, close in the well and strip back to bottom by
using the volumetric stripping method.
If the well is killed at some distance higher than the TD, a higher mud density is required than it
would take if the well were killed on bottom as the original mud density exists from beneath the bit to
TD. If this is the case, the well may need to be killed in stages.
Alternately, if the rig crew is very familiar with stripping into the borehole, it might be more prudent to
get as close to bottom as possible by stripping, then to kill with the correct mud density.
6. The Driller raises the elevators a few metres and the Floormen stab the kelly cock on the
pipe as quickly as possible and torque up same.
7. Close the kelly cock using the wrench.
8. The Driller opens the H.C.R. valve on the BOP and then closes the appropriate preventer.
The times taken to install and close the kelly cock and to close the BOP (including opening the
H.C.R. valve) should be recorded individually. The total time are to be filled in on the kick drill sheet
(example shown in the Appendix 1).
With the well now shut in:
9. Connect the top drive or kelly.
10. Open the kelly cock.
11. Observe and record SIDPP and SICP.
If it is decided to strip the drill string to bottom continue as follows:
12. Close the kelly cock and bleed off any pressure from top drive.
13. Disconnect the top drive and remove the pup joint from the kelly cock.
14. Install the Gray valve and connect the top drive.
15. Open the kelly cock and test the Gray valve.
Note the above assumes the topdrive kelly cock has an OD that allows it to be stripped into
the well. In many wells the regular 6 5/8” Kelly cock will not pass through 9 5/8” casing. This
aspect should be considered during the well planned phase.
The strip drill should be held in casing prior to drilling out the shoe-track. It can be combined with a
pit drill. Prior to conducting a strip drill determine whether there is a risk of drillpipe collapse or
casing burst. Prior to commencing the strip drill refer to the Stripping Checklist in Appendix 1.
6 Shut-in Procedures
6.1 Responsibilities for implementing Well Control Procedures
The shut in procedure and the preferred kick killing method to be used, is to be made known to the
crew by the Rig Manager and Operator, not later than the spud meeting. Any agreed procedures and
the methods should be in accordance with the procedures in this Manual.
The Driller is responsible for monitoring his instrumentation, evaluating any changes and information
given to him, performing flow checks and, where there are indications of a kick, shutting in the well
and informing the Rig Superintendent or Toolpusher.
6.2 General Shut-in Procedures
6.3.2.1 Annulus
To ensure that the annulus is close, check to be sure that the annular bop is completely close
on the well and is holding pressure. Then be sure that no fluids are flowing out of the mud
return (flow) line. It is best practice to line up the trip tank across the top of the BOPs to
confirm the rams or annular is not passing.
6.3.2.2 Drillstring
To confirm that pressure is holding on the drillstring, check to be sure that the mud pumps
pressure relief valves have not popped open and that closing pressure will not exceed the
pressure at which the relief valves will open; then, check the standpipe manifold. Every joint
should be pressure tested with no leaks.
in situations with danger of differential sticking (highly deviated and horizontal wells) and/or
plugging of the annulus.
The well can be controlled, even if weighting material supply is inadequate.
Easier to use in vertical wells with a taper string, in highly deviated wells and horizontal
wells.
The principal disadvantages of the Driller's Method are:
The well will be closed in under pressure longer.
The maximum pressure at the casing shoe and against the formation might be higher if the
influx is gas however this depends on the borehole and the drillstring configuration. The
downhole pressures of both methods will be the same as long as the drillstring - open hole
capacity is the same or less than the internal drillstring capacity.
The maximum choke pressure when the top of the influx reaches the surface will be higher if
the influx is gas.
In more complex situations the volumetric method or the bull heading can be considered.
All these methods are described in the following sections:
5. By a determining the initial circulation pressure in this way the SCR can be re calculated as:
Slow circulation rate = initial circulating pressure - shut in drill pipe pressure
This procedure is satisfactory at any time during a kill providing the mud density in the drillstring is
stable during the process. It is however preferable to maintain pump rate constant as much as
possible. Any decision to change pump rate should be taken early.
Once well killing procedures have been discussed and agreed the well kill procedure should
commence as follows:
3. Open the choke about one-quarter, start the pump and break circulation; then bring the
pump up to the kill rate (the time to bring up the pumps to kill speed should be one minute no
less no more)
4. While the driller is bringing the pump up to the kill rate, the choke operator should operate
the choke so as to keep the casing pressure at/or near the closed in casing pressure
reading.
5. Once the pump is up to the kill rate, the choke operator should transfer his intention to the
drill pipe pressure gauge and adjust the choke to maintain the initial circulation pressure on
the drill pipe pressure gauge. If there is no slow circulation rate pressure or uncertainty about
it, the pressure reading on the drill pipe gauge, by keeping the casing pressure constant, will
be the established initial circulating pressure (remember the time delay between drill pipe
and casing pressure gauges).
6. The initial circulating pressure is held constant on the drill pipe pressure gauge by adjusting
the choke throughout the whole of the first circulation, until all of the kick fluid has been
circulated out of the well. The pump rate must also be held constant at the kill rate
throughout this period.
7. To confirm that there is no more kick in the well, shut in drill pipe pressure and shut in casing
pressure should be near same (pumps off) and the suction pit level should be nearly the
same like before the kick.
8. Once the kick is out of the hole, shut in the well in and continue to mix up the kill mud density
required as per the following formulae
SIDPP(ps i)
Kill mud density(ppg)= original mud density(ppg) + (ppg)
TVD(ft) x 0.052
SIDPP(bar)x 10.2
Kill mud density(kg/l)= original mud density(kg/l) + (kg/l)
TVD(m)
SIDPP(kpa)x102
3
Kill mud density(kd/m )= original mud density(kg/m ) +
3
(kg/m3)
TVD(m)
Notes:
This is the kill mud density to balance formation pressure. It is the lowest as possible mud
density which will kill the well. Once the well is dead, it will be necessary to increase the mud
density further to provide a trip margin.
The heavy mud gradient can include a suitable overbalance margin.
Some operators prefer to continue circulating the well while kill mud is being mixed. There is
no theoretical reason why this should not be done, though it results in further wear and tear
on equipment under pressure - in particular the choke. In situations of highly deviated or
horizontal wells this will make sense and one can even consider moving and slowly rotating
the string through the closed annular bop.
At this stage the well is now controlled but not killed.
st
Figure 7-1 Pressure profiles during 1 Circulation of Driller’s Method
Notes:
If the influx was gas and all the gas was not removed during the first step
(circulation), the first option of keeping casing pressure constant could lead to higher
annular pressures and a new kick.
The drill pipe pressure will go down as the drill pipe is being slugged with the heavier
mud. In practice, if all the kick was properly removed in the first step (circulation), the
choke should not need to be touched once the pumps are steady at the kill rate, until
kill mud reaches the bit.
Once the kill mud reaches the bit, the pressure held on the drill pipe is just that
required to circulate the kill mud around the well. This is the slow circulating rate
pressure, increased slightly for the extra mud density.
Kill mud density
Final circulating pressure = slow circulating pressure x
Original mud density
5. Thereafter the drill pipe pressure is held at the final circulating pressure by controlled
opening of the choke, as the kill mud moves up the annulus.
6. When the kill mud reaches surface shut in the well and check for zero shut in pressures. The
preventers should only be opened and normal circulation resumed after flow has ceased
from the choke line for a reasonable flow check time.
7. Set all valves to normal operating position.
8. After circulating the hole clean perform a check trip.
9. Resume drilling ahead.
Because of the possibility that the annular may not be circulated completely clean, during the first
step (circulation), it may be preferable to work out how the drill pipe pressure should vary as kill mud
is pumped around the well. This will allow the drill pipe pressure to be used throughout, so
eliminating the possibility of small gas bubbles in the annulus producing misleading information.
A worked example using the Drillers method is included in Appendix 1 of this manual.
nd
Figure 7-2 Pressure profiles during 2 Circulation of Driller’s Method
Once the well is shut in and pressure still remains, the shut in drillpipe pressure is used to calculate
the kill mud weight. Mud off the required weight is made up in the mud pits. When ready, kill mud is
pumped down the drillpipe. At commencement, enough drillpipe pressure must be held to circulate
the mud, plus a reserve equivalent to the original shut-in drillpipe pressure. This total steady
decreases as the mud goes down to the bit, until with kill mud at the bit, the required pressure is
simply that needed to pump kill mud around the well.
The choke is adjusted to reduce drillpipe pressure while kill mud is pumped down the string. With kill
mud at the bit, the static head of mud in the drillpipe balances formation pressure. For the remainder
of the circulation, as the influx is pumped to the surface, followed by drillpipe contents and the kill
mud, the drillpipe pressure is held at the final circulation pressure by choke adjustment.
Ensure sufficient barite is on location and the mixing capacity is according to the selected pump rate.
The wait and weight method uses the same calculations already described for a drillpipe pressure
schedule. The calculations are:
SIDPP(ps i)
Kill mud density(ppg)= original mud density(ppg) + (ppg)
TVD(ft)x 0.052
SIDPP(bar)x 10.2
Kill mud density(kg/l)= original mud density(kg/l) + (kg/l)
TVD(m)
SIDPP(kpa)x102
3
Kill mud density(kg/m )= original mud density(kg/m ) +
3
(kg/m3)
TVD (m)
Prior to undertaking the following procedure it is assumed that the well is shut in as per the Shut-in
Procedure described in 6 and all pre-kick information is recorded on the pre kick sheet as follows:
Pre-recorded Information items on the Surface BOP Kill Sheet can be noted as follows:
1. Formation Strength Data:
a. Leak-Off Test pressure (A)
b. Drilling fluid density at Leak-Off Test (B)
c. Maximum Allowable Drilling Fluid Density (C)
2. Initial MAASP at current drilling fluid density
3. Pump Data:
a. Pump Rates and corresponding Dynamic Pressure Loss
4. Current Well Data:
a. Drilling fluid data: Density and Gradient in use
b. Casing & shoe data: Size, Measured depth and True Vertical Depth (TVD)
in steps according to the IWCF Surface BOP Kill Sheet and the graph until the kill mud has
reached the bit.
As long as the heavy or kill mud interface is still inside the drillstring there should be very
little change in the choke opening position. If the drillpipe pressure must be adjusted to
correspond with the pressure line on the IWCF Surface BOP Kill Sheet , that pressure
change should be made using the annulus pressure gauge.
Allow sufficient time for that pressure transient to work its way back to the drillpipe gauge.
Typically, at the speed of sound in the drilling fluid, or about 1 second per 1000 ft (300 m) for
the travel path.
Where the kick is a small one, at or near the bottom of the hole, the drillpipe pressure tends
to drop of its own accord as the kill mud moves down. Little or no choke adjustment is
required.
Only in cases of diffused gas kicks with gas far up the annulus will significant choke
adjustments be needed during this period.
DO NOT ATTEMPT TO INCREASE THE STANDPIPE PRESSURE BY CHOKE
MANIPULATION AGAINST THE DIRECT READING OF THE STANDPIPE PRESSURE.
This will result in excess pressure build-up and possible formation breakdown.
16. After kill mud has reached the bit, the drillpipe pressure is maintained at the final circulating
pressure, until the kill mud returns to surface. As an option the pump can be stopped and the
well shut in. The shut in drillpipe pressure now should be zero.
The behaviour of the choke pressure is different depending on the type of influx. When the
gas starts to reach the surface there will be big variations in choke pressure due to slugs of
mud and gas, and it will be impossible to adjust the choke accordingly.
As with the driller's Method, this final circulating pressure is held constant as long as pump
rate is held constant at the selected value. If, for any reason, the pump rate is felt to be
wrong, it can be changed using the same procedure described previously. However, pump
rate changes should be avoided, where possible. While the pump rate is adjusted, the
casing pressure is held steady by adjusting the choke. Once the pump is stabilised at its
new speed, the revised circulating pressure is read from the drill pipe gauge. If a gas influx is
very near to the surface, adjusting pump rate by holding a steady casing pressure may
significantly increase the bottom hole pressure. This is due to the rapid expansion of gas
near the surface. Alterations in pump rate have to be made early on.
17. After the kick has been circulated out, stop the pump and perform a flow check over the
open choke and check the mud density.
18. The well should be circulated for at least another WellCAPacity to condition the mud in the
system, and to ensure that the overbalance is adequate. If not, the mud density should be
adjusted to the correct value while circulating to condition the hole and the mud system.
19. The preventers should only be opened and normal circulation resumed after flow has ceased
from the choke line for a reasonable flow check time.
20. Set all valves to normal operating position.
21. After circulating the hole clean perform a check trip.
22. If circulation after the check trip is normal (no excess gas on bottoms up), the next normal
operation can be performed.
Figure
Figure 7-3 Profile of Circulating Pressure while killing by Wait and Weight Method
Figure 7-4 Profile of Circulating Pressure while killing by Wait and Weight Method
A worked example using the Wait and Weight method is included in Appendix 1 of this manual.
Although the method is theoretically viable, caution should be exercised during implementation to
avoid further influx gains.
underbalanced. The safety margin should be reduced for critical wells; such as where a low
MAASP does not allow for excess pressure to be applied to the well bore.
4. Bleed off mud (V1) from the well, while maintaining Pchoke constant.
V1 = Pw x OH / DC cap p1
5. When the additional mud volume has accumulated in the trip tank the well is closed in until
Pchoke rises, under the influence of the migrating gas influx, by one increment of Pw.
6. By repeating step (5) and (6) as often as necessary, gas is allowed to migrate upward and
expand while a nearly constant BHP is maintained.
7. When gas is considered to be above the bit (calculated by migration rate), use a
conventional well killing to remove the influx from the well.
8. If conventional well killing is still not possible, the method has to be continued until gas has
reached the surface.
9. Gas has to be replaced with mud by pumping mud into the well intermittently through the kill
line. This procedure is called “Lubricating”.
10. Pump mud V2 = Pw x (CSG/DP cap.) (pmud in use ) into the annulus.
11. Allow the gas to migrate to the surface again.
12. Bleed off gas ONLY until the choke pressure (the pressure prior to pumping 2 mud) is
reduced by one Pw increment.
13. Repeat the lubricating exercise until all gas has been replaced with mud and the well is
under control noting that this method has not killed the well; it has only removed the influx .
14. Strip back to bottom and kill the well by using the Driller's Method (after solving the initial
circulation problems).
15. Make flow check and if well is static open the BOP.
16. Circulate bottoms up.
17. Perform a check trip.
18. Resume operations.
Proper records should be kept during the well killing operation i.e.:
Pchoke versus time to identify an increase in the number of pressure build ups, which
is an indication of gas entering annular capacities.
Pchoke versus V to maintain the correct BHP.
13. Strip back to bottom and kill the well by using the Driller's Method (after solving the initial
circulation problems).
Note: Proper records should be kept during the well killing operation:
Pchoke versus time to identify an increase in the number of pressure build ups,
which is an indication of gas entering annular capacities.
Pchoke versus
Where:
3
Vinf = Initial influx volume, (litre, m or bbl)
3
OH / DC cap = Open hole / DC annular capacity, (m /m, l/m or bbl/ft
3
OH cap = Open hole capacity, (m /m, l/m or bbl/ft)
P1 = Mud gradient, (kPa/m, bar/m or psi/ft)
Pinf = Estimated influx gradient, (kPa/m, bar/m or psi/ft)
Pw = Working pressure increment.
Note: Convenient values for working pressure increments are between 350 to 700
kPa (50 to 100 psi or 3.5 to 6.5 bar) depending on scale divisions on the pressure
gauges. In critical cases where a low MAASP does not allow excessive pressures to
be applied to the well bore; a smaller pressure increment could be used until the
influx is above the DCs.
14. Once the required choke pressure is reached, Pchoke is kept constant while the drillpipe is
stripped back in the hole. Excess pressure is bled off via the choke manifold into the trip
tank.
15. The closed-end pipe displacement of each stripped in stand of drillpipe is then drained from
the trip tank into a stripping tank.
16. The string is then stripped into the hole until a volume of ∆V1 has accumulated in the trip
tank.
∆V1 = Pw x OH / DC cap p1
17. Once the correct mud volume (∆V1) has entered the trip tank, the choke is closed and the
annular pressure is allowed to rise by Pw by means of stripping DP into the hole.
Note: The closed end displacement volume should NOT be bled off from the trip tank
into the stripping tank during this operation.
It is recommended to strip the complete stand in the hole for each phase of the
operation (whilst maintaining Pchoke constant, or when increasing Pchoke by Pw ) to
simplify the bleeding off process from trip tank to stripping tank and to improve the
accuracy of ∆V1 measurements which directly results in improved BHP.
Note: As a result of stripping the complete stand, higher then required choke pressures
will occasionally be obtained which should be taken into account when next Pw
increment needs to be added.
18. Steps (13) through (17) are repeated as often as necessary, until:
a. Bit is on bottom.
b. Gas has reached surface.
c. Stripping is no longer possible due to excessive pressures; BOP stack problems open
hole resistance, etc.
19. Stripping is then stopped and the well is killed conventionally, if the influx is above the bit.
20. When the bit is back on bottom, the well can be killed conventionally (Driller's Method) by
using following procedure:
21. If not already done, fill up the string with mud.
22. By using last SCR, calculate circulation pressure and Pchoke. Add 3,5 bar (50 psi) to the
calculated pressure to compensate for pressure drop in the inside BOP.
23. Circulate the string content, by maintaining a constant BHP.
24. After the string contents has been pumped; close in the well and check for trapped
pressures. Leave about 3,5 bar (50 psi) in standpipe pressure.
25. Continue to kill the well by using the Driller's Method. If it is a swab kick, the normal mud can
be used as it is proven (during drilling) that it was overbalanced.
Note: These rates obviously assume that the there exists a formation which is able to take this
volume per minute.
4. Connect the points A - B - C - D obtained in steps (1), (2), and (3) with straight lines. This
profile represents the standpipe pressure while pumping the new mud from surface to bit.
Note: The standpipe pressure at point of interest is calculated using following formula:
PST’s' = Pst (start) + (Pc2 - Pc1) x {Px (AH)/D (AH)} - Px (TV) x (p2 - p1)
The static Pdp, at point of interest is calculated as follows:
Pdp'X' = Pdp - Dx (TV) x (p2 - p1)
Where:
Pst'X' = Standpipe pressure at point of interest, kPa or psi
Pst(start) = Standpipe pressure observed at start of kill, kPa or psi
Pc2 = Circulating pressure at end of kill, kPa or psi
Pc1 = Circulating pressure at start of kill, kPa or psi
Dx(AH) = Along hole depth at point of interest, m or ft
D(AH) = Along hole total depth, m or ft
Dx(TV) = True vertical depth at point of interest, m or ft
p1 = Original mud gradient, kPa/m or psi/ft
p2 = Kill mud gradient, kPa/m or psi/ft
5. Calculate (or read from the directional drilling map) TVD of along the hole (AH) height of
influx at bottom and at the shoe to obtain equivalent hydrostatic heads for specific influx
volumes and apply "adjusted annular capacities" into the formulas.
6. Proceed with applying standard well control calculations as per vertical wells.
Figure 7-9 Rig Layout for combined Stripping and Volumetric Method
Regardless of the method used to strip pipe into the hole, to enable effective pressure control it is
very important to measure all of the fluid that comes out of the wellbore. Formation fluid that has
entered the well may be gas and during the stripping operation migration may take place. If there is
no migration of fluid, the volume of mud release from the wellbore, as pipe is stripped, should equal
the closed-end pipe displacement and the surface pressure should remain the same.
If the gas influx migrates, the surface pressure will increase even though the volume of drilling fluid
released at the surface is exactly equal to the closed-end pipe displacement. In this case it is
necessary to bleed off additional fluid to let the gas expand and thus reduced the change out
formation breakdown. This is achieved by maintaining choke pressure constant whilst pipe is
stripped in.
When the bit and DCs enter the influx, a dramatic loss of hydrostatic head will take place. This loss
of hydrostatic head should be anticipated and additional backpressure must be added at the very
start of the stripping operations.
In general, the annular preventer is used for stripping pipe into or out of the hole. The annular
preventer allows the use of one preventer and permits the tool joints to pass through the packing
element. To minimise friction the pipe should be well lubricated with grease and closing pressures
applied to the annular kept to a minimum whilst avoiding leakage. Additionally, drillpipe protectors
should be removed and if possible sharp edges and tong marks on the pipe body and tool joints filed
off.
Once the well is closed in, SICP and SIDPP must be continuously observed. If both start to show
signs of an increase, it will be due to upward migrating gas.
The gas should be allowed to expand by opening the choke until SIDPP reverts to the closed-in
pressure observed at the time of equipment failure. (If circulation is stopped after the kill fluid
reaches the bit, SIDPP will normally be zero.)
Once repairs have been completed the killing procedure can be restarted.
7.6.3 Hydrates
The formation of hydrates is dependent upon a combination of the following conditions:
a. Presence of free water
b. Gas at or below it's dew point
c. Low temperature
d. High pressure
The hydrate problem is aggravated by pressure drop / gas expansion (through the choke) and
pressure pulsing.
As the gas passes through these restrictions the resulting pressure drop plus the sudden increase in
velocity cause “expansion cooling” of the gas immediately downstream of the choke.
Hydrates can cause severe problems by plugging valves or chokes and completely blocking flow.
Upstream pressure increases and this compounds the problem.
Prevention of hydrates will always be easier and better than the cure. It may be necessary to inject
methanol or glycol to suppress hydrate formation. Ports can be modified into the choke manifold for
this purpose.
The hydrate problem is virtually non-existent in Oil base muds. With Water base muds, maintaining a
high chloride concentration in the mud will lower the freezing point.
If hydrates do form and plug off the choke or kill line they can be very difficult to remove.
Considerable heat is required for decomposition, for example, circulating hot brine solution.
7.6.4 Well Kill Problem - Quick Check List & Trouble Shooting Charts
Unexpected changes in pressures during a well kill could be interpreted by reference to the following
list and tables which should be consulted prior to closing in the well and assessing the situation
further:
(a) A jumping rotary hose or a surging pressure gauge are signs of a pump problem.
(b) If the standpipe pressure and the choke pressure both increase suddenly, the choke or
choke manifold is plugged.
(c) If only the standpipe pressure increases suddenly, a bit nozzle or the annulus is plugged.
(d) If the standpipe pressure drifts downwards, there could be a leak or hole in the drillstring.
(e) If the standpipe pressure and choke pressure do not respond to choke adjustment and the
pit level is falling, loss of circulation is occurring.
A Trouble shooting Chart for other scenarios is presented below:
7.6.4.1 Drillpipe Pressure and Casing Pressure BOTH UP the same amount
Check Pump rate too fast. Circulating pressure is too high Slow the pump rate down to the
pump rate. because the pump is running planned rate. If pressure comes
faster than was planned. down, everything is OK. If not,
continue down chart.
Increase Drillpipe pressure Choke opening was too small. If the pressure come down when
choke and casing the choke opening was
opening. pressure will come increased, everything is OK. If
down. not, continue down chart.
Open Drillpipe and casing Either choke opening was to If pressures come down,
choke all pressure will come small or the choke is on way to everything is OK. If not, continue
the way. down. plug. down chart.
Stop the Drillpipe and casing The choke manifold has started Switch to alternate chokeline. If
pump. pressure will come to plug up. pressure come down, go back to
down. kill the well, if not continue down
chart.
Shut the Pressures stay up. Manifold is plugged. Switch to alternate chokeline. if
well in. pressure come down, go back to
kill the well, if not continue down
chart.
Shut the Pressures stay up. Manifold plugged at or above Close the master valve on the
well in. “T”. kill line, release the pressure
from the manifold and clean it
out.
7.6.4.2 Drillpipe pressure UP, and Casing pressure UP just a small amount
Check Pump rate too fast. Circulating pressure is too high Slow the pump rate down to the
pump rate. because the pump rate is faster planned rate. If pressures come
than planned. down, everything is OK. If not,
continue down chart.
Increase Drillpipe pressure Choke opening was too small. If the pressure come down when
choke and casing pressure the choke opening was
opening. will come down. increased, everything is OK. If
not, continue down chart.
Casing pressure Wait at least 2 minutes to see if Allow for a long time lag with big
comes down, but not there is a long lag between choke gas kicks. If pressure will not
drillpipe pressure. movement and drillpipe pressure. come down, continue down chart.
Drillpipe pressure A mud ring or pack off near the Raise or reciprocate the drillpipe.
does not come bit. If drillpipe pressure comes down,
down. OK. If not, continue down chart.
Or:
stop the pump and shut in the
well in and bleed the pressure off
the drillpipe until at least one jet
clears. Then start up holding
casing pressure constant until
you reach the new pump rate.
then use the new circulating
pressure as the constant
circulating pressure.
Check Pump rate too fast. Circulating pressure too Slow the pump to the
pump high because rate is planned rate.
rate. faster than planned.
Increase Casing pressure A mud ring or pack off Raise or reciprocate the
choke gets very low near the bit. drillpipe. If drillpipe
opening. before drillpipe pressure comes down, OK.
pressure comes If not, continue down chart.
down.
Open Drillpipe pressure Plugged bit. Stop the pump and shut the
choke. does not come well in. Try rocking the
down. pump to clear the bit. You
may have too shoot off or
back off the bit.
Increase Pressure does not Lost circulation, bad cement job, Take a new slow
or seem to respond to or a hole in the casing. Check circulating rate. Add
decrease choke movement. pit volume. circulation material.
in choke Add barite plug. Add
opening. cement plug over
barite plug
Check pit Volume OK. Check of the choke for failure. Switch to alternate
volume. choke.
Check Pump rate too Pump rate is lower than planned Increase the pump
pump slow. rate to the planned
rate. rate. If pressures
come up, OK. If not,
continue down chart.
Decrease Drillpipe and casing Choke opening was too great. If pressures increase
choke pressure increase. when the choke size
opening. was decreased, OK.
If not, continue down
chart.
Check Pump rate too Circulating pressure is too Increase the pump
pump rate. slow. low because the pump is rate to the planned
running slower then was rate. If pressures
planned. come up, OK. If not
continue down chart.
Continually Drillpipe pressure Hole in the drillpipe. Stop the pump and
decreasing stays the same, shut in the well in.
choke casing pressure You may have to
opening. goes up. strip out to replace a
joint of pipe.
Decrease Drillpipe and casing Washout in bit or in drillpipe. Stop the pump and
choke pressure go up. shut in the well in.
opening. You may have to
strip out to replace a
joint of pipe.
Location: Date:
Rig: Driller: Time:
Depth: m
Bit depth: m Pit drill during tripping
Duration
Omit not applicable steps
Time to recognize kick sec.
Time to place Kelly cock (and close) sec.
Time to open HCR valve sec.
Time to close annular preventer sec.
Time to close pipe rams sec.
Time to place top drive sec.
Time to open Kelly cock sec.
sec.
Total Time sec..
Depth: m
Bit depth: m Pit drill during drilling
Duration
Omit not applicable steps
Time to recognize kick sec.
Time to raise bit from bottom sec.
Time to stop pumps sec.
Time to open HCR valve sec.
Time to close annular preventer sec.
Time to close pipe rams sec.
sec.
Total Time sec.
Remarks:
Driller:___________________ Toolpusher:_________________
Depth: m
Bit depth: m Pit drill during tripping
1
Duration
Omit not applicable steps
Time to recognize kick sec.
Time to place Kelly cock (and close) sec.
Time to open HCR valve sec.
Time to close annular preventer sec.
Time to close pipe rams sec.
Time to close choke (close valve in sec.
front)
Time to place top drive sec.
Time to open Kelly cock sec.
Total Time sec.
Depth: m
Bit depth: m Pit drill during drilling
Duration
Omit not applicable steps
Time to recognize kick sec.
Time to raise bit from bottom sec.
Time to stop pumps sec.
Time to open HCR valve sec.
Time to close annular preventer sec.
Time to close pipe rams sec.
Time to close choke (close valve in sec.
front)
Total Time sec.
Remarks:
Driller:___________________ Toolpusher:_________________
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Vertical Well (Metric/Bar) NAME :
INITIAL MAASP =
M. DEPTH m
PUMP NO. 1 DISPL. PUMP NO. 2 DISPL. T.V. DEPTH m
l / stroke l / stroke
HOLE DATA:
(PL) DYNAMIC PRESSURE LOSS [bar]
SIZE in
SLOW PUMP
PUMP NO. 1 PUMP NO. 2
RATE DATA: M. DEPTH m
T.V. DEPTH m
SPM
SPM
DRILL PIPE x =
VOLUME PUMP STROKES
HEAVY WALL DRILL PIPE x = +
PUMP DISPLACEMENT SLOW PUMP RATE
DRILL COLLARS x = +
DC x OPEN HOLE x =
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Vertical Well (Metric/Bar) NAME :
KICK DATA :
SIDPP bar SICP bar PIT GAIN litres
(J) x 100
(J) = ICP - FCP Bar --.--------- = Bar/100 strokes
(E)
STATIC & DYNAMIC DRILL PIPE PRESSURE [bar]
STROKES
KICK DATA :
SIDPP psi SICP psi PIT GAIN barrels
................. + =
KMD X 0.052 ppg
STROKES
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Deviated Well (Metric/Bar) NAME :
DC x OPEN HOLE x =
DP / HWDP x OPEN HOLE x = +
OPEN HOLE VOLUME (F) l stks min
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Deviated Well (Metric/Bar) NAME :
KICK DATA :
CIRCULATING PRESS.
(O) + (P) = ............. + ............. =
AT KOP (KOP CP) ............... bar
CIRCULATING PRESS.
(R) + (S) = ............. + ............. =
AT EOB (EOB CP) ............... bar
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Deviated Well (Metric/Bar) NAME :
STATIC & DYNAMIC DRILL PIPE PRESSURE [bar]
STROKES
PRESSURE
[bar]
STROKES
DATE :
International Well Control Forum
SURFACE BOP KILL SHEET NAME :
DC x OPEN HOLE x =
DP / HWDP x OPEN HOLE x = +
OPEN HOLE VOLUME (F) bbl stks min
KICK DATA :
CIRCULATING PRESS.
(O) + (P) = ............. + ............. =
AT KOP (KOP CP) ............... psi
CIRCULATING PRESS.
(R) + (S) = ............. + ............. =
AT EOB (EOB CP) ............... psi
STROKES
PRESSURE
[psi]
STROKES
Pan = ………..
F – factor = ………..
Ps = F x Vi = …………
Pw selected = …………
divisions in triptank
T. T. Level Pch
T
i
Stand Pchoke Triptank Remarks
m
No. level
e
1 Has one person being designated to supervise the entire stripping operation?
2 Is the bop stack spaced for stripping and are drawings with measurement available?
4 Was a heavy pill pumped into the hole before they started out of the hole?
7 Is there everything rigged up for the combined stripping and volumetric method?
9 Has wellbore force being calculated to verify that the string can be stripped back either through
the annular preventer or ram preventer?
10 Has open hole capacity and open hole to DC capacity been calculated?
12 Will all the fluid which will be bled off go into the calibrated trip tank?
13 Have arrangements been made to accurately record and calculate all pressures and volumes?
20 Have specific jobs been assigned to personnel on location and have proper instructions been
given?
21 Has the Kelly cock been opened before the first stand was made up, in order to check the inside
BOP and to confirm that circulation is possible?
22 Has the correct amount of mud to be bleeding off as the pipe is stripped in been calculated?
25 Has the rig been prepared for lubricating the DP when they are stripped back into the hole?
The measured kick volume at the time the well was closed in will be compensated due to the
increased BHP to:
Vinf.o x (po) / (p1)
Actual pressures during volumetric killing operations are usually lower than calculated P x values
because:
a. The influx is fragmented and dispersed in the mud instead of remaining as a
single slug.
b. The influx is probably not on bottom at the time of closing in the well.
Gas migration rate can be estimated in a water based mud using following formula:
Where:
Pa1 = Closed-in casing pressure at time T1 minutes, (kPa, bar or psi)
Pa2 = Closed-in casing pressure at time T2 minutes without having allowed the
influx to expand, (kPa, bar or psi)
p1 = Mud gradient, (kPa/m, bar/m or psi/ft)
P
r
e
s
s
u
r
e
Cumulative Volume
Calculation of MAASP
Calculation of the maximum pressure (at the top of the gas) when the gas influx reaches the shoe
can be done either by calculation or graphically as follows:
Calculation of the maximum pressure (at the top of the gas) when the gas influx reaches the shoe
using the formula:
Calculation of the maximum pressure when the gas influx reaches the shoe using the graph.
Make a graph with the depth to the left and the pressures at the bottom. Draw in the casing shoe
setting depth (Figure 1)
Draw a line for the formation break down pressure crossing the casing shoe line at the right FGT
pressure and extend this line to the bottom of the graph.
Draw a line for the actual BHP (Bottom hole pressure) when the kick occurred.
Draw up the influx height and extend this line to the top, parallel with the BHP line.
If this line is crossing the formation break down line below the shoe line the MAASP will be
exceeded. (Line b in the graph).
If crossing is above the shoe line the pressure at the shoe will be below the MAASP. (Line a in the
graph).
MAASP = FBP - Head of mud in use to shoe.
EMD is the Maximum Allowable Drilling Fluid Density on the IWCF form in the formation strength
data.
Once the formation pressure is known, the mud density required to kill (balance) can be calculated
thus:
Kill mud density (ppg) = Formation press. (psi)
Kill mud density (kg/l) = Formation press. (bar)
Kill mud density (kg/m ) = Formation press. (kPa)
3
SIDPP SICP
Drillpipe Annulus
In any other case the results can become negative or result in an incorrect gradient for the influx.
The solution is for each kick has to be handled as a gas kick.
The relationship between surface pressures, influx height and density is:
Grad. of influx, psi/ft = Grad. of mud, psi/ft - [(SICP - SIDPP) Influx height, ft]
Further, if that same mass of gas is taken to a different absolute pressure, then it will also occupy a
different calculable volume.
Note: The effects of compressibility and temperature must also be taken into account for
absolute precision but may be neglected for most field determinations.
For a unit of gas we have a unit of pressure, but we can compress that unit of gas to half it's original
size by doubling the pressure upon it. Original pressure x Original volume = New pressure x New
volume, or,
P1 x V1 = P2 x V2
Working this equation will show the extremes that occur with gas kicks.
At 10000' the hydrostatic pressure of the mud and the kick (ignoring formation pressure) would be:
10000 ft x 0.052 psi/ft = 5200 psi
As the bubble reaches 5000 ft with a hydrostatic head of 2600 psi, the volume of the gas bubble is
now:
P1 x V1 = P2 x V2
5200 x 30 = 2600 x V2
V2 = (5200 x 30) 2600 or V2 = 60 bbls.
But as the gas bubble breaks out at surface in atmospheric (14.6 psi), the original 30 bbl influx of gas
now becomes:
P1 x V1 = P2 x V2
5200 x 30 = 14.6 x V2
V2 = (5200 x 30) 14.6 or V2 = 10685 bbls.
This is a much greater volume than the entire annular capacity so the well would be blowing wildly.
As the bubble reaches 1530 m with a hydrostatic head of 180 bar, the volume of the gas bubble is
now:
P1 x V1 = P2 x V2
360 x 4.77 = 180 x V2
V2 = (360 x 4.77) 180 or V2 = 9.54 m .
3
3
(But as the gas bubble breaks out at surface in atmospheric (1 bar), the original 4.77 m influx of
gas now becomes:
P1 x V1 = P2 x V2
360 x 4.77 = 1 x V2
V2 = (360 x 4.77) 1 or V2 = 1717 m .
3
This is a much greater volume than the entire annular capacity so the well would be blowing wildly.
Note: In horizontal wells and while the gas is in the horizontal section there will be no noticeable
migration of gas. In highly deviated wells the migration can be very slowly or even zero. Even in
vertical wells it can be that no migration takes place.
8.12 Hydrates
The formation of hydrates is dependent upon a combination of the following conditions:
a. Presence of free water
b. Gas at or below it's dew point
c. Low temperature
d. High pressure
The hydrate problem is aggravated by pressure drop / gas expansion (through the choke) and
pressure pulsing.
As the gas passes through these restrictions the resulting pressure drop plus the sudden increase in
velocity cause “expansion cooling” of the gas immediately downstream of the choke.
Hydrates can cause severe problems by plugging valves or chokes and completely blocking flow.
Upstream pressure increases and this compounds the problem.
Prevention of hydrates will always be easier and better than the cure. It may be necessary to inject
methanol or glycol to suppress hydrate formation. Ports can be modified into the choke manifold for
this purpose.
The hydrate problem is virtually non-existent in Oil base muds. With Water base muds, maintaining a
high chloride concentration in the mud will lower the freezing point.
If hydrates do form and plug off the choke or kill line they can be very difficult to remove.
Considerable heat is required for decomposition, for example, circulating hot brine solution.
and if annular capacity is 8.23 ft/bbl then 553 ft becomes 67 bbls. This is the maximum volume of
influx that we could have at the shoe and if we calculate back using Boyles Law to find a tolerable
volume of original influx, the equation reads thus:
P1 x V1 = P2 x V2 or (2994 x 67) ÷5512 = V2 = 36 bbls.
Calculating our 40 bbl influx, then the volume at the shoe would be:
V2 = (5512 x 40) ÷2994 = 73 bbls.
This is clearly not viable to circulate out using the Driller’s Method. However, if the annulus volume
below the shoe is greater than the string volume then there will be kill mud in the annulus prior to
the bubble getting to the shoe and hence lowering the pressure at the shoe.
A 6360 litre gas influx (gradient 0.0271 bar/m) enters the well and the surface pressures after close
in are SIDPP = 36 bar, SICP = 49 bar.
3 3
and if annular capacity is 19 m/m then 184 m becomes (184 x 19) = 9.68 m . This is the
maximum volume of influx that we could have at the shoe and if we calculate back using Boyles
Law to find a tolerable volume of original influx, the equation reads thus:
3
P1 x V1 = P2 x V2 or (211 x 9.68) ÷380 = V2 = 5.37 m
3
Calculating our 6.360 m influx, then the volume at the shoe would be:
3
V2 = (380 x 6.36) ÷211 = 11.45 m .
This is clearly not viable to circulate out using the Driller’s Method. However, if the annulus volume
below the shoe is greater than the string volume then there will be kill mud in the annulus prior to
the bubble getting to the shoe and hence lowering the pressure at the shoe.
Solution:
Kg of Barite required per m3 of mud volume =
3
= 241, 37 kg/m
Volume to take out of original mud due to Barite addition without increasing the volume of mud
amount:
Weight of Barite required for mud density increase after reduced mud amount
For mud density in kg/l :
(1,59 1,44 )
x 1000 = 54.34 L/ m3
( 4,2 1, 44)
That means: 54.34 L/m³ x 263m³ : 1000 = 14.29m³ have to reduced of the old mud amount
(1,59 1,44 )
x 4200 = 228.26kg/ m3
( 4,2 1,44)
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Vertical Well (Metric/Bar) NAME :
INITIAL MAASP =
((C)
- Current Density) x Shoe TVD = 50
10.2 CASING SHOE DATA:
SIZE 13 3/8” in
M. DEPTH 1066 m
PUMP NO. 1 DISPL. PUMP NO. 2 DISPL. T.V. DEPTH 1066 m
13,89 l / stroke 13,89 l / stroke
HOLE DATA:
(PL) DYNAMIC P
RESSURE OSS
L [bar]
SIZE 12 1/4” in
SLOW PUMP
PUMP NO. 1 PUMP NO. 2
RATE DATA: M. DEPTH 2438 m
TOTAL WELL SYSTEM VOLUME (D+H) = (I) 175262 l 12618 stks 252 min
Kill Sheet Page 2a Driller`s Method. Step 1: Circulating out all the Kick.
PAGE 2 OF 2
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Vertical Well (Metric/Bar) NAME :
KICK DATA :
SIDPP 36 bar SICP 49 bar PIT GAIN 2400 litres
(J) x 100
(J) = ICP - FCP Bar --.--------- = Bar/100 strokes
(E)
72
60
50
40
30
20
10
0 5 10 X1000
ICP constant still all the Influx is out. STROKES
Kill Sheet Page 2b Driller`s Method. Step 2: Circulating in the Kill Mud.
PAGE 2 OF 2
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Vertical Well (Metric/Bar) NAME :
KICK DATA :
SIDPP 36 bar SICP 49 bar PIT GAIN 2400 litres
(J) x 100
(J) = ICP - FCP 32 Bar --.--------- = 2 Bar/100 strokes
(E)
STATIC & DYNAMIC DRILL PIPE PRESSURE [bar]
72
60
50
FCP now Constant
40
36
30
Keep Casing
Pressure Constant
20
10
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Vertical Well (Metric/Bar) NAME :
INITIAL MAASP =
((C)
- Current Density) x Shoe TVD = 50
10.2 CASING SHOE DATA:
SIZE 13 3/8” in
M. DEPTH 1066 m
PUMP NO. 1 DISPL. PUMP NO. 2 DISPL. T.V. DEPTH 1066 m
13,89 l / stroke 13,89 l / stroke
HOLE DATA:
(PL) DYNAMIC P
RESSURE OSS
L [bar]
SIZE 12 1/4” in
SLOW PUMP
PUMP NO. 1 PUMP NO. 2
RATE DATA: M. DEPTH 2438 m
TOTAL WELL SYSTEM VOLUME (D+H) = (I) 175262 l 12618 stks 252 min
DATE :
International Well Control Forum
Surface BOP Kill Sheet - Vertical Well (Metric/Bar) NAME :
KICK DATA :
SIDPP 36 bar SICP 49 bar PIT GAIN 2400 litres
(J) x 100
(J) = ICP - FCP 32 Bar --.--------- = 2 Bar/100 strokes
(E)
STATIC & DYNAMIC DRILL PIPE PRESSURE [bar]
72
60
50
FCP
40
Surface
to
30
Bit Bit to Surface
20
10
If tripping out with an exposed shallow gas zone the following precautions must be followed after
performing a flow check and lining up the trip tank:
The Drilling Supervisor must be on the drillfloor for the whole trip
Pump out of the hole, circulating out singles for a Kelly rig, as per appropriate drilling
practices, until at least three joints above the gas zone.
Whilst handling the bha the hole must continue to be kept full and the fill-up volume
monitored closely
9.5.7 Losses
If losses are encountered, they are to be cured using Lost Circulation Material or cement.
Full returns must be regained before proceeding to drill ahead.
If the losses cannot be cured, possible courses of action include
(a) plugging back with cement,
(b) setting casing high, or
(c) abandoning the hole.
Drilling ahead with total losses and using a floating mudcap may be considered in areas where the
geophysical structure is very well known and appropriate dispensation obtained.
have kill mud of at least the pilot hole content premixed (at recommended 0.12 sg heavier than
original mud) and stored in such a way that it can be pumped immediately at maximum rate
The dynamic kill attempt is described below. At first sign of flow, the following action is required:
(a) pump mud immediately at maximum pump rate
(b) open diverter valve(s) and close diverter element (accomplished on a single actuator)
(c) if the well continues to flow, pump heavier mud at maximum pump rate.
(d) if the well still continues to flow after the heavier mud has been pumped, carry on
pumping mud at maximum rate. When running out of mud, change over to water. Do
not reduce the pump speed.
At this stage, the drilling location may need to be abandoned, depending on the severity and type
of flow and the condition of the diverter equipment. However should a risk assessment deem it
practicable and safe, further dynamic kill attempts may be made as follows:
(a) prepare another batch of heavier mud whilst pumping mud or water at maximum rate
(use mud which is 0,25 sg heavier than the original mud weight).
(b) pump heavy mud at maximum rate.
(c) repeat sequence if dynamic killing is still unsuccessful, but do not use excessive mud
weight which could result in formation breakdown.
Note: The procedure for handling a shallow gas kick with a diverter system is also given in the
form of decision trees in Figure 9-1 below.
If a dynamic kill is unsuccessful (or not attempted) the well must continue to be diverted until it
bridges or depletes. However, most diverter systems are not capable of coping with prolonged
shallow gas flows and will eventually fail as a result of erosion thus an evacuation plan should be
ready to be implemented as soon as conditions dictate.
NO
Well continues to flow
excessively ?
Activate Blow -out Emergency Procedure
Evacuate non -essential personnel
Abandon location as soon as diverter
system fails
NO
Well continues to flow
excessively ? Increase
mud weight
YES
YES
Pump (0.25 SG ) heavier mud Gas cut mud
at maximum rate
NO
Flow Check
Appendix
Well Control Manual2 Shallow Gas Page 131 of 142
Well Control Manual Rev 1.01, June 2010
FLOW RATE Gallons/Minute x 0.003785 to give Cubic Metres per Minute (rn3/min)
Barrels/Minute x 0.159 to give Cubic Metres per Minute (m3/min)
Cubic Metres/minute x 6.2905 to give Barrels per Minute (bbl/min)
Cubic Metres/minute x 264.2 to give Gallons per Minute (gals/min)
MUD WEIGHT PPG x 0.052 to give Pounds per Square Inch per Foot (psi/ft)
TO PRESSURE [Pressure Gradient]
GRADIENT SG x 433 to give Pounds per Square Inch per Foot (psi/ft)
lb/ft3 ÷ 144 to give Pounds per Square Inch per Foot (psi/ft)
Kg/m3 x 0.000434 to give Pounds per Square Inch
Or ÷ 2303 per Foot (psi/ft)
Kg/m3 x 0.00982 to give kilo Pascals per Metre (kPa/m)
10.2 Formulae - SI
Drilling Fluid Density [kg/m 3 ]
1. PRESSURE GRADIENT [kPa/m] =
102
2. DRILLING FLUID DENSITY [kg/m³] = Pressure Gradient [kPa/m] x 102
3
Drilling Fluid Density [kg / m ]
3. HYDROSTATIC PRESSURE [kPa] = x True Vertical Depth [m]
102
4. FORMATION PRESSURE [kPa] = Hydrostatic Pressure In Drill String [kPa] + SIDPP [kPa]
3
Pump Output [m / min]
7. ANNULAR VELOCITY [m/min] = 3
Annular Volume [m / m]
3
SCR or PL [kPa] x Kill Fluid Density [kg / m ]
9. FINAL CIRCULATING PRESSURE [kPa] = 3
Original Drilling Fluid Density [kg / m ]
11. SHUT IN CASING PRESSURE [kPa] = {(Drilling Fluid Grad [kPa/m] - Influx Grad [kPa/m]) x Influx TVD Height [m]} + SIDPP [kPa]
3
Kick Size [m ]
13. HEIGHT OF INFLUX ALONG HOLE [m] = 3
Annular Volume [m / m]
3
Drilling Fluid Density [kg / m ] SICP [kPa] - SIDPP [kPa]
14. GRADIENT OF INFLUX [kPa/m] = -
102 Influx TVD Height [m]
P1 x V1 P1 x V1
21. BOYLE-GAY LUSAC LAW: = P1 V1 = P2 V2 P2 = V2 =
V2 P2
3 3
Drilling Fluid Density [kg / m ] x Metal Displ [m / m]
22. PRESSURE DROP PER MT. TRIPPING DRY PIPE [kPa/m] = 3 3
Casing Capacity [m / m] - Metal Displ [m / m] x 102
3 3 3
Drilling Fluid Density [kg / m ] x (Metal Displ [m / m] + Pipe Capacity [m / m])
23. PRESSURE DROP PER MT. TRIPPING WET PIPE [kPa/m] = 3
Annular Capacity [m / m] x 102
3
Length of Drill Collars [m] x Metal Displ [m / m]
24. LEVEL DROP FOR POOH DRILL COLLARS [m] = 3
Casing Capacity [m / m]
3 3
Overbalance [kPa] x (Casing Capacity [m / m] - Metal Displ [m / m]) x 102
25. PIPE TO PULL BEFORE WELL STARTS TO FLOW [m] = 3 3
Drilling Fluid Density [kg / m ] x Pipe Displ [m / m]
3. HYDROSTATIC PRESSURE [psi] = Drilling Fluid Density [ppg] x 0.052 x True Vertical Depth [ft]
4. FORMATION PRESSURE [psi] = Hydrostatic Pressure In Drill String [psi] + SIDPP [psi]
Pressure [psi]
5. EQUIVALENT DRILLING FLUID DENSITY [ppg] =
True Vertical Depth [ft] x 0.052
SIDPP [psi]
10. KILL FLUID DENSITY [ppg] = + Original Drilling Fluid Density [ppg]
TVD [ft] x 0.052
11. SHUT IN CASING PRESSURE [psi] = {(Drilling Fluid Grad [psi/ft] - Influx Grad [psi/ft]) x Influx TVD Height [ft]} + SIDPP [psi]
2
New SPM
16. NEW PUMP PRESSURE WITH NEW PUMP STROKES [psi] = Current Pressure [psi] x (only approximate!)
Old SPM
18. NEW MAASP AFTER KILL [psi] = (Max. Allow. Drill. Fluid Density [ppg] - Kill Fluid Density [ppg]) x 0.052 x Shoe TVD
[ft]
(Kill Fluid Density [ppg] - Original Drill Fluid Density [ppg]) x 1500
19. BARYTE TO RAISE DRILLING FLUID DENSITY [lbs/bbl] =
35.8 - Kill Fluid Density [ppg]
P1 x V1 P1 x V1
21. BOYLE-GAY LUSAC LAW: = P1 V1 = P2 V2 P2 = V2 =
V2 P2
Drilling Fluid Density [ppg] x 0.052 x (Metal Displ [bbls / ft] + Pipe Capacity [bbls / ft])
23. PRESSURE DROP PER FT. TRIPPING WET PIPE [psi/ft] =
Annular Capacity [bbls / ft]
Overbalance [psi] x (Casing Capacity [bbls / ft] - Metal Displ [bbls / ft])
25. PIPE TO PULL BEFORE WELL STARTS TO FLOW [ft] =
Drilling Fluid Density [ppg] x 0.052 x Metal Displ [bbls / ft]
4. FORMATION PRESSURE [bar] = Hydrostatic Pressure In Drill String [bar] + SIDPP [bar]
Pressure [bar]
5. EQUIVALENT DRILLING FLUID DENSITY [kg/l] =
True Vertical Depth [m] x 0.0981
6. PUMP OUTPUT [liter/min] = Pump Output [litter/stk] x Pump Speed [spm]
SIDPP [bar]
10. KILL FLUID DENSITY [kg/l] = + Original Drilling Fluid Density [kg/l]
TVD [m] x 0.0981
or SHUT IN CASING PRESSURE [bar] = Drill Fluid Grad [bar/m] - Influx Grad [bar/m] x Influx TVD Height [m] + SIDPP [bar]
2
New SPM
16. NEW PUMP PRESSURE WITH NEW PUMP STROKES [bar] = Current Pressure [bar] x (only approximate !)
Old SPM
Surface leak - off [bar]
17. MAX. ALLOWABLE DRILLING FLUID DENSITY [kg/l] = + Test Drilling Fluid Density [kg/l]
Casing Shoe TVD [m] x 0.0981
18. NEW MAASP AFTER KILL [bar] = {Max. Allow. Drill Fluid Density [kg/l] - Kill Fluid Density [kg/l]} x 0.0981 x Shoe TVD [m]
P1 x V1 P1 x V1
21. BOYLE-GAY LUSAC LAW: = P1 V1 = P2 V2 P2 = V2 =
V2 P2