CONTENTS
1.0 PURPOSE
1.1 Overview
2 Warehouse 12m*3.6m*3m 2
3 Meeting Room 12m*3.6m*3m 1
Welding Rod
4 12m*3.6m*3m 1
Drying Room
5 Office 12m*3.6m*3m 2
6 Medical Room 12m*3.6m*3m 1
7 Dinner Room 12m*3.6m*3m 1
Pre-separator Tank 15
16
Generator
Material Storage
500KW
20m*30m
2
1
17 Prefabrication
20m*35m 1
Platform
18 Fence 2.5m 520m
19 T Wall 2.5m 160m
20 Bunker 2.5*2.5*6m 3
21 Gate 8*2.5m 2
22 Gate 5*2.5*6m 1
2 Warehouse 12m*3.6m*3m 2
3 Meeting Room 12m*3.6m*3m 1
Welding Rod
4 12m*3.6m*3m 1
Drying Room
5 Office 12m*3.6m*3m 2
6 Medical Room 12m*3.6m*3m 1
7 Dinner Room 12m*3.6m*3m 1
15 Generator 500KW 2
16 Generator 100KW 2
17 Material Storage 20m*30m 1
18 Prefabrication
20m*40m 1
Platform
19 Fence 2.5m 700m
20 T Wall 2.5m 160m
21 Bunker 2.5*2.5*6m 5
22 Gate 8*2.5m 3
23 Gate 5*2.5*6m 1
2 Warehouse 12m*3.6m*3m 2
3 Meeting Room 12m*3.6m*3m 1
Welding Rod
4 12m*3.6m*3m 1
Drying Room
5 Office 12m*3.6m*3m 2
6 Medical Room 12m*3.6m*3m 1
7 Dinner Room 12m*3.6m*3m 1
100t mobile crane (LTM1100-5.2)and 25t mobile crane (KATO NK-250E-Ⅲ)will be used for the lifting
works .
NOTE:- Total lifting lode = Net Weight + Weight of rigging accessories + Weight of hook block and dynamic rope.
-Rate of capacity load of crane = Total lifting lode÷Chart capacity in working max radius×100%.
Method of lifting pump skid is “Single Crane Hoisting Method”, construction flow chart as follow:
Crane in position
Sling connection
Joint inspection
Trial hoisting
Formal hoisting
Object in position
Sling release
Crane demobilization
Fig 3.1 Construction flow chart of the “Single Crane Hoisting Method”
Staff involved in lifting must be certificate,ensure that crane operators are qualified based on the
requirements set by local regulatory authorities.
Each mobile crane must be inspected by a competent person for mechanical defects upon its arrival, once
again before its use on the site, and monthly thereafter.
All lifting tackle must be certified.
The lift supervisor shall inspect all tackle prior to use.
Any damaged tackle item shall be marked ‘NOT FOR USE’ and returned to depot for disposal.
Nylon slings must be protected from sharp corners using suitable packing.
The safe working load (SWL) must be prominently displayed on the boom of anycrane and clearly marked
on other lifting devices.
Considering the total load to be lifted (including applicable crane component weights) and crane
configuration, the lift must not exceed 85 percent of the crane capacity for the greatest radius the load
achieves during pick, swing, or set. If the load exceeds 85%.the lift will be classified as a critical lift.
If changing the crane configuration within the manufacturer specifications provides greater gross capacity,
the modified configuration must be used to keep the lift below 85 percent capacity. If not, a larger capacity
crane must be used.
A lift is classified as critical, critical lifts must have a formal Critical Lift Plan/Rigging study before being
executed.
PROBABILITY
E. VERY LIKELY TO OCCUR NO CONTROLS IN PLACE
D. LIKELY TO OCCUR ONLY ONE PROCEDURAL CONTROL IS IN PLACE
C. COULD OCCUR MULTIPLE CONTROLS ARE IN PLACE BUT INCLUDE ONLY PROCEDURAL BARRIERS.
B. UNLIKELY TO OCCUR MULTIPLE CONTROLS ARE IN PLACE WHICH INCLUDE PROCEDURAL AND ACTIVE BARRIERS.
A. VERY UNLIKELY TO OCCUR MULTIPLE CONTROLS ARE IN PLACE WHICH INCLUDE AT LEAST ONE PASSIVE BARRIER, ACTIVE BARRIERS AND PROCEDURAL BARRIERS.
ATTACHMENTS