CONSTRUCTION OF MADUNAGHAT WATER TREATMENT PLANT AND PATENGA BOOSTER PUMP STATION

ID Task Name Duration Start Finish


October November December January February
10/28 11/4 11/11 11/18 11/25 12/2 12/9 12/16 12/23 12/30 1/6 1/13 1/20 1/27 2/3 2/10 2/17 2/24
1
INTAKE SCHEDULE 102 days Sat 11/11/17 Tue 2/20/18
2
Zone-1 97 days Thu 11/16/17 Tue 2/20/18
3
Wall at -1.5 Level 1 day Thu 11/16/17 Thu 11/16/17
4
Wall at +0.8 Level 1 day Thu 11/30/17 Thu 11/30/17
5
Wall at +1.6 Level 1 day Wed 12/13/17 Wed 12/13/17
6
Slab at +1.8 Level 1 day Fri 12/29/17 Fri 12/29/17
7
Wall at +4.2 Level 1 day Sat 1/13/18 Sat 1/13/18
8
Wall at +6.3 Level 1 day Sun 1/28/18 Sun 1/28/18
9
Slab at +6.5 Level 1 day Tue 2/20/18 Tue 2/20/18
10
Zone-2 99 days Tue 11/14/17 Tue 2/20/18
11
Wall at -2.5 Level 1 day Tue 11/14/17 Tue 11/14/17
12
Wall at -0.3 Level 1 day Tue 11/28/17 Tue 11/28/17
13
Wall at +2 Level 1 day Sun 12/10/17 Sun 12/10/17
14
Wall at +4.3 Level 1 day Sat 12/23/17 Sat 12/23/17
15
Wall at +6.3 Level 1 day Fri 1/5/18 Fri 1/5/18
16
Slab at +6.5 Level 1 day Tue 2/20/18 Tue 2/20/18
17
Zone-3 71 days Sat 11/11/17 Sat 1/20/18
18
Wall at -3.6 Level 1 day Sat 11/11/17 Sat 11/11/17
19
Wall at -1.2 Level 1 day Mon 11/27/17 Mon 11/27/17
20
Wall at +1.2 Level 1 day Mon 12/4/17 Mon 12/4/17
21
Wall at +3.6 Level 1 day Tue 12/19/17 Tue 12/19/17
22
Slab at +4.5 Level 1 day Sat 1/20/18 Sat 1/20/18

Task Project Summary Inactive Summary Manual Summary External Milestone


Split External Tasks Manual Task Start-only Progress
Project: Project1
Milestone External Milestone Duration-only Finish-only Deadline
Summary Inactive Milestone Manual Summary Rollup External Tasks