Documentos de Académico
Documentos de Profesional
Documentos de Cultura
EMANKMENT CONSTRUCTION
XIANG JIAN
Sinohydro Bureau 7 Bakun Project Management Team in Malaysia
[Abstracts] In the course of rock-fill dam construction, to minimize the project cost mainly depended on synchronization
of excavation & embankment strength at the same time point, synchronizing of excavation/embankment strength at the same
point is the key issue to solve the question how to save the cost in course of excavation/embankment works, here is to
introduce a solution aiming to the above question based on the practice of Bakun Project construction.
[Key words] Bakun Project , Rock-fill dam, Excavation-Embankment Balance, Rock allocation
1. Introduction
To effectively control the cost of rock-fill dam construction mainly depended on the extent of balanced
allocation on earth/rock excavation/embankment. Maximally utilize the rock materials from main structures
foundation excavation and directly transport them to the filling zones instead of stocking and secondary
transporting to the filling zones is the economic way to achieve the cost control
However, in the work practices, we usually are very difficult to manage the direct transportation of excavated
materials from structure foundation excavation to dam filling zones without secondary transportation, that is
because the contradiction of supply/demand from excavation/embankment is always hard to be integrative at a
certain time point, mainly due to the following reasons:
Completion of dam foundation excavation is the critical condition to start the dam embankment
work, and conduction of dam foundation excavation work should take up a certain period of work
duration while foundation excavation work at every other structure since is restrained by
completion time point has to be commenced not late than a certain time point, in this regard, the
excavated material from structure foundation excavation at early stage should have to be stocked at
that time instead of directly to be utilized for dam embankment;
After completion of dam foundation excavation, although the excavated materials from other
structure foundation excavation can be directly utilized, however, the work strength of dam
embankment is lower than of structure foundation excavation, or otherwise, therefore the surplus
material at the same time point should have to be stocked or disposed.
In view of the above reasons, shortening the time of dam foundation excavation, starting dam embankment
in advance as well as by adjusting work strength of excavation/embankment can reduce the amount of disposed
materials or secondary transportation for temporary stocked material. Thus, when planning of main structure
foundation excavation and dam embankment work, systematically working out of a reasonable excavation
/embankment work programme at every time interval is an effective way to achieve economic benefit. Its purpose
is under the condition of satisfying completion date of structure foundation excavation, to maximally utilize the
excavated materials from structure foundation excavation directly into dam embankment and reduce the
secondary transportation. The mathematical model hereinafter is built up to show how to minimize the amount
required for secondary transportation of suitable materials obtained from structure foundation excavation
2
Chart 1
n
qe i qf i* ti [ if qe i qf i0then
min Qd=
qe i
i=1 qf i=qe i qf iotherwise qe i qf i=0 ]
mn
Qe= ti
j=1i=1
qeij
3
In which
Qe: total volume of suitable materials obtained from structure excavation
mnumbers of zones at structure excavation area;
nnumbers of time interval divided for excavation/embankment work;
ti time at time interval i
Qeconstant( determined by volume of suitable materials from structure foundation excavation);
nnumbers of time intervals divided for excavation/embankment work, same as the above n.
n
Qe =
n
qi * ti t=ti
i=1
i=1
Here, t means overall construction time, under the condition of fixed overall construction time, t is as
constant, to simplify the calculation, the unit of t is regarded as months viz.
mn
Qe=
j=1i=1
qe ij
m
qeij
qe i=
j=1
By study the above chart, it can tell our optimized target is to adjust the work strength curve of
excvation close in on of embankment. So the target function can convert as:
n
min Qd=
i=1
qe i qf i [qe i qfi0otherwise qe i qf i=0 ]
certain analytic formula that is because the above assume t1= t2 =ti= tn=1 (month )then
accordingly converting to at every work area the ultimate excavation strength [qij]= f ijx1x2. the
ultimate embankment strength [q i0]= g yi 1y2..and (x1x2. as well as y1y2..represent
complicate variables ( the factors of work enviroment and resource etc that may determine work capacities at
every work area) .
[qij]: depending on size of work face, efficiency of single unit of excavating machine, numbers of
equipment, and ultimate traffic flow on haul road
[q i0]: depending on size of work face, efficiency of single unit of embankment machine, numbers of
equipemnt, and ultimate traffic flow on haul road ;
[qij] &[q i0]: derived according to work face condition, resources status, layered geological condition and
topograph condition.
m
q j=q
i i
j=1
sum of work strength of suitable materials obtained from m excavation areas at time interval i
n
q 0i =Q0 (total volume of embankment)
i=1
According to the q i and [q i] derived from the above, can further derive:
q ij [q i]
qi0[q 0i]
qi00
qij0
In consideration of having m structure excavation areas, then the formula can convert to:
Target function
n m m
min Qd= qij q i 0
[if
qij q i 00then
j=1
i=1 j=1
m m m
j=1
qij q i 0=
j=1
q qij q 0j
otherwise
j=1
q ij q i 0=0]
in which m
j=1
q ij qi 0
which meansthe difference of total sum of excavation strength for suitable materials excavated
simultaneously at time interval i(month) at structure excavation areas m less embankment strength at same
time interval i(month), viz. the amount of disposed materials at time interval i(month) which is
nonnegative value.
(month) m
n
min Qd=
q ij q i 0
j=1
i=1
which meansat time interval n, reaching the minimum amount of disposed materials in total
3. Solution Steps
3.1 Calculate out the total amount of structure excavation Qj according to the topography, geological
condition and design drawings, and then calculate out the amount of suitable material from each bench
excavation regarding the bench height of excavation/blasting as step length. As for total amount of
embankment, calculate out the amount of each layer of embankment subject to the certain step length.
3.2 With reference to the overall construction duration, determine the excavation start/completion date of
each structure, and according to the tentative work resources determine the start/completion date of
5
availability of supplying the excavated material for embankment. And subject to the one month as step
length determine the excavation time intervals. Determine the embankment start/completion date and
subject to the one month as step length determine the embankment time intervals.
3.3 According to the work face, topography, geological condition, haul road and equipment/plant condition
etc. determine the monthly restrained work strength including for excavation and embankment.
3.4 Calculate out monthly restrained work strength, including embankment strength [qf i] and strength for
supplying excavated material [qf i j], and then fill them in the table of constraint equation as below:
3.5 Formulate the target function equation.
3.6 With reference to the table data, the method of linear programme can be adopted for solutionhere not
going into details.
Constraint Equation
Excavating
1 2 j m Filling zone
Zone
4. Graphic Method
To simply the solution equation, the graphic method can be adopted for direct solution which its solution
step is as: calculating out the basic data described in the above, plotting the strength curves respectively
for embankment and excavation/supply (see Chart 2 as below); By following the constraint condition,
with graphic method, adjusti the both strength curves of excavation/embankment so as able to make the
two curves close as much as possible, in other words, to reduce the area of Zone 1, 2 ,3 and 4 shown in
the above Chart 1, but the attention should be drawn that the adjusted strength curve of excavation
should be within the scope of ultimate strength curve of excavation/supply; Solving for embankment
strength at every time interval and its corresponded excavation strength at every area at every time
interval. The virtue of graphic method is able to show the time-point strength process visually. During
execution period, with reference to the statistic data collected from past time interval, timely adjusting of
the curve at future time interval can dynamically realize the optimal control.
6
Chart 2
c) Calculate the total amount of embankment, determine the rolling passes, quantities/efficiency of
equipment, and haul road condition subject to the level of work face, calculate the amount of
embankment at every layer, then finally obtain the monthly ultimate embankment strength [qi0].
d) Determine the start/completion date of excavation at every structure area subject to the overall
construction duration; determine the start/completion date of supplying excavated materials for
embankment with reference to the initial work resources plan, determine time interval at every
excavation area with regarding one month as time step length , and determine the start/completion
date of embankment and time interval of embankment in one month as step length.
e) Calculate the amount of ultimate excavation at every area at every time interval (unit in month)
subject to constrained factors such as planned bench height for blasting/excavation, work space at
work face, equipment efficiency and haul road condition etc.; calculate the amount of suitable
materials for embankment obtained from ultimate excavation at time interval subject to geologic
topographic maps, and then get the constraint work strength [qij](m3/month) as below table:
8
Dec. 2004 495,238 29,477 202,869 166,721
Jan 2005 509,486 42,378 214,246 268,260
Feb. 2005 523,735 39,939 311,644 268,884
Mar. 2005 537,984 44,504 295,409 260,717
Apr. 2005 552,233 36,701 269,409 266,843
May 2005 566,481 26,434 217,540 266,762
Jun 2005 580,730 21,080 216,956 254,043
Jul.2005 594,979 16,006 217,013 228,190
Aug. 2005 609,227 17,690 224,360 192,125
Sep. 2005 623,476 13,777 179,440 262,998
Oct.2005 637,725 28,169 142,998 298,425
Nov. 2005 661,973 9,344 200,796 290,876
Dec. 2005 712,326 29,251 253,206 261,802
Jan 2006 850,231 30,299 231,448 269,523
Feb. 2006 901,245 29,967 205,554 471,130
Mar. 2006 902,237 64,053 164,757 243,525
Apr. 2006 884,567 29,289 159,677 379,322
May 2006 854,567 10,112 145,435 458,197
Jun 2006 834,567 11,017 124,617 520,306
Jul.2006 803,234 12,668 128,452 453,331
Aug. 2006 761,777 0 72,488 506,061
Sep. 2006 705,687 0 45,965 290,743
Oct.2006 503,456 0 23,200 223,563
Nov. 2006 431,422 0 20,445 349,088
Dec. 2006 401,422 0 7,000 265,563
Jan. 2007 362,312 0 7,000 245,563
Feb. 2007 321,467 0 0 225,563
Mar. 2007 301,467 0 0 225,563
Apr. 2007 234,123 0 0 225,563
[Qj] 19,096,327 889,239 5,658,100 9,286,731
ZMin{(q q q )}
i3 i4 i0
qi0[q i0 ]
qi1[q i1 ]
qi2[qi2]
qi3[qi3]
qi40
9
qi0=[Q0]
qi6=[Q0]
{qi0,qi1,qi2,qi3}{[qi0],[qi1],[qi2],[qi3]}
{qi0,qi1,qi2,qi3}0
5.5 The ultimate work capacity is substituted into the equation, and the linear programming method written
into computer program is solved for the optimized allocation result of rock excavation/embankment as
below table:
10
May 2006 561,454 10,112 145,435 456,202 155,547 50,296 611,749
Jun 2006 561,454 11,017 124,617 456,202 135,634 30,383 591,836
Jul.2006 562,162 12,668 128,452 453,331 141,120 32,289 594,451
Aug. 2006 541,138 0 72,488 475,810 72,488 7,161 548,299
Sep. 2006 504,003 0 45,965 290,743 45,965 0 336,708
Oct.2006 490,714 0 23,200 223,563 23,200 0 246,763
Nov. 2006 418,680 0 20,445 349,088 20,445 0 369,533
Dec. 2006 388,680 0 7,000 265,563 7,000 0 272,563
Jan. 2007 349,570 0 7,000 245,563 7,000 0 252,563
Feb. 2007 308,725 0 0 225,563 0 0 225,563
Mar. 2007 289,433 0 0 225,563 0 0 225,563
Apr. 2007 229,984 0 0 225,563 0 0 225,563
5.6 Allocation curve subject to the solved data( see below curve charts)
5.6.1 Result Curve of Balanced Allocation for Excavation/Embankment at every work area
11
5.6.2 Result Curve of Balanced Allocation for Overall Excavation/Embankment
6. Conclusions
The above allocation methodology, from the angle of adjusting of time point of work strength of
excavation/embankment, provided a kind of optimization method for balanced planning of the dam materials. This
method can easily reflect the dynamic and actual status of excavation/embankment work system, meanwhile, it
can more accurately calculate the volume of disposal at the relevant time interval, therefore, it can also be adopted
as guideline for reasonable planning of stock area for disposed materials. The solution of optimized work strength
of excavation/embankment at every time point can be as the basis of optimizing allocation of construction
resources and based on the planning result, through work process control the actual economic expectation can be
achieved .
12