Está en la página 1de 3

PLAN DE INVERSION MENSUAL

DEC-11 A ENERO 11 ENE-12 A FEB 15 FEB-16 A FEB 26


MES 1 MES 2 MES 3
ITEM DESCRIPCION UNIDAD CANTIDAD VALOR UNITARIO VALOR TOTAL % INVERSION % INVERSION % INVERSION
1.00 OBRAS PRELIMINARES
2
1.01 LOCALIZACION Y REPLANTEO M 186.25 $ 6,061.00 $ 1,128,861.25 100% $ 1,128,861.25 0% $ - 0% $ -
SUBTOTAL $ 1,128,861.25 0 $ 1,128,861.25 $ - $ -
2.00 CIMENTACIÓN
3
2.01 EXCAVACION MANUAL MATERIAL COMUN M 11.11 $ 31,090.00 $ 345,254.45 100% $ 345,254.45 0% $ - 0% $ -
3
2.02 CONCRETO CICLOPEO FY=14 MPA M 8.14 $ 576,540.00 $ 4,693,035.60 100% $ 4,693,035.60 $ -
2.03 VIGA DE CIMENTACION 0,20X0,20 M ML 203.50 $ 64,648.00 $ 13,155,868.00 100% $ 13,155,868.00 0% $ - 0% $ -
2.04 ACERO FY:60.000 PSI KG 2171.17 $ 6,558.00 $ 14,238,532.86 100% $ 14,238,532.86 0% $ - 0% $ -
SUBTOTAL $ 32,432,690.91 100% $ 32,432,690.91 0% $ - 0% $ -
3.00 ESTRUCTURA EN CONCRETO
3.01 VIGA AEREA 0,10 X 0,20 CCTO 3.000 PSI ML 175.25 $ 57,772.00 $ 10,124,543.00 100% $ 10,124,543.00 0% $ - 0% $ -
3.02 COLUMNA EN CCTO 3.000 PSI 0,10 X 0,20 M ML 73.29 $ 46,987.00 $ 3,443,677.23 100% $ 3,443,677.23 0% $ - 0% $ -
2
3.03 PLACA PARA TANQUE AERERO E=0,10M M 13.13 $ 195,873.00 $ 2,571,812.49 100% $ 2,571,812.49 0% $ - 0% $ -
3.04 IMPERMEABILIZACION PLACA MANTO ASFALTICO CON FOIL DE ALUM.M2 13.13 $ 64,557.00 $ 847,633.41 100% $ 847,633.41 0% $ - 0% $ -
SUBTOTAL $ 16,987,666.13 100% $ 16,987,666.13 $ - $ -
4.00 MAMPOSTERIA
2
4.01 MURO EN BLOQUE No. 5 M 301.65 $ 52,148.00 $ 15,730,444.20 100% $ 15,730,444.20 0% $ - 0% $ -
2
4.02 PAÑETE LISO SOBRE MURO MORT-1:4, E=0,02 M M 230.30 $ 23,805.00 $ 5,482,291.50 100% $ 5,482,291.50 0% $ - 0% $ -
2
4.03 PAÑETE IMPERMEABILIZADO SOBRE MURO M 12.05 $ 37,460.00 $ 451,393.00 100% $ 451,393.00 0% $ - 0% $ -
4.04 MEDIA CAÑA EN MORTERO 1:4 ML 29.50 $ 15,749.00 $ 464,595.50 100% $ 464,595.50 0% $ - 0% $ -
2
4.05 MESON EN CCTO REF 3.000 PSI E=0,07 M M 5.00 $ 97,204.00 $ 486,020.00 100% $ 486,020.00 0% $ - 0% $ -
2
4.06 PINTURA EN VINILO-FACHADA PRINCIPAL M 69.45 $ 13,131.00 $ 911,947.95 100% $ 911,947.95 0% $ - 0% $ -
SUBTOTAL $ 23,526,692.15 100% $ 23,526,692.15 0% $ - 0% $ -
5.00 PISOS
2
5.01 MORTERO DE NIVELACION E=0,04 M M 170.20 $ 25,587.00 $ 4,354,907.40 0% $ - 100% $ 4,354,907.40 0% $ -
2
5.02 PISO EN GRESS M 159.88 $ 46,566.00 $ 7,444,972.08 0% $ - 100% $ 7,444,972.08 0% $ -
5.03 GUARDA ESCOBA ANCHO 10CM ML 176.08 $ 25,017.00 $ 4,404,993.36 0% $ - 100% $ 4,404,993.36 0% $ -
2
5.04 PLACA DE PISO CONCRETO DE 3000 PSI E=0,07 M M 170.20 $ 81,977.00 $ 13,952,485.40 25% $ 3,488,121.35 75% $ 10,464,364.05 0% $ -
SUBTOTAL $ 30,157,358.24 11.6% $ 3,488,121.35 88.4% $ 26,669,236.89 $ -
PLAN DE INVERSION MENSUAL
DEC-11 A ENERO 11 ENE-12 A FEB 15 FEB-16 A FEB 26
MES 1 MES 2 MES 3
ITEM DESCRIPCION UNIDAD CANTIDAD VALOR UNITARIO VALOR TOTAL % INVERSION % INVERSION % INVERSION
6.00 CUBIERTA
6.01 CORREA EN TUBO RECTANGULAR DE 3 X 1 1/2" ML 85.00 $ 45,516.00 $ 3,868,860.00 100% $ 3,868,860.00 0% $ - 0% $ -
2
6.02 CUBIERTA EN TEJA ZINC ARQUITECTONICO M 243.08 $ 39,426.00 $ 9,583,672.08 100% $ 9,583,672.08 0% $ - 0% $ -
6.03 CABALLETE FIJO ZINC ARQUITECTONICO ML 5.00 $ 15,627.00 $ 78,135.00 100% $ 78,135.00 0% $ - 0% $ -
SUBTOTAL $ 13,530,667.08 100% $ 13,530,667.08 $ - $ -
7.00 INSTALACIONES HIDRAULICAS
7.01 PUNTO HIDRAULICO PVC-P 1/2" UND 25.00 $ 34,665.00 $ 866,625.00 100% $ 866,625.00 0% $ - 0% $ -
7.02 RED DE DISTRIBUCION PVC-P 1/2" ML 101.55 $ 17,825.00 $ 1,810,128.75 100% $ 1,810,128.75 0% $ - 0% $ -
7.03 LLAVE TERMINAL DE 1/2" (INSTALADA) UND 5.00 $ 40,270.00 $ 201,350.00 67% $ 134,233.33 33% $ 67,116.67 0% $ -
7.04 TANQUE LAVADERO PREFABRICADO 0,70X1,20X0,80 MTS UND 5.00 $ 455,766.00 $ 2,278,830.00 0% $ - 100% $ 2,278,830.00 0% $ -
7.05 TANQUE PLASTICO DE 500 L. INCLUYE INSTALACION UND 5.00 $ 330,000.00 $ 1,650,000.00 0% $ - 100% $ 1,650,000.00 0% $ -
SUBTOTAL $ 6,806,933.75 41.3% $ 2,810,987.08 58.7% $ 3,995,946.67 0% $ -
8.00 INSTALACIONES ELECTRICAS
8.01 CABLE PARA ACOMETIDA ELECTRICA CU THHN/THW Nº 8 AWG ML 75.00 $ 20,278.00 $ 1,520,850.00 0% $ - 100% $ 1,520,850.00 0% $ -
8.02 TABLERO PARCIAL 4 CIRCUITOS CON BREAKERS UND 5.00 $ 176,746.00 $ 883,730.00 0% $ - 100% $ 883,730.00 0% $ -
8.03 PUNTO ELECTRICO (TOMA CORRIENTE 110V) UND 25.00 $ 106,861.00 $ 2,671,525.00 0% $ - 100% $ 2,671,525.00 0% $ -
8.04 PUNTO ELECTRICO MONOFASICO DE ALUMBRADO UND 30.00 $ 86,061.00 $ 2,581,830.00 0% $ - 100% $ 2,581,830.00 0% $ -
SUBTOTAL $ 7,657,935.00 0 $ - $ 7,657,935.00 $ -
9.00 INSTALACIONES SANITARIAS
9.01 PUNTO SANITARIO DE 2" UND 10.00 $ 52,137.00 $ 521,370.00 100% $ 521,370.00 0% $ - 0% $ -
9.02 PUNTO SANITARIO DE 3" UND 15.00 $ 67,128.00 $ 1,006,920.00 50% $ 503,460.00 50% $ 503,460.00 0% $ -
9.03 PUNTO SANITARIO DE 4" UND 5.00 $ 75,748.00 $ 378,740.00 0% $ - 100% $ 378,740.00 $ -
9.04 TUBERIA PVC-SANITARIA DE 4" ML 66.20 $ 46,006.00 $ 3,045,597.20 100% $ 3,045,597.20 0% $ - 0% $ -
9.05 CAJA DE INSPECCION 0,60 X 0,60 MT UND 5.00 $ 333,126.00 $ 1,665,630.00 0% $ - 100% $ 1,665,630.00 0% $ -
9.06 LAVAMANOS BLANCO DE 1 LLAVE UND 5.00 $ 225,243.00 $ 1,126,215.00 0% $ - 100% $ 1,126,215.00 0% $ -
9.07 SANITARIO COMPLETO INSTALADO UND 5.00 $ 352,926.00 $ 1,764,630.00 0% $ - 100% $ 1,764,630.00 0% $ -
9.08 JUEGO DE INCRUSTACIONES UND 5.00 $ 80,457.00 $ 402,285.00 0% $ - 100% $ 402,285.00 0% $ -
9.09 DUCHA SENCILLA CON REGISTRO UND 5.00 $ 66,109.00 $ 330,545.00 0% $ - 100% $ 330,545.00 0% $ -
9.10 TUBERIA PVC AGUAS LLUVIAS 2" ML 26.50 $ 25,674.00 $ 680,361.00 0% $ - 100% $ 680,361.00 0% $ -
SUBTOTAL $ 10,922,293.20 0 $ 4,070,427.20 $ 6,851,866.00 $ -
PLAN DE INVERSION MENSUAL
DEC-11 A ENERO 11 ENE-12 A FEB 15 FEB-16 A FEB 26
MES 1 MES 2 MES 3
ITEM DESCRIPCION UNIDAD CANTIDAD VALOR UNITARIO VALOR TOTAL % INVERSION % INVERSION % INVERSION
10.00 ACABADOS
2
10.01 ENCHAPE EN CERAMICA M 39.55 $ 53,237.00 $ 2,105,523.35 0% $ - 100% $ 2,105,523.35 0% $ -
2
10.02 PISO EN CERAMICA 20,5 X 20,5 M M 10.33 $ 55,743.00 $ 575,825.19 0% $ - 100% $ 575,825.19 0% $ -
10.03 LAVAPLATOS EN ACERO INOX.CON BANDEJA L= 1,00M UND 5.00 $ 334,567.00 $ 1,672,835.00 0% $ - 100% $ 1,672,835.00 0% $ -
10.04 REJILLA DE PISO CON SOSCO DE 3" UND 10.00 $ 25,396.00 $ 253,960.00 0% $ - 100% $ 253,960.00 0% $ -
SUBTOTAL $ 4,608,143.54 0% $ - $ 4,608,143.54 $ -
11.00 CARPINTERIAS
PUERTA EN LAMINA COLL-ROLLED CAL-18 ANTICORROSIVO Y 2
11.01 M $ 288,504.00 $ 12,376,821.60
CERRADURA 42.90 0% $ - 100% $ 12,376,821.60 0% $ -
2
11.02 VETANA METALICA LAM.CAL.18 CON VIDRIOS INCL REJA M 36.00 $ 283,731.00 $ 10,214,316.00 0% $ - 63% $ 6,383,947.50 37.5% $ 3,830,368.50
2
11.03 PINTURA EN ESMALTE M 76.50 $ 15,382.00 $ 1,176,723.00 0% $ - 0% $ - 100% $ 1,176,723.00
SUBTOTAL $ 23,767,860.60 0% $ - $ 18,760,769.10 $ 5,007,091.50
SUBTOTAL OBRA FISICA $ 171,527,101.85 $ 97,976,113.15 $ 68,543,897.20 $ 5,007,091.50
12.00 CONTROL AMBIENTAL
12.01 CONTROL AMBIENTAL GL 1.00 $ 1,586,398.15 $ 1,586,398.15 0% $ - 0% $ - 100% $ 1,586,398.15
SUBTOTAL $ 1,586,398.15 $ - $ 1,586,398.15
TOTAL $ 173,113,500.00 56.6% $ 97,976,113.15 39.6% $ 68,543,897.20 3.81% $ 6,593,489.65

___________________________________________
CRISTIAN EDUARDO CAMARGO Q
Representante legal

También podría gustarte