Está en la página 1de 2

ACCESORIOS BAOS

CONCRETOS y ANLISIS UM CANT. BOGOT CALI B/QUILLA MEDELLN ANLISIS UM CANT. BOGOT CALI B/QUILLA MEDELLN

MORTEROS
ANLISIS UM CANT. BOGOT CALI B/QUILLA MEDELLN ANLISIS UM CANT. BOGOT CALI B/QUILLA MEDELLN

HERRAMIENTA MENOR % 5.00 21,433 20,711 20,162 20,711


CONCRETOS HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
CONCRETO CORRIENTE GRAVA COMUN 1500 P.S.I. m 450,094 434,921 423,392 434,921
AGUA lt 160.00 2,560 2,560 2,560 2,560 MORTERO 1:3 m
ARENA LAVADA DE PEA m 0.50 30,856 30,856 30,856 30,856
AGUA lt 240.00 3,840 3,840 3,840 3,840
CEMENTO GRIS kg 210.00 119,700 115,500 111,720 115,500 ARENA FINA m 1.09 50,576 48,047 48,047 48,047
GRAVA 1 m 1.00 46,400 34,500 59,508 41,800 CEMENTO GRIS kg 454.00 258,780 249,700 241,528 249,700
HERRAMIENTA MENOR % 10.00 23,147 21,537 23,660 22,267 HERRAMIENTA MENOR % 5.00 17,257 16,677 16,268 16,677
HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135 HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818 MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
254,616 236,906 260,257 244,936 362,406 350,217 341,637 350,217
CONCRETO CORRIENTE GRAVA COMUN 2000 P.S.I. m MORTERO 1:3 IMPERMEABILIZADO m
AGUA lt 170.00 2,720 2,720 2,720 2,720 AGUA lt 240.00 3,840 3,840 3,840 3,840
ARENA LAVADA DE PEA m 0.63 38,879 38,879 38,879 38,879 ARENA FINA m 1.09 50,576 48,047 48,047 48,047
CEMENTO GRIS kg 260.00 148,200 143,000 138,320 143,000 CEMENTO GRIS kg 454.00 258,780 249,700 241,528 249,700
GRAVA 1 m 0.84 38,976 28,980 49,987 35,112 HERRAMIENTA MENOR % 5.00 26,189 25,609 25,200 25,609
HERRAMIENTA MENOR % 10.00 26,073 24,553 26,186 25,166 HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135 MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818 SIKA -1 (20 KG) kg 1.10 178,640 178,640 178,640 178,640
286,800 270,085 288,044 276,830 549,978 537,789 529,209 537,789
CONCRETO CORRIENTE GRAVA COMUN 2500 P.S.I. m MORTERO 1:4 m
AGUA lt 170.00 2,720 2,720 2,720 2,720 AGUA lt 220.00 3,520 3,520 3,520 3,520
ARENA LAVADA DE PEA m 0.48 29,622 29,622 29,622 29,622 ARENA FINA m 1.16 53,824 51,133 51,133 51,133
CEMENTO GRIS kg 300.00 171,000 165,000 159,600 165,000 CEMENTO GRIS kg 364.00 207,480 200,200 193,648 200,200
GRAVA 1 m 0.95 44,080 32,775 56,533 39,710 HERRAMIENTA MENOR % 5.00 14,839 14,340 14,013 14,340
HERRAMIENTA MENOR % 10.00 27,937 26,207 28,043 26,900 HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135 MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818 311,616 301,146 294,266 301,146
307,312 288,277 308,470 295,905 MORTERO 1:4 IMPERMEABILIZADO m
CONCRETO CORRIENTE GRAVA COMUN 3000 P.S.I. m AGUA lt 220.00 3,520 3,520 3,520 3,520
AGUA lt 180.00 2,880 2,880 2,880 2,880 ARENA FINA m 1.16 53,824 51,133 51,133 51,133
ARENA LAVADA DE PEA m 0.56 34,559 34,559 34,559 34,559 CEMENTO GRIS kg 364.00 207,480 200,200 193,648 200,200
DETALLADOS
GENERALES

CEMENTO GRIS kg 350.00 199,500 192,500 186,200 192,500 HERRAMIENTA MENOR % 5.00 22,959 22,460 22,133 22,460
GRAVA 1 m 0.84 38,976 28,980 49,987 35,112 HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
HERRAMIENTA MENOR % 10.00 30,787 29,087 30,558 29,700 MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135 SIKA -1 (20 KG) kg 1.00 162,400 162,400 162,400 162,400
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818 482,136 471,666 464,786 471,666
338,654 319,959 336,136 326,704 MORTERO 1:5 m
CONCRETO CORRIENTE GRAVA COMUN 3500 P.S.I. m AGUA lt 182.00 2,912 2,912 2,912 2,912
AGUA lt 250.00 4,000 4,000 4,000 4,000 ARENA FINA m 1.20 55,680 52,896 52,896 52,896
ARENA LAVADA DE PEA m 0.67 41,347 41,347 41,347 41,347 CEMENTO GRIS kg 302.00 172,140 166,100 160,664 166,100
CEMENTO GRIS kg 420.00 239,400 231,000 223,440 231,000 HERRAMIENTA MENOR % 5.00 13,134 12,693 12,421 12,693
GRAVA 1 m 0.67 31,088 23,115 39,870 28,006 HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
HERRAMIENTA MENOR % 10.00 34,779 33,142 34,061 33,631 MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135 275,819 266,554 260,846 266,554
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818 MORTERO 1:6 m
382,567 364,557 374,671 369,937 AGUA lt 158.00 2,528 2,528 2,528 2,528
CONCRETO CORRIENTE GRAVA FINA 2000 P.S.I. m ARENA FINA m 1.20 55,680 52,896 52,896 52,896
AGUA lt 170.00 2,720 2,720 2,720 2,720 CEMENTO GRIS kg 261.00 148,770 143,550 138,852 143,550
ARENA FINA m 0.63 29,232 27,770 27,770 27,770 HERRAMIENTA MENOR % 5.00 11,947 11,546 11,311 11,546
HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
CEMENTO GRIS kg 260.00 148,200 143,000 138,320 143,000
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
GRAVA NO 7 - 1/2 m 0.84 49,987 33,743 49,987 49,987
HERRAMIENTA MENOR % 10.00 26,209 23,919 25,075 25,543 250,878 242,473 237,540 242,473
HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818 PAETES
288,301 263,105 275,825 280,973
CONCRETO CORRIENTE GRAVA FINA 3000 P.S.I. m FILOS Y DILATACIONES m
AGUA lt 180.00 2,880 2,880 2,880 2,880 HERRAMIENTA MENOR % 5.00 309 304 300 304
ARENA FINA m 0.56 25,984 24,685 24,685 24,685 HORA CUADRILLA AA ALBAILERA-PREST. hc 0.16 3,062 3,062 3,062 3,062
CEMENTO GRIS kg 350.00 199,500 192,500 186,200 192,500 MORTERO 1:4 m 0.01 3,116 3,011 2,943 3,011
GRAVA NO 7 - 1/2 m 0.84 49,987 33,743 49,987 49,987 6,487 6,377 6,304 6,377
HERRAMIENTA MENOR % 10.00 31,030 28,576 29,570 30,200 MALLA CON VENA BAJO ENTRAMADO m
HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
HERRAMIENTA MENOR % 5.00 565 565 565 565
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
HORA CUADRILLA AA ALBAILERA-PREST. hc 0.40 7,654 7,654 7,654 7,654
341,334 314,337 325,275 332,205 MALLA CON VENA 0.60M X 2.00M un 0.83 3,569 3,569 3,569 3,569
PUNTILLA CON CABEZA 2 lb 0.04 84 84 84 84
MORTEROS 11,872 11,872 11,872 11,872
PAETE BAJO ESTERILLA DE GUADUA 1:5 m
MORTERO 1:2 m HERRAMIENTA MENOR % 5.00 999 994 991 994
AGUA lt 250.00 4,000 4,000 4,000 4,000 HORA CUADRILLA AA ALBAILERA-PREST. hc 0.90 17,222 17,222 17,222 17,222
ARENA FINA m 0.97 45,008 42,758 42,758 42,758 MORTERO 1:5 m 0.01 2,758 2,666 2,608 2,666
CEMENTO GRIS kg 610.00 347,700 335,500 324,520 335,500 20,979 20,881 20,821 20,881

210 CONSTRUDATA
CONCRETOS Y MORTEROS - PAETES

ANLISIS UM CANT. BOGOT CALI B/QUILLA MEDELLN ANLISIS UM CANT. BOGOT CALI B/QUILLA MEDELLN

PAETE BAJO MALLA 1:4 m PAETE LISO BAJO PLACA 1:6 m


HERRAMIENTA MENOR % 5.00 1,173 1,162 1,155 1,162 HERRAMIENTA MENOR % 5.00 987 982 980 982
HORA CUADRILLA AA ALBAILERA-PREST. hc 0.90 17,222 17,222 17,222 17,222 HORA CUADRILLA AA ALBAILERA-PREST. hc 0.90 17,222 17,222 17,222 17,222
MORTERO 1:4 m 0.02 6,232 6,023 5,885 6,023 MORTERO 1:6 m 0.01 2,509 2,425 2,375 2,425
24,627 24,407 24,262 24,407 20,717 20,629 20,577 20,629
PAETE BAJO MALLA 1:5 m PAETE LISO MUROS 1:3 m
HERRAMIENTA MENOR % 5.00 1,137 1,128 1,122 1,128 HERRAMIENTA MENOR % 5.00 1,051 1,039 1,030 1,039
HORA CUADRILLA AA ALBAILERA-PREST. hc 0.90 17,222 17,222 17,222 17,222 HORA CUADRILLA AA ALBAILERA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:5 m 0.02 5,516 5,331 5,217 5,331 MORTERO 1:3 m 0.02 7,248 7,004 6,833 7,004
23,875 23,680 23,560 23,680 22,077 21,821 21,640 21,821
PAETE BAJO MALLA 1:6 m PAETE LISO MUROS 1:4 m
HERRAMIENTA MENOR % 5.00 1,112 1,104 1,099 1,104 HERRAMIENTA MENOR % 5.00 1,000 990 983 990
HORA CUADRILLA AA ALBAILERA-PREST. hc 0.90 17,222 17,222 17,222 17,222 HORA CUADRILLA AA ALBAILERA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:6 m 0.02 5,018 4,849 4,751 4,849 MORTERO 1:4 m 0.02 6,232 6,023 5,885 6,023
23,351 23,175 23,071 23,175 21,010 20,790 20,646 20,790
PAETE IMPERMEABILIZADO MUROS 1:3 m PAETE LISO MUROS 1:5 m
HERRAMIENTA MENOR % 5.00 1,514 1,496 1,483 1,496 HERRAMIENTA MENOR % 5.00 965 955 950 955
HORA CUADRILLA AA ALBAILERA-PREST. hc 0.72 13,777 13,777 13,777 13,777 HORA CUADRILLA AA ALBAILERA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:3 IMPERMEABILIZADO m 0.03 16,499 16,134 15,876 16,134 MORTERO 1:5 m 0.02 5,516 5,331 5,217 5,331
31,790 31,406 31,136 31,406 20,258 20,064 19,944 20,064
PAETE IMPERMEABILIZADO MUROS 1:4 m PAETE LISO MUROS 1:6 m
HERRAMIENTA MENOR % 5.00 1,412 1,396 1,386 1,396 HERRAMIENTA MENOR % 5.00 940 931 926 931
HORA CUADRILLA AA ALBAILERA-PREST. hc 0.72 13,777 13,777 13,777 13,777 HORA CUADRILLA AA ALBAILERA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:4 IMPERMEABILIZADO m 0.03 14,464 14,150 13,944 14,150 MORTERO 1:6 m 0.02 5,018 4,849 4,751 4,849
29,653 29,324 29,107 29,324 19,734 19,558 19,454 19,558
PAETE LISO BAJO PLACA 1:4 m PAETE RUSTICO BAJO PLACA 1:5 m
HERRAMIENTA MENOR % 5.00 1,017 1,012 1,008 1,012 HERRAMIENTA MENOR % 5.00 1,562 1,548 1,539 1,548
HORA CUADRILLA AA ALBAILERA-PREST. hc 0.90 17,222 17,222 17,222 17,222 HORA CUADRILLA AA ALBAILERA-PREST. hc 1.20 22,962 22,962 22,962 22,962
MORTERO 1:4 m 0.01 3,116 3,011 2,943 3,011 MORTERO 1:5 m 0.03 8,275 7,997 7,825 7,997
21,355 21,245 21,172 21,245 32,798 32,507 32,327 32,507
PAETE LISO BAJO PLACA 1:5 m PAETE RUSTICO MUROS 1:5 m
HERRAMIENTA MENOR % 5.00 999 994 991 994 HERRAMIENTA MENOR % 5.00 1,370 1,357 1,348 1,357
HORA CUADRILLA AA ALBAILERA-PREST. hc 0.90 17,222 17,222 17,222 17,222 HORA CUADRILLA AA ALBAILERA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MORTERO 1:5 m 0.01 2,758 2,666 2,608 2,666 MORTERO 1:5 m 0.03 8,275 7,997 7,825 7,997
20,979 20,881 20,821 20,881 28,780 28,488 28,308 28,488

DETALLADOS
GENERALES

EDICIN 179 JUNIO - AGOSTO 2016 211

También podría gustarte