Está en la página 1de 3

Inspection Checklist Form

After all the hard works in designing the electrical systems done by the
Consultant; now, it is the time for electrical contractor to implement that design.

The question is...how to check that all the works carried out by the contractor
are in properly manner and according to the drawing?

This is where the Inspection Checklist takes place. Inspection Checklist is


crucial in determining that those works done in accordance to the drawings and
tare checking had been carried out by the consultant.

Below are few samples of inspection checklist than can be used as guidance for
you!

1. Opening and Penetration Inspection Checklist


2. Material At Site Checklist
3. Inspection Of Excavation & Installation of HDPE Pipes
4. Inspection Of HDPE Pipes (Mandrel Test)
5. Preliminary Earthing System - Pile Cap
6. Earthing System - Installation & Inspection Check list
7. Earthing/Lightning System - Final Testing & Inspection Checklist
8. Laying of Power Cable & Back Filling Inspection Checklist
9. Cut and Joint 33kV and Pilot Cables Inspection Checklist
10. 33kV HT Gas-Insulated Switchgear (GIS) Installation Inspection Checklist
11. UPVC Conduit - Installation & Inspection Checklist
12. Conduit-Installation & Inspection Checklist
13. Cable Ladder,Tray and Trunking-Installation & Inspection Checklist
14. Cable - Installation & Inspection Checklist
15. Light Fitting and Speaker - Installation & Inspection Checklist
16. Small Power and Lighting Switches Installation Inspection Checklist
17. Light Fitting,Speaker and CCTV Camera Inspection Checklist
18. DC Power Supply Installation Inspection Checklist
19. Busduct Installation Inspection Checklist
20. Generator Set and Acoustic Treatment Installation Inspection Checklist
21. LV Main Switchboard Installation Inspection Checklist
22. High Mast Installation Inspection Checklist
23. Street Lighting Installation Inspection Checklist
24. Cabling and Termination Checklist
25. Cable Continuity Test Checklist
26. Insulation Resistance Test Checklist
27. Firestop System - Installation & Inspection Checklist
28. Underfloor Trunking Inspection Checklist
29. Data Face Plate Installation Inspection Checklist
DOC. REF. :
PROJECT TITLE

OPERATION
REQUEST FOR INSPECTION (RFI)
Subcontractor : Date :
Location : Time :

Reference Reference
Drawing Documents

Work Item

Activity

Originator Acknowledged by
Participant Main Contractor Main Contractor Consultant's Engineer *Owner's Rep / Engineer
(Operation) (QA/QC) Representative *(if applicable)
Signature

Name
Date
To be attended by

Inspection Results :

Inspection passed. The Contractor is allowed to proceed with the works

Remedial works listed below to be completed and inspection is required after remedial works

Remedial works listed below to be completed but no further inspection required

Rejected

Remarks/Comments :

Inspected by
Main Contractor Main Contractor Consultant's Engineer *Owner's Rep / Engineer
Participant
(Operation) (QA/QC) Representative *(if applicable)

Signature

Name
Date
To be attended by
DOC. REF. :
PROJECT TITLE

QUALITY MANAGEMENT SYSTEM (QMS)


MATERIAL / EQUIPMENT RECEIVING INSPECTION
Material / Equipment Name Transport No.: MRI No.:

D / Order No.: Date:

Item Description Yes No Checking Method Remarks

1.0 Check Delivery Documents are in order (where applicable )

a Delivery Order match items / quantity

b Factory Test Certificates Refer to Delivery


Documents
c Mill Certificates

2.0 Conduct Physical Check (where applicable )


Goods in packages with no physical
a Visual
damage
Dimensional Check (where stipulated / Measuring Tape /
b
specified ) Calibre
c De-coloration Visual

d Grade of Material Comply To Order? Specification

e Serviceability Specification

New or Reconditioned ('yes'


f Visual / Specification
for new, 'no' for reconditioned)

Inspection Comments: The delivered goods inspected are: In Order Rejected

Note:
1) Accepted goods register to Stock Card
2) Rejected goods to be sprayed or marked 'X': RED by permanent marker & segregate the items and inform Operations & Purchasing Dept. for further action.

Name / Dept
Inspected by Signature Date Remarks
(for Subcon; state company )

Main Contractor

Subcontractor

The Subcontractor confirmed acknowledgement of receipt of the above mentioned material / equipment by their representative endorsement, and
shall be held responsible for the handling, storing and preservations of the transferred items in accordance to qualm

Note:
Delete where applicable
Add items in blank space where necessary

También podría gustarte