Address: Pueblo,Cagayan de Oro City
Date Estimate: November 04, 2015

Peace in Christ! In connection of the above-said subject, we would like to present to you our formal proposal for you to evaluate
and consider.

SCOPE OF WORKS

Item No. Description Item Total

1.0 SITE WORKS (clearing ) Php 7,698.00


- Site Clearing/Demolition of Wall on area to be close and door relocation
- Preparation of Area
- Scaffolds and Temporary Facilities
- Removal of Existing Tiles on Master's Toilet & Bath Only

2.0 TOILET WORKS (installation of new tiles,ceiling and piping repairs) Php 130,120.00
- Installation of New Tiles for Master's Toilet and Bath Only (floor-ceiling)
- New Ceiling for Master's Toilet and Bath Only
- Repair of Plumbing Pipings for three Toilet and Bath on ground floor
- New Set of Toilet Door, Double Hanging Towel Rod & Shower Sliding Glass including installation
- No Lavatory,Shower, Watercloset or any Plumbing Fixtures included

3.0 MASONRY WORKS (laying & plastering of CHB) Php 5,096.00


- Installation of CHB and plastering on walls to be closed

4.0 CARPENTRY WORKS (installation and fabrication of shelves ) Php 16,960.00


- Installation and Fabrication of shelves or cabinets on living area and bar
- Installation and Fabrication of shelves/ cabinets at Master's Toilet & Bath Only
- Installation and Fabrication of Customize or Concealed Door on Master's Bedroom

5.0 ELECTRICAL WORKS (wiring & installation of electrical fixtures @ Ground Floor Area) Php 14,020.00
- Wiring & Roughing-Ins Installations
- Installation of Light Fixtures & other Electrical Fixtures
- Wiring & Installations of Speakers

6.0 STONEWORKS & PAINTING WORKS (ground floor only) Php 44,700.60
- Installation of Stoneworks at designated areas (interior only )
- Painting Works for Affected Walls during construction
- Ceiling Area for Master's Toilet & Bath Only
- Painting for shelves or cabinets at living area,bar, Master's bedroom and Toilet & Bath

DIRECT COST Php 218,594.60

MATERIALS Php 218,594.60


Labor Php 131,156.76
Tools & Mobilization Php 13,115.68
Contractor's Profit Php 13,115.68

TOTAL PROJECT COST Php 375,982.71


TOTAL COST FOR LABOR ONLY Php 165,086.11
Tax 4,952.58
TOTAL PROJECT COST FOR LABOR ONLY Php 170,038.70
For the whole scope of works,our quotation shall be ONE HUNDRED SEVENTY THOUSAND THIRTY-EIGHT PESOS & 70/100.
Php 170,038.70

TERMS & CONDITIONS

1.Owner shall provide storage for all materials and tools as well as utility connections.
2.Work Duration: 45 Working Days starting 2 days after receipt of downpayment.
3.Terms of Payment:
a.Downpayment 35% (Php 59,513.54 )
b.Progress Billing
4.Works that are not included in the contract or not previously agreed upon shall be deemed additional
works and will be subject to additional payment.
5.Cost of repair for defective works due to the contractors fault shall be shouldered by the contractor.
6.This serves as formal agreement if conformed.

Prepared by:

Arch. Nennen Gultiane G. Nob,UAP


Associate Architect

Noted by:

Arch. Mae Butra-Paguia,PIA


Principal Architect

Approved by:

Owner/Representative
Project: PROPOSED HOUSE RENOVATION
Owner: #REF!
Address: Pueblo,Cagayan de Oro City
Date Estimate: November 04, 2015

Peace in Christ! In connection of the above-said subject, we would like to present to you our formal proposal for you to evaluate
and consider.

SCOPE OF WORKS

Item No. Description Item Total

1.0 SITE WORKS (clearing ) Php 7,698.00


- Site Clearing/Demolition of Wall on area to be close and door relocation
- Preparation of Area
- Scaffolds and Temporary Facilities
- Removal of Existing Tiles on Master's Toilet & Bath Only

2.0 TOILET WORKS (installation of new tiles,ceiling and piping repairs) Php 130,120.00
- Installation of New Tiles for Master's Toilet and Bath Only (floor-ceiling)
- New Ceiling for Master's Toilet and Bath Only
- Repair of Plumbing Pipings for three Toilet and Bath on ground floor
- New Set of Toilet Door, Double Hanging Towel Rod & Shower Sliding Glass including installation
- No Lavatory,Shower, Watercloset or any Plumbing Fixtures included

3.0 MASONRY WORKS (laying & plastering of CHB) Php 5,096.00


- Installation of CHB and plastering on walls to be closed

4.0 CARPENTRY WORKS (installation and fabrication of shelves ) Php 16,960.00


- Installation and Fabrication of shelves or cabinets on living area and bar
- Installation and Fabrication of shelves/ cabinets at Master's Toilet & Bath Only
- Installation and Fabrication of Customize or Concealed Door on Master's Bedroom

5.0 ELECTRICAL WORKS (wiring & installation of electrical fixtures @ Ground Floor Area) Php 14,020.00
- Wiring & Roughing-Ins Installations
- Installation of Light Fixtures & other Electrical Fixtures
- Wiring & Installations of Speakers

6.0 STONEWORKS & PAINTING WORKS (ground floor only) Php 44,700.60
- Installation of Stoneworks at designated areas (interior only )
- Painting Works for Affected Walls during construction
- Ceiling Area for Master's Toilet & Bath Only
- Painting for shelves or cabinets at living area,bar, Master's bedroom and Toilet & Bath

DIRECT COST Php 218,594.60

MATERIALS Php 218,594.60


Labor Php 131,156.76
Tools & Mobilization Php 13,115.68
Contractor's Profit Php 13,115.68

TOTAL PROJECT COST Php 375,982.71


Tax 11,279.48
TOTAL PROJECT COST Php 387,262.19
For the whole scope of works,our quotation shall be THREE HUNDRED EIGHTY-SEVEN THOUSAND TWO HUNDRED SIXTY-TWO PESOS
& 19/100.
Php 387,262.19

TERMS & CONDITIONS

1.Owner shall provide storage for all materials and tools as well as utility connections.
2.Work Duration: 45 Working Days starting 2 days after receipt of downpayment.
3.Terms of Payment:
a.Downpayment 35%(Php 135,541.76)
b.Progress Billing
4.Works that are not included in the contract or not previously agreed upon shall be deemed additional
works and will be subject to additional payment.
5.Cost of repair for defective works due to the contractors fault shall be shouldered by the contractor.
6.This serves as formal agreement if conformed.

Prepared by:
-
Arch. Nennen Gultiane G. Nob,UAP
Associate Architect

Noted by:

Arch. Mae Butra-Paguia,PIA


Principal Architect

Approved by:

Owner/Representative
Project: PROPOSED HOUSE RENOVATION
Owner: Mr. Milben and Mrs. Sheryl Asombrado
Address: Pueblo,Cagayan de Oro City
Date Estimate: November 04, 2015

Item No. Description Quantity Unit Unit Price Item Total

1.0 SITE WORKS (clearing )

Site Clearing/Demolition of Wall 23.38 Sq.m 100.00 2,338.00


Scaffolds/ Temporary Facilities 1 Lot 5000.00 5,000.00
3" CW Nails 3 Kg 120.00 360.00
Subtotal 7,698.00

2.0 TOILET WORKS (installation of new tiles,ceiling and piping repairs)


2.a New Tiles for Master's Bedroom
0.60x0.60 Non-skid Floor Tiles (master's t&b) 22 Pcs 300.00 6,600.00
0.20x0.60 Wall Tiles 230 Pcs 200.00 46,000.00
Tile Adhesive 20 Bags 245.00 4,900.00
Portland Cement 20 Bags 245.00 4,900.00
Tile Grout 13 Bags 95.00 1,235.00
Stainless Double Towel Hanging Rod 1 Set 3200.00 3,200.00
Installation of Sliding Glass for Shower 1 Set 26000.00 26,000.00
Solid Toilet Door with Jamb 1 Set 11000.00 11,000.00
Granite Countertop 1 Set 7000.00 7,000.00
Hardware & Accessories 1 Lot 1000.00 1,000.00

2.b Ceiling Repair for Master's Toilet and Bath


3.5mm thk Hardiflex 3 Shts 400.00 1,200.00
Furring Channel 3 Lengths 135.00 405.00
Carrying Channel 3 Lengths 135.00 405.00
Wall Angle 5 Lengths 55.00 275.00
Hardware & Accessories 1 Lot 1000.00 1,000.00

2.c Repair of Piping for 3 toilet and bath at Ground 1 Lot 15000.00 15,000.00
Subtotal 130,120.00

3.0 MASONRY WORKS (laying & plastering of CHB)

4" thk CHB 68 Pcs 9.50 646.00


10mm Deformed Bar 7 Length 165.00 1,155.00

Mortar for Block Laying


Portland Cement 7 Bags 245.00 1,715.00
Fine Sand 1 Cu. M. 600.00 300.00
###
Plastering
Portland Cement 4 Bags 245.00 980.00
Fine Sand 1 Cu. M. 600.00 300.00
Subtotal 5,096.00

4.0 CARPENTRY WORKS (installation and fabrication of shelves )

18mm thk Marine Plywood 8 Pcs 1200.00 9,600.00


Customize Hidden Door on Wall with Accessories 1 Set 4000.00 4,000.00
2" Finishing Nails 3 Kg 90.00 270.00
Roller Guide 2 Sets 180.00 360.00
Cabinet Handle 2 Sets 180.00 360.00
2" Finishing Nails 3 Kg 90.00 270.00
Plastic Laminate 1 Sht 1100.00 1,100.00
Hardware & Accessories 1 Lot 1000.00 1,000.00
Subtotal 16,960.00

5.0 ELECTRICAL WORKS (wiring & installation of electrical fixtures @ Ground Floor Area) ###
###
Fixtures
Cylindrical Pinlight Assembly 6" 5 Sets 350.00 1,750.00
Flourescent Lamp Assembly 5 Sets 300.00 1,500.00
Installation & Wiring for Speakers 1 Lot 3500.00 3,500.00
###
Roughing-ins
Convenience Outlet Assembly 3 Pcs 400.00 1,200.00
Assorted Switch Assembly 3 sets 400.00 1,200.00
Junction Box no. 4"x4"x3/4" PVC 2 Pcs 30.00 60.00
Utility Box no. 2"x4"x1/2" PVC 3 Pcs 30.00 90.00
THHN no. 2.0mm 1 Box 2800.00 1,400.00
THHN no. 3.5mm 1 Box 3800.00 1,900.00
THHN no. 8.0mm 4 Meters 75.00 300.00
PVC Pipe no. 20mm 3 Length 90.00 270.00
PVC Connector no. 20mm 5 Pcs 15.00 75.00
PVC Elbow no. 20mm 5 Pcs 45.00 225.00
PVC Flexible Pipe no. 1/2" 1 Rolls 800.00 400.00
Electrical Tape 5 Pcs 30.00 150.00
Subtotal 14,020.00

6.0 STONEWORKS & PAINTING WORKS (ground floor only)

Stoneworks
Natural Stone Wall Cladding (exterior & Interior) 5.17 Sq.m 2,000.00 10,340.00
Portland Cement 6 Bags 245.00 1,470.00
Tile Adhesive Paste 6 Bags 245.00 1,470.00

Boysen Paints
Ceiling Area (t&b at Master's Bedroom) 6 Sq.m 120.00 720.00
Wall Painting for Affected Areas 38.68 Sq.m 120.00 4,641.60
Cabinet/Shelves 1 Lot 10,000.00 10,000.00

Body Filler 4 Gal 540.00 2,160.00


Acrytex Primer 4 Gal 800.00 3,200.00
Acrytex Cast 4 Gal 480.00 1,920.00
Lacquer putty 3 Gal 480.00 1,440.00
Quick Dry Enamel 3 Gal 790.00 2,370.00
Lacquer Thinner 3 Gal 650.00 1,950.00
Paint Thinner 3 Gal 450.00 1,350.00
Waste Cotton 4 Kls 70.00 280.00
MaskingTape 8 Pcs 45.00 360.00
#120 Sand Paper 8 Pcs 18.00 144.00
#80 Sand Paper 3 Sq. Ft. 80.00 240.00
Roller Brush with Paint Tray 3 Pcs 150.00 450.00
2" Paint Brush 3 Pcs 65.00 195.00
Subtotal 44,700.60

TOTAL MATERIALS

SUMMARY OF EXPENSES

SITE WORKS (clearing ) 7,698.00


TOILET WORKS (installation of new tiles,ceiling and piping repairs) 130,120.00
MASONRY WORKS (laying & plastering of CHB) 5,096.00
CARPENTRY WORKS (installation and fabrication of shelves ) 16,960.00
ELECTRICAL WORKS (wiring & installation of electrical fixtures @ Ground Floor Area) 14,020.00
STONEWORKS & PAINTING WORKS (ground floor only) 44,700.60
TOTAL MATERIALS 218,594.60

DIRECT COST ###


###
MATERIALS 218,594.60
Labor 131,156.76
Tools & Mobilization 13,115.68
Constructor's Profit 13,115.68

TOTAL PROJECT COST 375,982.71


Withholding Tax 3% 11,279.48

TOTAL FINAL PROJECT COST 387,262.19

Prepared by:

Arch. Nennen Gultiane G. Nob


Associate Architect

Noted by:

Arch. Mae Butra-Paguia


Principal Architect ###

Approved by:
Owner
#REF!
#REF! #REF!
#REF!
#REF!

Peace in Christ! In connection of the above-said subject, we would like to present to you our formal proposal
for you to evaluate and consider.

SCOPE OF WORKS

Item No. Description Item Total

#REF! #REF! Php #REF!


- Site Clearing/Demolition of Wall on area to be close and door relocation
- Preparation of Area
- Scaffolds and Temporary Facilities
- Removal of Existing Tiles on Master's Toilet & Bath Only

#REF! #REF! Php #REF!


- Installation of New Tiles for Master's Toilet and Bath Only
- New Ceiling for Master's Toilet and Bath Only
- Repair of Plumbing Pipings
- New Set of Toilet Door, Double Hanging Towel Rod & Shower Sliding Glass including installation
- No Lavatory,Shower, Watercloset or any Plumbing Fixtures included

#REF! #REF! Php #REF!


- Installation of CHB and plastering on walls to be closed

#REF! #REF! Php #REF!


- Installation and Fabrication of shelves or cabinets on living area and bar

#REF! #REF! Php #REF!


- Wiring & Roughing-Ins Installations
- Installation of Light Fixtures & other Electrical Fixtures
- Wiring & Installations of Speakers

#REF! #REF! Php #REF!


- Installation of Stoneworks at designated areas (interior and exterior )
- Painting Works for Affected Walls during construction
- Ceiling Area for Master's Toilet & Bath Only
- Painting for shelves or cabinets at living area

DIRECT COST Php #REF!

MATERIALS Php #REF!


Labor Php #REF!
Tools & Mobilization Php #REF!
Contractor's Profit Php #REF!

TOTAL PROJECT COST Php #REF!


TOTAL COST FOR LABOR ONLY Php #REF!
Tax #REF!
TOTAL PROJECT COST FOR LABOR ONLY Php #REF!
For the whole scope of works,our quotation shall be ONE HUNDRED SEVENTY-FIVE THOUSAND SEVEN HUNDRED THREE PESOS & 18/100.

Php #REF!

TERMS & CONDITIONS

1.Owner shall provide storage for all materials and tools as well as utility connections.
2.Work Duration: 45 Working Days starting 2 days after receipt of downpayment.
3.Terms of Payment:
a.Downpayment 35% (Php 61,496.11 )
b.Progress Billing
4.Works that are not included in the contract or not previously agreed upon shall be deemed additional
works and will be subject to additional payment.
5.Cost of repair for defective works due to the contractors fault shall be shouldered by the contractor.
6.This serves as formal agreement if conformed.

Prepared by:
-
Arch. Nennen Gultiane G. Nob,UAP
Associate Architect

Noted by:

Arch. Mae Butra-Paguia,PIA


Principal Architect

Approved by:

Owner/Representative
#REF!
#REF! #REF!
#REF!
#REF!

Peace in Christ! In connection of the above-said subject, we would like to present to you our formal proposal
for you to evaluate and consider.

SCOPE OF WORKS

Item No. Description Item Total

#REF! #REF! Php #REF!


- Site Clearing/Demolition of Wall on area to be close and door relocation
- Preparation of Area
- Scaffolds and Temporary Facilities
- Removal of Existing Tiles on Master's Toilet & Bath Only

#REF! #REF! Php #REF!


- Installation of New Tiles for Master's Toilet and Bath Only
- New Ceiling for Master's Toilet and Bath Only
- Repair of Plumbing Pipings
- New Set of Toilet Door, Double Hanging Towel Rod & Shower Sliding Glass including installation
- No Lavatory,Shower, Watercloset or any Plumbing Fixtures included

#REF! #REF! Php #REF!


- Installation of CHB and plastering on walls to be closed

#REF! #REF! Php #REF!


- Installation and Fabrication of shelves or cabinets on living area and bar

#REF! #REF! Php #REF!


- Wiring & Roughing-Ins Installations
- Installation of Light Fixtures & other Electrical Fixtures
- Wiring & Installations of Speakers

#REF! #REF! Php #REF!


- Installation of Stoneworks at designated areas (interior and exterior )
- Painting Works for Affected Walls during construction
- Ceiling Area for Master's Toilet & Bath Only
- Painting for shelves or cabinets at living area

DIRECT COST Php #REF!

MATERIALS Php #REF!


Labor Php #REF!
Tools & Mobilization Php #REF!
Contractor's Profit Php #REF!

TOTAL PROJECT COST Php #REF!


Tax #REF!
TOTAL PROJECT COST Php #REF!
For the whole scope of works,our quotation shall be FOUR HUNDRED THOUSAND SEVEN HUNDRED NINETY-FOUR PESOS & 3/100.

Php #REF!

TERMS & CONDITIONS

1.Owner shall provide storage for all materials and tools as well as utility connections.
2.Work Duration: 45 Working Days starting 2 days after receipt of downpayment.
3.Terms of Payment:
a.Downpayment 35%(Php 140,277.91)
b.Progress Billing
4.Works that are not included in the contract or not previously agreed upon shall be deemed additional
works and will be subject to additional payment.
5.Cost of repair for defective works due to the contractors fault shall be shouldered by the contractor.
6.This serves as formal agreement if conformed.

Prepared by:
-
Arch. Nennen Gultiane G. Nob,UAP
Associate Architect

Noted by:

Arch. Mae Butra-Paguia,PIA


Principal Architect

Approved by:

Owner/Representative
PRODUCTIVITY WORKS FOR ALL PROJECT WORKS

CARPENTRY WORKS

Item no. FORMWORK CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
FW
FW01 Formwork to Footings 2 Carpenters, 1 Helper 1.20 9.6
FW02 Formwork to Isolated Footings 2 Carpenters, 1 Helper 1.60 12.8
FW03 Formwork to Rafts 2 Carpenters, 1 Helper 1.40 11.2
FW04 Formwork to Tie Beams 2 Carpenters, 1 Helper 1.00 8
FW06 Formwork to Underground Water Tank 2 Carpenters, 1 Helper 4.8
FW07 Formwork to Basement Retaining Walls 2 Carpenters, 1 Helper 7.2
FW08 Formwork to Columns (small size) 2 Carpenters, 1 Helper 5.6
FW09 Formwork to Columns (large size) 2 Carpenters, 1 Helper 7.2
FW10 Formwork to D/S Beam internal (shallow) 2 Carpenters, 1 Helper 4.8
FW11 Formwork to D/S Beam internal (deep) 2 Carpenters, 1 Helper 5.6
FW12 Formwork to D/S Beam external (shallow) 2 Carpenters, 1 Helper 3.2
FW13 Formwork to D/S Beam external (deep) 2 Carpenters, 1 Helper 4.8
FW14 Formwork to Slab Decking (10ft) 2 Carpenters, 1 Helper 1.60 12.8
FW15 Formwork to Slab Decking (>10ft) D/S Beams 2 Carpenters, 1 Helper 1.20 9.6
FW16 Formwork to Staircase (non-spiral) 2 Carpenters, 1 Helper 3.2
FW17 Formwork to Balcony Parapets 2 Carpenters, 1 Helper 4.8
FW18 Formwork to Roof Parapets 2 Carpenters, 1 Helper 6.4

FW19 Shutter manufacture for Pile Caps 1 Carpenter, 1 Helper 2.00 16


FW20 Shutter fix for Pile Caps 1 Carpenter, 1 Helper 1.50 12
FW21 Deshutter Footings/Pile Caps 1 Helper 6.00 48
FW22 Shutter make Column Necks 1 Carpenter, 1 Helper 1.50 12
FW23 Shutter fix Column Necks 1 Carpenter, 1 Helper 1.20 9.6
FW24 Deshutter Column Necks 1 Helper 4.80 38.4
FW25 Shutter make Tie Beams 1 Carpenter, 1 Helper 1.20 9.6
FW26 Shutter fix Tie Beams 1 Carpenter, 1 Helper 1.00 8
FW27 Column Shutter making 1 Carpenter, 1 Helper 1.20 9.6
FW28 Column Shutter fixing 1 Carpenter, 1 Helper 1.00 8
FW29 Column deshuttering 1 Helper 4.00 32
FW30 Walls Shutter making 1 Carpenter, 1 Helper 1.50 12
FW31 Walls Shutter fixing 1 Carpenter, 1 Helper 0.80 6.4
FW32 De shutter Tie Beam shutter 1 Helper 4.00 32
FW33 Wall formwork deshuttering 1 Helper 3.20 25.6
FW34 Staircase formwork making 1 Carpenter, 1 Helper 0.80 6.4
FW35 Staircase formwork fixing 1 Carpenter, 1 Helper 0.80 6.4
FW36 Staircase formwork deshuttering 1 Helper 1.60 12.8
FW37 Drop beams formwork making 1 Carpenter, 1 Helper 1.00 8
FW38 Drop beams formwork fixing 1 Carpenter, 1 Helper 0.80 6.4
FW39 Drop beams formwork stripping 1 Helper 3.20 25.6
FW40 Suspended Slab formwork fixing 1 Carpenter, 1 Helper 1.20 9.6
FW41 Suspended Slab formwork deshutter 1 Helper 5.00 40
FW42 Formwork fixing for Sunshades 1 Carpenter, 1 Helper 0.70 5.6
FW43 Parapet formwork making 1 Carpenter, 1 Helper 1.20 9.6
FW44 Parapet formwork fixing 1 Carpenter, 1 Helper 1.00 8
FW45 Parapet formwork stripping 1 Helper 4.00 32
FW46 Fixing of Lintel formwork 1 Carpenter, 1 Helper 0.50 4
FW47 Deshutter of Lintel formwork 1 Helper 2.00 16
FW48 Deck formwork fixing 1 Carpenter, 1 Helper 1.50 12
FW49 Deck formwork deshuttering 1 Helper 6.00 48
FW50 Pipe Scaffolding erection for Slab 1 Scaffolder 0.85 6.8
FW51 Inverted Beam shutter fixing 1 Carpenter, 1 Helper 1.00 8
FW52 Deshuttering Manholes - square or circle (timber) 1 Carpenter, 1 Helper 4.00 32
FW53 Manhole Shutter erection - square or circle (timber) 1 Carpenter, 1 Helper 1.50 12
FW54 Metal Shutter for Manholes 1 Carpenter, 1 Helper 1.00 8
FW55 Metal Shutter for Precast Beams 2 Carpenters, 2 Helpers 3.00 24
FW56 Metal Shutter for Pile Caps 2 Carpenters, 2 Helpers 3.00 24
FW57 Metal Shutter for Pile Cap Beams 2 Carpenters, 2 Helpers 3.00 24

MASONRY WORKS

Item no. MASONRY WORKS CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MBW
MBW 01 Hollowblock works (100, 150 & 200 mm) 1 Mason, 1 Helper 12.00 120
MBW 02 Hollowblock works (large panels) 1 Mason, 1 Helper 14.00 140
MBW 03 Solid Blockwork 1 Mason, 1 Helper 9.50 95
MBW 04 Solid Blockwork as Raft forms 1 Mason, 1 Helper 11.00 110

PLASTERWORKS

Item no. PLASTERWORKS CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MPL
MPL 01 Plaster (internal), walls final coat 1 Mason, 1 Helper 1.60 16
MPL 02 Plaster (internal), walls rush coat 2 Helpers 1.40 14
MPL 03 Plaster (internal), walls mesh 1 Helper 1.80 18
MPL 04 Plaster (internal), walls hacking 1 Helper 1.00 10
MPL 05 Plaster (internal), walls guide point 1 Mason, 1 Helper 1.20 12
MPL 06 Plaster (internal), walls corner beads 1 Mason, 1 Helper 10.00 100
MPL 07 Plaster (external), walls with grooves 1 Mason, 1 Helper 10.00 100
MPL 08 Plaster (external), walls without grooves 1 Mason, 1 Helper 1.20 12
MPL 09 Plaster (external), walls rush coat 2 Helpers 15.00 150
MPL 10 Plaster (external), walls mesh 1 Helper 10.00 100
MPL 11 Plaster (external), walls hacking 1 Helper 10.00 100
MPL 12 Plaster (external), walls guide points 1 Mason, 1 Helper 10.00 100
MPL 13 Plaster (external), walls corner beads 1 Mason, 1 Helper 10.00 100
MPL 14 Plastering of Arches/Mullions 1 Mason, 1 Helper 0.80 8
MPL 15 Floor Screed 25mm thk 1 Mason, 1 Helper 0.60 6
MPL 16 Floor Screed 50mm thk 1 Mason, 1 Helper 2.00 20
MPL 17 Roof Screed 100mm thk 1 Mason, 1 Helper 1.50 15
MPL 18 Mosaic Floor Tiles fixing 1 Mason, 1 Helper 1.60 16

CERAMIC WORKS

Item no. CERAMIC WORKS CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MCR
MCR01 Ceramic tiles to walls by mortar 1 Mason, 1 Helper 1.20 12
MCR02 Ceramic tiles to walls, mortar to corridors 1 Mason, 1 Helper 1.00 10
MCR03 Ceramic tiles to walls, cut pieces 1 Mason 2.00 20
MCR04 Ceramic tiles to walls grouting 1 Helper 5.00 50
MCR05 Ceramic tiles to walls by glue 1 Mason, 1 Helper 1.20 12
MCR06 Ceramic tiles to walls, corridors, by glue 1 Mason, 1 Helper 1.30 13
MCR07 Ceramic tiles to walls, by glue, cut pieces 1 Mason 2.00 20
MCR08 Ceramic tiles to walls, by glue, grouting 1 Helper 5.00 50
MCR09 Ceramic tiles to floors 1 Mason, 1 Helper 1.00 10
MCR10 Ceramic tiles to floors in halls 1 Mason, 1 Helper 1.20 12
MCR11 Ceramic tiles to floors, cut pieces 1 Mason 2.00 20
MCR12 Ceramic tiles to floors, grouting 1 Helper 5.00 50
MCR13 Ceramic skirting by glue 1 Mason, 1 Helper 2.50 25
MCR14 Ceramic skirting by glue to halls, corridors 1 Mason, 1 Helper 3.00 30
MCR15 Marble flooring 1 Mason, 1 Helper 0.60 6

TILING WORKS

Item no. TILING WORKS CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MTW
MTW01 Mosaic / Terrazzo tiles to roofs 1 Mason, 1 Helper 1.60 16
MTW02 Mosaic / Terrazzo tiles to floors 1 Mason, 1 Helper 1.40 14
MTW03 Mosaic skirting to halls 1 Mason, 1 Helper 2.50 25
MTW04 Mosaic skirting flush / recessed 1 Mason, 1 Helper 1.40 14
MTW05 Grouting / Sealing to roof / floor tiles 1 Helper 2.50 25

BLOCK PAVING WORKS

Item no. PAVING WORKS CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MKP
MKP01 PCC Curve kerb base (to curves) 1 Mason, 1 Helper 2.50 25
MKP02 PCC to kerb base (straight line) 1 Mason, 1 Helper 3.00 30
MKP03 Haunching to kerb base (dumpes) 1 Mason, 1 Helper 4.00 40
MKP04 Kerbstone (without PCC) 1 Mason, 1 Helper 1.50 15
MKP05 Interlock paving on pre prepared sub-base 1 Mason, 1 Helper 2
MKP06 Screed works including preparation 1 Mason, 1 Helper 1.50 15
MKP07 Haunching of kerb base (Mixing truck) 1 Mason, 1 Helper 10.00 100

MANHOLE / DRAINAGE CONSTRUCTION

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
DRW
DRW01 Excavation for drains / manholes 1 Helper 5
DRW02 Backfill to drains / manholes 1 Helper 10
DRW03 Blockwork to manholes 1 Mason, 1 Helper 2
DRW04 Plaster to manholes 1 Mason, 1 Helper 2
DRW05 Benching to manholes 1 Mason, 1 Helper 4
DRW06 Fix covers to manholes 1 Mason, 1 Helper 2
DRW07 Fix gully traps 1 Mason, 1 Helper 1
DRW08 Laying of PVC sleeves 4"-12" 4 Helpers 24.00 240

MISCELLANEOUS LABOUR WORKS

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MLW
MLW01 Bitumen paint to concrete blockwork surfaces 1 Helper 4.00 40
MLW02 Bitumen painting bases / piles 1 Helper 7.00 70
MLW03 Hacking of concrete surfaces 1 Helper 5.00 50
MLW04 Fixing of flexcell sheets 1 Helper 6
MLW05 Pile cutting/dressing 1 Helper 1
MLW06 Pile cutting/dressing (smal diameter) 1 Helper 2
MLW07 Vertical sealant (12 mm) 1 Helper 2.50 25
MLW08 Horizontal sealant (12 mm) 1 Helper 5.00 50
MLW09 Roof preparation for lw concrete 1 Mason, 1 Helper 5.00 50
MLW10 Angle fillet fixing 1 Mason, 1 Helper 4.00 40
MLW11 Hourdi block shifting and fixing to slab 2 Helpers 20.00 200
MLW12 Polythene sheet fixing 1 Helper 3.00
MLW13 Shaping of soil blinding 1 Mason, 1 Helper 1.00 10
MLW14 Protection board installation 1 Carpenter, 1 Helper 8.00 80

MISCELLANEOUS CARPENTRY WORKS

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MCW
MCW01 A/C subframe manufacture / fixing 1 Carpenter 5 NOS
MCW02 Door subframe manufacture / fixing 1 Carpenter 4 NOS
MCW03 Water bar fixing 1 Carpenter 2.0 20

CONCRETE PLACEMENT WORKS

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
CPW
CPW01 Concrete to pile caps by pump 6 Masons, 18 Helpers, 1 Carpenter 180
Standard rate 1 man 1 10
CPW02 Concrete to PCC blinding (100mm thk) 1 Mason, 10 Helpers 27
CPW03 Concrete to slabs / beams, by pump 6 Masons, 18 Helpers, 1 Carpenter 180
CPW04 Concrete to slabs / beams, by crane 1 Mason, 6 Helpers, 0.5 Operator 8.10 81
CPW05 Concrete to walls / columns, by pump 4 Masons, 16 Helpers, 2 Carpenters 1.20 12
CPW06 Concrete by site mix 1 Masons, 12 Helpers, 0.5 Carpenter 1.60 16
CPW07 Concrete columns 8 Helpers 1.40 14
CPW08 Concrete suspended slab (pump) 3 Masons, 6 Helpers 1.80 18
CPW09 Concrete parapets / staircases 8 Helpers 1.00 10
CPW10 Blinding concrete 50mm (ready mix) 1 Mason, 4 Helpers 8.00 80
CPW11 Blinding concrete 50mm (site mix) 1 Mason, 8 Helpers 1.00 10
CPW12 Concrete footings and pile caps 1 Mason, 4 Helpers 12.00 120
CPW13 Concrete tie beams, ground beams 1 Mason, 5 Helpers 6.00 60
CPW14 Concrete column necks 8 Helpers 1.50 15
CPW15 Concrete ground slab 3 Masons, 6 Helpers 1.50 15
CPW16 Concrete to precast slabs, beams 2 Masons, 1 Helper 3.00 30

GENERAL LABOUR WORKS

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
GLW
GLW01 Unloading reinforcement (flat bed truck) 4 Helpers 2 Nos
GLW02 Loading reinforcement to slab (with crane) 4 Helpers 2 Nos
GLW03 Loading blockwork to site (with wheel burrow) 1 Helper 400 Nos
GLW04 Loading mortar to site location
GLW05 Mixing mortar for distribution 0.3 L mixer 4 Helpers 6
GLW06 Site mixing of ready mix for distribution hand mix 3
GLW07 Loading ready mix to site location

NON TARGET RELATED ACTIVITIES

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
NTRA
NTRA01 Stacking of formwork 2 Helpers
NTRA02 Curing of substructure works 2 Helpers
NTRA03 Curing of beams / slabs Hessiant water 2 Helpers
NTRA04 Curing of columns (Hessiant water) 1 Mason, 2 Helpers 1.6 16
NTRA05 Builders work make good chases 1.2 12
NTRA06 Site cleaning 1 Helper 25 250
NTRA07 Repairs to finished works 1
NTRA08 Maintenance of site services 2 Helpers Non-Measurable
NTRA09 Operators for mixers 2 Mixers Non-Measurable
NTRA10 Operators for compaction equipment 1 Unit Non-Measurable
NTRA11 Office boy Arabtec 1, Consultant 1 Non-Measurable
NTRA12 Watchman 2 Min Non-Measurable
NTRA13 Storekeeper 1 Shift Non-Measurable

REINFORCEMENT

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
RF
RF01 Fix rebars to footings and tie beams 1 Steel Fixer 25.0 250
RF02 Fix rebars to walls, columns, beams, solid slabs 1 Steel Fixer 20.0 200
RF03 Fix rebars to ribs of hourdi slab 1 Steel Fixer 18.0 180
RF04 Fix rebars to mesh reinforcement 1 Steel Fixer 15.0 150
RF05 Fix rebars to hidden beams 1 Steel Fixer 20.0 200

RF01 Fix rebars to footings and tie beams 1 Steel Fixer 78.0 780
RF02 Fix rebars to walls, columns, beams, solid slabs 1 Steel Fixer 38.0 380
RF03 Fix rebars to ribs of hourdi slab 1 Steel Fixer 35.0 350
RF04 Fix rebars to mesh reinforcement 1 Steel Fixer 15.0 150
RF05 Fix rebars to hidden beams 1 Steel Fixer 420

RFC01 Steel cutting and bending 18.25mm 1 Steel Fixer 50 500


RFC02 Steel cutting and bending 8-16 mm 1 Steel Fixer 40 400

EXCAVATION

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
EX
EX01 Manual Excavation 1 Helper 3
EX02 Backfill and leveling 1 Helper 5
EX03 Shaping of sloped earth for blinding for bases including compaction 1 Mason, 2 Helpers 6
PRODUCTIVITY WORKS FOR ALL PROJECT WORKS

EXCAVATION

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
EX
EX01 Manual Excavation 1 Helper 3
EX02 Backfill and leveling 1 Helper 5
EX03 Shaping of sloped earth for blinding for bases including compaction 1 Mason, 2 Helpers 6

CARPENTRY WORKS

Item no. FORMWORK CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
FW
FW01 Formwork to Footings 2 Carpenters, 1 Helper 1.2 10
FW02 Formwork to Isolated Footings 2 Carpenters, 1 Helper 1.6 13
FW03 Formwork to Rafts 2 Carpenters, 1 Helper 1.4 11
FW04 Formwork to Tie Beams 2 Carpenters, 1 Helper 1.0 8
FW06 Formwork to Underground Water Tank 2 Carpenters, 1 Helper 5
FW07 Formwork to Basement Retaining Walls 2 Carpenters, 1 Helper 7
FW08 Formwork to Columns (small size) 2 Carpenters, 1 Helper 6
FW09 Formwork to Columns (large size) 2 Carpenters, 1 Helper 7
FW10 Formwork to D/S Beam internal (shallow) 2 Carpenters, 1 Helper 5
FW11 Formwork to D/S Beam internal (deep) 2 Carpenters, 1 Helper 6
FW12 Formwork to D/S Beam external (shallow) 2 Carpenters, 1 Helper 3
FW13 Formwork to D/S Beam external (deep) 2 Carpenters, 1 Helper 5
FW14 Formwork to Slab Decking (10ft) 2 Carpenters, 1 Helper 1.6 13
FW15 Formwork to Slab Decking (>10ft) D/S Beams 2 Carpenters, 1 Helper 1.2 10
FW16 Formwork to Staircase (non-spiral) 2 Carpenters, 1 Helper 3
FW17 Formwork to Balcony Parapets 2 Carpenters, 1 Helper 5
FW18 Formwork to Roof Parapets 2 Carpenters, 1 Helper 6

FW19 Staircase formwork making 1 Carpenter, 1 Helper 0.8 6


FW20 Staircase formwork fixing 1 Carpenter, 1 Helper 0.8 6
FW21 Drop beams formwork making 1 Carpenter, 1 Helper 1.0 8
FW22 Drop beams formwork fixing 1 Carpenter, 1 Helper 0.8 6
FW23 Drop beams formwork stripping 1 Helper 3.2 26
FW24 Suspended Slab formwork fixing 1 Carpenter, 1 Helper 1.2 10
FW25 Formwork fixing for Sunshades 1 Carpenter, 1 Helper 0.7 6
FW26 Parapet formwork making 1 Carpenter, 1 Helper 1.2 10
FW27 Parapet formwork fixing 1 Carpenter, 1 Helper 1.0 8
FW28 Parapet formwork stripping 1 Helper 4.0 32
FW29 Fixing of Lintel formwork 1 Carpenter, 1 Helper 0.5 4
FW30 Deck formwork fixing 1 Carpenter, 1 Helper 1.5 12
FW31 Pipe Scaffolding erection for Slab 1 Scaffolder 0.9 7
FW32 Metal Shutter for Manholes 1 Carpenter, 1 Helper 1.0 8
FW33 Metal Shutter for Precast Beams 2 Carpenters, 2 Helpers 3.0 24
FW34 Metal Shutter for Pile Caps 2 Carpenters, 2 Helpers 3.0 24
FW35 Metal Shutter for Pile Cap Beams 2 Carpenters, 2 Helpers 3.0 24

FW36 A/C subframe manufacture / fixing 1 Carpenter 5


FW37 Door subframe manufacture / fixing 1 Carpenter 4
FW38 Water bar fixing 1 Carpenter 2.0 20

REINFORCEMENT

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
RF
RF01 Fix rebars to footings and tie beams 1 Steel Fixer 25.0 200
RF02 Fix rebars to walls, columns, beams, solid slabs 1 Steel Fixer 20.0 160
RF03 Fix rebars to ribs of hourdi slab 1 Steel Fixer 18.0 140
RF04 Fix rebars to mesh reinforcement 1 Steel Fixer 15.0 120
RF05 Fix rebars to hidden beams 1 Steel Fixer 20.0 160
RFC01 Steel cutting and bending 18.25mm 1 Steel Fixer 50 400
RFC02 Steel cutting and bending 8-16 mm 1 Steel Fixer 40 320

CONCRETE PLACEMENT WORKS

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
CPW
CPW01 Concrete to pile caps by pump 6 Masons, 18 Helpers, 1 Carpenter 18.0 140
CPW02 Concrete to PCC blinding (100mm thk) 1 Mason, 10 Helpers 3 22
CPW03 Concrete to slabs / beams, by pump 6 Masons, 18 Helpers, 1 Carpenter 18 140
CPW04 Concrete to slabs / beams, by crane 1 Mason, 6 Helpers, 0.5 Operator 8.10 65
CPW05 Concrete to walls / columns, by pump 4 Masons, 16 Helpers, 2 Carpenters 1.20 10
CPW06 Concrete by site mix 1 Masons, 12 Helpers, 0.5 Carpenter 1.60 13
CPW07 Concrete columns 8 Helpers 1.40 11
CPW08 Concrete suspended slab (pump) 3 Masons, 6 Helpers 1.80 14
CPW09 Concrete parapets / staircases 8 Helpers 1.00 8
CPW10 Blinding concrete 50mm (ready mix) 1 Mason, 4 Helpers 8.00 64
CPW11 Blinding concrete 50mm (site mix) 1 Mason, 8 Helpers 1.00 8
CPW12 Concrete footings and pile caps 1 Mason, 4 Helpers 12.00 96
CPW13 Concrete tie beams, ground beams 1 Mason, 5 Helpers 6.00 48
CPW14 Concrete column necks 8 Helpers 1.50 12
CPW15 Concrete ground slab 3 Masons, 6 Helpers 1.50 12
CPW16 Concrete to precast slabs, beams 2 Masons, 1 Helper 3.00 24

MASONRY WORKS

Item no. MASONRY WORKS CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MBW
MBW 01 Hollowblock works (100, 150 & 200 mm) 1 Mason, 1 Helper 12.0 96
MBW 02 Hollowblock works (large panels) 1 Mason, 1 Helper 14.0 112
MBW 03 Solid Blockwork 1 Mason, 1 Helper 9.5 76
MBW 04 Solid Blockwork as Raft forms 1 Mason, 1 Helper 11.0 88

PLASTERWORKS

Item no. PLASTERWORKS CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MPL
MPL 01 Plaster (internal), walls final coat 1 Mason, 1 Helper 1.6 13
MPL 02 Plaster (internal), walls rush coat 2 Helpers 1.4 11
MPL 03 Plaster (internal), walls mesh 1 Helper 1.8 14
MPL 04 Plaster (internal), walls hacking 1 Helper 1.0 8
MPL 05 Plaster (internal), walls guide point 1 Mason, 1 Helper 1.2 10
MPL 06 Plaster (internal), walls corner beads 1 Mason, 1 Helper 10.0 80
MPL 07 Plaster (external), walls with grooves 1 Mason, 1 Helper 10.0 80
MPL 08 Plaster (external), walls without grooves 1 Mason, 1 Helper 1.2 10
MPL 09 Plaster (external), walls rush coat 2 Helpers 15.0 120
MPL 10 Plaster (external), walls mesh 1 Helper 10.0 80
MPL 11 Plaster (external), walls hacking 1 Helper 10.0 80
MPL 12 Plaster (external), walls guide points 1 Mason, 1 Helper 10.0 80
MPL 13 Plaster (external), walls corner beads 1 Mason, 1 Helper 10.0 80
MPL 14 Plastering of Arches/Mullions 1 Mason, 1 Helper 0.8 6
MPL 15 Floor Screed 25mm thk 1 Mason, 1 Helper 0.6 5
MPL 16 Floor Screed 50mm thk 1 Mason, 1 Helper 2.0 16
MPL 17 Roof Screed 100mm thk 1 Mason, 1 Helper 1.5 12
MPL 18 Mosaic Floor Tiles fixing 1 Mason, 1 Helper 1.6 13

TILING WORKS

Item no. CERAMIC WORKS CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
TW
TW01 Ceramic tiles to walls by mortar 1 Mason, 1 Helper 1.2 10
TW04 Ceramic tiles to walls grouting 1 Helper 5.0 40
TW05 Ceramic tiles to walls by glue 1 Mason, 1 Helper 1.2 10
TW09 Ceramic tiles to floors 1 Mason, 1 Helper 1.0 8
TW10 Ceramic tiles to floors in halls 1 Mason, 1 Helper 1.2 10
TW12 Ceramic tiles to floors, grouting 1 Helper 5.0 40
TW13 Ceramic skirting by glue 1 Mason, 1 Helper 2.5 20
TW15 Marble flooring 1 Mason, 1 Helper 0.6 5
TW16 Mosaic / Terrazzo tiles to roofs 1 Mason, 1 Helper 1.6 13
TW17 Mosaic / Terrazzo tiles to floors 1 Mason, 1 Helper 1.4 11
TW18 Mosaic skirting to halls 1 Mason, 1 Helper 2.5 20
TW19 Mosaic skirting flush / recessed 1 Mason, 1 Helper 1.4 12
TW20 Grouting / Sealing to roof / floor tiles 1 Helper 2.5 20

BLOCK PAVING WORKS

Item no. PAVING WORKS CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
MKP
MKP01 PCC Curve kerb base (to curves) 1 Mason, 1 Helper 2.5 20
MKP02 PCC to kerb base (straight line) 1 Mason, 1 Helper 3.0 24
MKP04 Kerbstone (without PCC) 1 Mason, 1 Helper 1.5 12
MKP06 Screed works including preparation 1 Mason, 1 Helper 1.5 12
MKP03 Haunching to kerb base (dumpes) 1 Mason, 1 Helper 4.0 32
MKP07 Haunching of kerb base (Mixing truck) 1 Mason, 1 Helper 10.0 80

MANHOLE / DRAINAGE CONSTRUCTION

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
DRW
DRW01 Excavation for drains / manholes 1 Helper 5
DRW02 Backfill to drains / manholes 1 Helper 10
DRW03 Blockwork to manholes 1 Mason, 1 Helper 2
DRW04 Plaster to manholes 1 Mason, 1 Helper 2
DRW05 Benching to manholes 1 Mason, 1 Helper 4
DRW06 Fix covers to manholes 1 Mason, 1 Helper 2
DRW07 Fix gully traps 1 Mason, 1 Helper 1
DRW08 Laying of PVC sleeves 4"-12" 4 Helpers 24.0 240
LABOUR WORKS

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
LW
LW01 Unloading reinforcement (flat bed truck) 4 Helpers 2 (Nos)
LW02 Loading reinforcement to slab (with crane) 4 Helpers 2 (Nos)
LW03 Loading blockwork to site (with wheelbarrow) 1 Helper 400 (Nos)
LW04 Loading mortar to site location
LW05 Mixing mortar for distribution 0.3 L mixer 4 Helpers 6
LW06 Site mixing of ready mix for distribution hand mix 3
LW07 Loading ready mix to site location

LW08 Bitumen paint to concrete blockwork surfaces 1 Helper 4.0 32


LW09 Bitumen painting bases / piles 1 Helper 7.0 56
LW10 Hacking of concrete surfaces 1 Helper 5.0 40
LW11 Fixing of flexcell sheets 1 Helper 6
LW12 Pile cutting/dressing 1 Helper 2
LW13 Vertical sealant (12 mm) 1 Helper 2.5 20
LW14 Horizontal sealant (12 mm) 1 Helper 5.0 40
LW15 Roof preparation for lw concrete 1 Mason, 1 Helper 5.0 40
LW16 Angle fillet fixing 1 Mason, 1 Helper 4.0 32
LW17 Polythene sheet fixing 1 Helper 3.0 24
LW18 Shaping of soil binding 1 Mason, 1 Helper 1.0 8
LW19 Protection board installation 1 Carpenter, 1 Helper 8.0 64

NON TARGET RELATED ACTIVITIES

Item no. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)
NTRA
NTRA01 Stacking of formwork 2 Helpers
NTRA02 Curing of substructure works 2 Helpers
NTRA06 Site cleaning 1 Helper 25 200
NTRA07 Repairs to finished works 1 8
NTRA08 Maintenance of site services 2 Helpers Non-Measurable
NTRA09 Operators for mixers 2 Mixers Non-Measurable
NTRA10 Operators for compaction equipment 1 Unit Non-Measurable
NTRA11 Office boy Arabtec 1, Consultant 1 Non-Measurable
NTRA12 Watchman 2 Min Non-Measurable
NTRA13 Storekeeper 1 Shift Non-Measurable
PRODUCTIVITY WORKS FOR ALL PROJECT WORKS

INTERIOR WORK

No. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (SQ.M)

1 Apply 1 coat sealer to flat surface- ceilings & walls etc.


(a) brush and roll 0.09
(b) airless spray 0.05

2 Ceilings 1 x Sealer
2 x acrylic ceiling flat
(a) brush and roll 0.22
(b) airless spray 0.17

3 Walls and flat surfaces 0.24


1 x sealer/undercoat
2 x low sheen acrylic

*Includes sanding, small defect fillings etc. white/colours.


Colours below 40% LRV add 10%

4 Timber Surfaces 0.31


1 x AP under coat
2 x topcoats gloss/semi-gloss
(including stopping etc)

5 Prime, undercoat and full gloss enamel (2) coats


Flat surfaces wallboards 0.33
Timber flat surfaces (stopping) 0.40
Timber 0-150 0.11
Timber 150-300 0.12

6 Seal, stop and 2 coats clear varnish


Satin- gloss 0.26
0-150 0.10
150-300 0.12

7 Resene colorwood timber stain only


0-150 0.08
150-300 0.02
(stopping and clear over extra) 0.04

8 Particle board flooring


Stopping fixing (overall) 0.02
Seal PBS and 3 coats
Moisture cure and polyurethane 0.36

9 Tounge and groove timber flooring


Stopping fixing (overall) 0.10
3 coats moisture cure and polyurethane 0.29

10 Window liners 100mm 0.06


Prime/clear and 2 coats

11 Timber windows interior


Prime/clear and 2 coats
Measure flat over glass 1.10

12 2 colour broken ground sponging over basecoat 0.45


13 Metallic finish on flat 1.40
Metallic finish on texture (includes basecoats) 1.10
Overglaze to metallics 0.14

14 Apply by airless surface prep (Resene Broadwall 3 in 1)


Skim coats to plasterboard
From level 4 to level 5 0.18

15 Supply, size and hand butt jointed lining paper to plasterboards 0.40

16 Supply, size and hand selected wallpaper 0.75

17 Supply, size paste the wall and hang selected paper 0.40

18 Size only, plasterboard walls- 'Shurstik' or 'Metalyn' latex size 0.06

19 Seal old stained or yellowed paperfaced plasterboard with 0.11


pigmented sealer

20 Supply and fix Nylex/Autex Foam backed pinboard fabric

21 Stripping wallpaper
(a)standard 0.14
(b)vinyl 0.16
(c)embossed 0.18
*indicative rate only - try for labour hourly rate

22 Supply, size paste the wall and hand selected paper 0.40

23 Supply, size paste the wall and hand 'Kontur' 1.000 wide textured 0.28
lining
Apply 2 coats low sheen acrylic to above 0.14
INTERIOR DOORS/FRAMES

No. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (each)

1 (a)Flush doors approx 1980 x 800 including both sides and frame 3.60
either acrylic or alkyd systems. Remove and replace hardware.
Prime, stop, undercoat and topcoats 'in situ'

2 (b)Ditto to above but remove doors and paint off site. 2.00
Return and rehang include painting frame etc

3 (c)Ditto but remove all hardware. 3.00


Use "painter's own" temporary hinge.
Spray all coats frame and door either HVLP or airless 0920
tip size

4 Paired bi-fold types as for above. Cavity sliders use rate (a) 3.60

5 Overheight doors
at 2700 high add 18% to rates above 4.00
at 3000 high add 25% to rates above 4.20

Open louver panelled doors add 10% to rates above

6 Fire doors approx 1980 x 800 each side and frame. 4.9
Protect identity markers and smoke stop frame seal from paint
splashes (painted in situ)
ORDINARY PAINTING

No. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (each)

1 Priming Works(Includes surface prep. works) 1 Painter + 1 Helper 18.75 150 sq.m.

2 Putty Works 1 Painter + 1 Helper 9.375 75 sq.m.

3 Painting Works - First Coat 1 Painter 31.25 250 sq.m.

4 Painting Works - Second Coat 1 Painter 43.75 350 sq.m.

EXPOXY PAINTING

No. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (each)

1 Surface Prep + Priming 1 Painter + 1 Helper 6.25 50 sq.m.

2 Painting 1 Painter + 1 Helper 12.5 100 sq.m.

No. CREW SIZE HOURLY PRODUCTION


PRODUCTION RATE PER 8HRS (each)

1 Prepare Walls - 14.2 113.6 sq.m.

2 Prepare Doors - 12.5 100 sq.m.

3 Prepare Door Frames - 25 200 m.

4 Burn Off / Heat Strip Paintwork - 1.1 8.8 sq.m.

5 Internal Timber, 1 coat primer before fixing, generally - 6.7 53.6 sq.m.

6 Internal Timber, 1 coat primer before fixing, timber lengths - 20 160 m.

7 Internal Timber, knot, 1 primer, stop, 1 undercoat, 1 gloss - 1.7 13.6 sq.m.

8 Internal Timber, touchup primer, 1 undercoat, 1 coat gloss - 3.1 24.8 sq.m.

9 Internal Timber, polyurethane varnish, 2 coats - 3.3 26.4 sq.m.

10 Internal Timber, polyurethane varnish, 3 coats - 2.2 17.6 sq.m.

11 Internal Timber, linseed oil to hardwood, 2 coats - 3.6 28.8 sq.m.

12 External Timber, knot, 1 primer, 2 undercoats, 1 coat gloss, - 1.5 12 sq.m.

13 External Timber, touchup primer, 2 undercoats, 1 coat gloss, - 2 16 sq.m.

14 External Timber, 2 coats wood preservative - 4 32 sq.m.


15 External Timber, 3 coats polyurethane varnish - 2 16 sq.m.

16 Internal Walls, 2 coats emulsion to plaster - 8 64 sq.m.

17 Internal Walls, 2 coats emulsion to brick/blockwork - 6 48 sq.m.

18 Internal Walls, 1 mist, 2 coats emulsion to plaster - 6 48 sq.m.

19 Internal Walls, 1 mist, 2 coats emulsion to brick/blockwork - 4.5 36 sq.m.

20 Internal Walls, 1 primer, 1 undercoat, 1 gloss to plaster - 2.3 18.4 sq.m.

21 Internal Walls, undercoat to door frame - 20 160 m.

22 Internal Walls, gloss to door frame - 16.5 132 m.

23 Internal Walls, undercoat to door - 7.1 56.8 sq.m.

24 Internal Walls, gloss to door - 6.2 49.6 sq.m.

25 External Walls, 2 coats sandtex to render/concrete - 2.5 20 sq.m.

26 External Walls, 2 coats sandtex to brick/blockwork - 2 16 sq.m.

27 External Walls, 1 sealer, 2 emulsion to render/concrete - 2 16 sq.m.

28 External Walls, 1 sealer, 2 emulsion to brick/blockwork - 1.7 13.6 sq.m.

29 Floors, epoxy paint - 2.9 23.2 sq.m.

30 Ceilings, emulsion paint, 2 coats - 6.1 48.8 sq.m.

31 Ceilings, emulsion paint, 3 coats - 5 40 sq.m.

32 Ceilings, textured paint - 4.2 33.6 sq.m.

33 Ceilings, artex finish - 4.1 32.8 sq.m.

34 Internal Steelwork, 1 primer, 1 undercoat, 1 gloss - 2.4 19.2 sq.m.

35 External Steelwork, 1 primer, 2 undercoats, 1 gloss - 1.7 13.6 sq.m.

36 Guttering Steelwork, 1 coat primer, 2 undercoats, 1 gloss - 2.5 20 m.