General 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3

MASSARO - MADELCO - VOLTERRA ( 81 VIVIENDAS ) SEMANA ACTUAL PRUEBAS CEA

ACUMULADO PROGRAMADO 2.00% 6.67% 12.67% 19.67% 28.67% 41.00% 46.33% 54.33% 63.67% 71.33% 83.00% 92.33% 97.33% 99.33% 100.00%
URBANIZACION ACUMULADO AVANCE REAL 0.00% 0.00% 0.00% 1.00% 2.00% 3.00% 5.00% 8.00% 11.00% 13.00% 15.00% 16.00%
DIFERENCIA RESPECTO A LO PROGRAMADO -2.00% -6.67% -12.67% -18.67% -26.67% -38.00% -41.33% -46.33% -52.67% -58.33% -68.00% -76.33% -97.33% -99.33% -100.00%
AVANCE SEMANAL PROGRAMADO 2.00% 4.67% 6.00% 7.00% 9.00% 12.33% 5.33% 8.00% 9.33% 7.67% 11.67% 9.33% 5.00% 2.00% 0.67%

0.3333333 2.00% 4.67% 6.00% 7.00% 9.00% 12.33% 5.33% 8.00% 9.33% 7.67% 11.67% 9.33% 5.00% 2.00% 0.67%

DESGLOSE SEMANAL DE PROGRAMA


PLATAFORMAS

AREA SOCIAL

MUROS DE CONTENCION 0.00% 0.00% 0.00% 1.00% 1.00% 1.00% 2.00% 3.00% 3.00% 2.00% 2.00% 1.00%
RED DRENAJE SANITARIO 4.00% 6.00% 9.00% 10.00% 10.00% 11.00% 5.00% 8.00% 8.00% 10.00% 5.00% 6.00% 5.00% 3.00%
RED DRENAJE PLUVIAL 0.00% 0.00% 0.00% 0.00% 0.00% 5.00% 9.00% 13.00% 18.00% 11.00% 28.00% 15.00% 1.00%
TERRACERIAS

RED AGUA POTABLE 2.00% 8.00% 9.00% 11.00% 17.00% 21.00% 2.00% 3.00% 2.00% 2.00% 2.00% 7.00% 9.00% 3.00% 2.00%
RED GAS
URBANIZACIÓN RED ELECTRICA

RED VOZ Y DATOS

BANQUETAS Y GUARNICIONES

PAVIMENTOS

AREA DE CONTENEDOR

BARDAS PERIMETRALES

AREAS VERDES

SEÑALETICA

URBANIZACIÓN - MADELCO
COND. VOLTERRA, ETAPA "C" ( 81 VIVIENDAS )
120.00%

100.00%
Porcentaje Avance

80.00%

60.00%

40.00%

20.00%

0.00%
41 42 43 44 45 46 47 48 49 50 51 52 1 2 3
Avance Programado 2.00% 6.67% 12.67% 19.67% 28.67% 41.00% 46.33% 54.33% 63.67% 71.33% 83.00% 92.33% 97.33% 99.33% 100.00%
Avance Real 0.00% 0.00% 0.00% 1.00% 2.00% 3.00% 5.00% 8.00% 11.00% 13.00% 15.00% 16.00%