Coliper tramo(m) (pulg) *2*L

90-150 26 40560

150-300 28.5 121837

300-800 27.9 380880

800-1000 29 168200

1000-1300 28.2 238572

= 2 = 28.02

BALANCE DE MATERIALES LECHADA PRINCIPAL

MASA KG P.E VOLUMEN LTR.

CEMENTO 100% 50 3.14 15.923

MASA 46% 23 1 23

TOTAL 73 38.923

DENSIDAD DE LECHADA PRINCIPAL

L.P= 73/38.93 = 1.875 GR/CC =15.63PPG

RENDIMIENTO= 38.923/159 LTRS./BBL =0.245 BBL/SRC

RENDIMIENTO(AGUA) = 23/ 150 LTRS/BBL =A.145 BBL/SRC

TIEMPO DE BOMBEABILIDAD= 3 HORAS ( LABORATORIO)

LECHADA REMOVIDA

MASA P.E VOLUMEN(LTRS.)

CEMENTO 100% 50 3.24 15.923

AGUA 130% 65 1 65

BENTONITA 8%(AGUA) 5.2 2.6 2

TOTAL 120.2 82.923

L.R.= 120.2/ 82.923 = 1.459 GR/CC = 12 PPG


RENDIMIENTO= 82.923 LTS/SRC/159 LTS/SRC = 0.522 BBL/SRC

TIEMPO DE BOMBEABILIDAD = 7 HORAS (LABORATORIO)

VOLUMENES

VOLUMEN DE LECHADA PRINCIPAL


V1= ((28.02^2- 20^2)/1029.4)*300*3.281= 368.2 BBL.
V2= ((18.75)^2/1029.4)*40*3.281= 44.8 BBL

VOLUMEN TOTAL= 368.2*FS(1.1)*44.8 BBL

VOLUMEN DE LECHADA PRINCIPAL=450 BBL


VOLUMEN DE LECHADA REMOVIDA
V1=((28.02^2-20^2)/1029.4)*(1000-90)*3.281= 1117 BBL
V2=((28.02^2-20^2)/1029.4)*90*3.281 = 122 BBL

VOLUMEN TOTAL=1117* FS(1.1) + 122 BBL

VOLUMEN DE LECHADA REMOVIDA. =1351 BBL

VOLUMEN DE LECHADA PARA DEZPLAZAR LAS LECHADAS

V= (18.75^2/1029.4)*1260*3.281 =1412 BBL

VOLUMEN DE LODO= 1412 BBL

SACOS DE CEMENTO
L. PRINCIPAL= 450 BBL / 0.245 BBL/SRC = 1837 SACOS
L. REMOVIDA= 1351 BBL/ 0.522 BBL/SRC = 2588 SACOS

TIIEMPO DE OPERACION

1.-MESCLAR Y BOMBEAR 1351 BBL DE LECHADA REMOVIDA


2588 SACOS/25 SACOS/ MINUTO= 104 MINUTO
2.-MESCLAR Y BOMBEAR 450 BBL DE LECHADA PRINCIPAL
1837 SACOS/ 25 SACOS/ MINUTO= 74 MINUTO
3.- BAJAR TAPON SUPERIOR 15 MINUTOS
4.- BOMBEAR 1412 BBL DE LODO A 8 RPM 177 MINUTO
5.- IMPREVISTOS 60 MINUTO
TOTAL= 430 MINUTO
LECHADA REMOVIDA = 430 MINUTO & 7 HRS.. 10 MINT.
T BOMBA < T OPERACIN
LECHADA PRINCIPAL = 326 MIN & 5 HRS. 26 MINT.
T BOMBA< T OPERACIN
COMO EL TIEMPO DE BOMBEABILIDAD ES MENOR , QUE EL TIEMPO DE OPERACIN ES NECESARIO
AGREGAR RETARDADORES TANTO A LA LECHADA PRINCIPAL COMO A LA REMOVEDORA.

LOS RETARDADORES SON ADITIVOS QUE AUMENTAN EL TIEMPO DE BOMBEABILIDAD DE LA


LECHADADA.

OTRA SOLUCIN SERIA EL USO DE STINGER:

*BAJAMOS ESTINGUER 4*3+DP`S;19.5 PPF ID=4.276

EL USO DEL STINGER NOS BENEFICIA EN QUE DISMINUYE EL TIEMPO DE OPERACIN AL


DISMINUIR EL VOLUMEN NECESARIO PARA DESPLAZAR LECHADA.

V1= (4.276^2* 1029.4)*1260*3.281 =74 BBL

LOS TIEMPOS I Y 2 SON LOS MISMOS

3.- BOMBEAR 74 BBL DE LODO A 8 BPM 10 MINT.

4.- IMPREVISTOS 60 MINT.

* LECHADA REMOV EDORA = 248 MINUTO O 4 HRS 8 MINT.

TIEMPO DE BOMBEABILIDAD > T OPERACIN

*LECHADA PRINCIPAL = 144 MINUTO O 2 HRS. 24 MINT.

TIEMPO DE BOMBEABILIDAD > T OPERACION