Está en la página 1de 1

CUADRA, KASHAIRA V.

BSCE/ 5th YEAR


CE524CM (MT 7:00-8:30PM)

START FINISH
ACTIVITY DESCRIPTION DURATION
DATE DATE
A CLEARING AND HAULING 1-Jan 14-Jan 14
B LAYOUT 14-Jan 18-Jan 5
C EXCAVATION 18-Jan 3-Feb 17
D SOIL POISONING 18-Jan 21-Jan 4
E FOOTING REBAR 3-Feb 13-Feb 11
F COLUMN REBAR 3-Feb 13-Feb 11
G FOOTING POURING 13-Feb 14-Feb 2
H COLUMN FORM 13-Feb 16-Feb 4
I BEAM REBAR 13-Feb 23-Feb 11
J COLUMN POURING 16-Feb 17-Feb 2
K BEAM FORM 23-Feb 26-Feb 4
L SLAB REBAR 23-Feb 5-Mar 11
M SLAB FORM 5-Mar 8-Mar 4
N BEAM POURING 26-Feb 27-Feb 2
O SLAB POURING 8-Mar 9-Mar 2
P ROOFING 9-Mar 18-Mar 10

GANTT CHART
1-Jan 11-Jan 21-Jan 31-Jan 10-Feb 20-Feb 1-Mar 11-Mar 21-Mar

A1-Jan 14
14-Jan 5
C 18-Jan 17
18-Jan 4
E 3-Feb 11
3-Feb 11
G 13-Feb 2
13-Feb 4
I 13-Feb 11
16-Feb 2
K 23-Feb 4
23-Feb 11
M 5-Mar 4
26-Feb 2
O 8-Mar 2
9-Mar 10