A Decade of
Decommissioning
and Abandonment
Part One, 2009-2013
Decommissioning &
Abandonment Summit
20-21 February 2018
Omni Hotel, Houston, Texas
Written by James Bourne of behalf of DecomWorld
Click here to pre-order the
conference brochureDecommissioning & Abandonment Summit 2018
20-21 February Omni Hotel, Houston, Texas Click here to pre-order the conference brochure
A Decade of Decommissioning and Abandonment Part One, 2009-2013
Business Intelligence for the Offshore Oil & Gas Industry
Overview
The inaugural DecomWorld Decommissioning & Abandonment summits
were set against the backdrop of recent hurricanes in the Gulf of Mexico
(GoM) that had left a trail of destruction and an indelible mark on the wider
oil and gas industry, notably the decommissioning part of it. Operators faced
seismic challenges, as the significant damage wrought by the elements --
in the 10 years to 2011, 183 platforms in the GoM were destroyed and 839
pipelines compromised due to hurricane activity forced new regulatory
regimes, upended project economics and paved the way for new technologies
designed to deal with the mammoth decommissioning tasks. All these issues
figured prominently at DecomWorld summits, as leading industry players
outlined the next steps forwards and gave tantalizing glimpses into the new
thinking needed to cope with Idle Iron Notice to Lessees (NTL) and other
challenges. The following contributions touch on the major issues as seen
from the prism of 2009-2013, as the industry grappled with a brave new
world.
Decommissioning &
Abandonment Summit
20-21 February 2018
Omni Hotel, Houston, Texas
Yet the 2013 summit was able to report some progress in reaching Idle Iron
targets. Addressing that summit, Michael Saucier, the head of the GoM region
at the BSEE, put the inventory of Idle Iron at 2,016 total idle wells (including
260 newly idle since NTL) and 400 idle platforms (including 62 newly idle
since NTL). He said 770 total platform removal permits had been approved
since the NTL three years earlier. He reinforced the message that the BSEE
was implementing a strict policy on the NTL, though in certain cases, he
acknowledged extensions could be granted if the data could justify it.
Risk mitigation
The concept of risk mitigation embedded itself firmly in the lexicon of the
DecomWorld summits in the 2009-2013 period. David Wisch, a Chevron
fellow, posed the key question in his address to the 2009 summit: whether
the notion of what is acceptable risk was changing noting that the original
decommissioning code left the determination of an acceptable level of
economic risk to the operators discretion, and that it could be beneficial for
an operator to perform explicit cost-benefit risk analyses in addition to simply
using this recommended practice. While many were meeting the codes
terms, said Wisch, the issue of risk was not being properly addressed.
The recent impact that hurricane damage had exerted on offshore structures
meant that this attitude had to be changed and entire portfolios assessed
and ranked according to risk exposure. This would lead to a more proactive
approach to risk mitigation, moving it beyond something that was once
deemed as simply a cost to be borne.
The issue of risk mitigation was prominent for other key speakers at the
2009-2013 summits. Some highlighted the opportunities that would be
forthcoming. As Kaiser noted in 2010, plugging idle wells also reduces
decommissioning risk because -- at least for permanent abandonments --
conductor removal decreases the chance the structure will be toppled. If a
structure is destroyed, wells that have been abandoned save operators time
and expenditure in decommissioning operations.
In 2011, Frank Buescher of Casparian Engineering, delivered a paper outlining
the importance of pre-emptive mitigation to avoid the risk of downed
structures, and how to manage resources by platform age, water depth, deck
height, platform axis orientation and well conductor density. He mentioned
techniques which could be employed to reduce risk including wave profile
reduction, platform strengthening, structural integrity analysis and removal
of conductors.
Buescher outlined the cost of the risk mitigation options in descending
order. Top of the list was deck elevation, followed by conductor removal and
riser removal. Platform strengthening would be a less expensive option for
operators, but came with a caveat: If you run your analysis and find out your
pile or foundation has a problem then strengthening the platform isnt going
Decommissioning &
to help you, he said.
Abandonment Summit
20-21 February 2018
Omni Hotel, Houston, Texas
Cost estimation
The early DecomWorld summits grappled with one of the big issues
confronting the industry cost, and more specifically, the difficulties in
estimating costs associated with decommissioning in the wake of hurricane
activity in the GoM. As BJ Kruse noted in 2009, the costs for removal of
toppled structures and wells was in the range of 10-15 times more than
normal abandonment and removal. In 2009, the average cost for removing a
structure stood at $1.2m and to plug a well, at $775,000.
In 2009, decommissioning costs were escalating to an all-time high a
source of considerable disquiet at the time, as the summit that year revealed.
Decommissioning costs, as a whole, had gone from less than 1% to just under
2% globally from 2006-2010. Decommissioning costs went up on average of
22% annually over the same period, according to one of the speakers, Richard
Ward, VP of Global Sales and Marketing, at TETRA Offshore Services.
Michael J. Saucier, Field Operations Supervisor at BSEEs Gulf of Mexico OCS
regional office, noted that some facilities topple during hurricanes, risking
pollution, and that it costs significantly more to clean up, plug, and abandon
a toppled well.
Numerous factors impact costs and costs are themselves subject to
significant uncertainty. According to Kaiser, again speaking in 2009, these
included the wide variety of configurations, sizes, weight, water depth,
ownership, preparation time, market rates, contact terms, economies of scale
weather and technology evolution. He noted that tor wells on producing
platforms, operators will need to determine the benefit and cost on an
individual well basis, which was difficult to evaluate. The estimated total cost
to perform the requirements specified by the NTL is likely to range between
$1.4bn to $3.5bn, according to Kaiser.
Decommissioning &
Abandonment Summit Edgar Anderson, President of Maritech Resources, highlighted some of
the lessons learned from decommissioning in the West Delta at the 2009
20-21 February 2018
DecomWorld Summit. Maritech, he said, was removing idle iron long before
Omni Hotel, Houston, Texas hurricanes and the MMS made it a popular thing to do, and budgeted $50m
annually for decommissioning and well abandonment. In his view, consistent
Click here to pre-order the
conference brochure
A Decade of Decommissioning and Abandonment Part One, 2009-2013
Business Intelligence for the Offshore Oil & Gas Industry
Having a price list is one strategy employed in the GoM that was popular
among many contractors. Another option was pure turnkey projects, where
for defined scope of work contactors offers proposals to execute that for
fixed amount a variation on this being qualified lump sum terms. Siems
noted that pay per performance was difficult to employ as it is very hard in
decommissioning work to determine the metrics on which you will evaluate
performance. There were, he said, so many variables outside the control of
the operator, especially on properties that are more than 50 years old and
may have stood idle for 20 years.
New technologies
The need for efficiency in decommissioning has proved a significant driver
for technology advances. New technologies therefore featured prominently
in the DecomWorld summits between 2009 and 2013, with the Katrina and
Rita hurricanes forcing the pace on solutions such as dynamically positioned
dive vessels and coupled ROV-diver work two technologies that came
as a response to damage to infrastructure in the wake of those events. As
DecomWorlds own reports have illustrated, the high cost of decommissioning
creates business opportunities for technology to cut costs -- while still
protecting people and the environment.
One innovative technology highlighted at the 2010 DecomWorld summit was
a new inflatable technique to stop annular bubbles in subsea P&A wells. Wade
Maxwell, GoM Decommissioning Project manager at Baker Hughes, noted
that plugging and abandoning wells using the normal method using cast
iron plugs, cement and or resin were not always sufficient to decommission
wells that are bubbling and need different handling. One solution was the
use of vented inflatable method using PIP inflatable technology. Under this
technology, developed in 2009, a vented PIP is run into a well that is bubbling
and is used as a mechanical barrier to divert the flow of bubbles while
cement that is place on top of the PIP sets up. On top of the vent tubing, a
mechanical disconnect device is in place to facilitate disconnecting from the
tool once the initial cementing operations have been concluded and a plug
has been placed in the tubing. This technology would help the bottom line,
said Maxwell, with expected savings of $900,000 to $1.3m per well versus the
conventional method.
Efficient methods for the use of ROVs in subsea commissioning were
developed in the late 2000s, and the DecomWorld summits played host to
the announcement of exciting new developments in this area. According to
Mads Bardsen, President of Subsea Services at Trico Marine, there was no one
tool fits approach, but some tools were a better match for use with ROVs
than others. The advantage of ROVs are clear in reducing exposure for drivers
he said and more appropriate for decommissioning compared to repairing
structures on producing fields.
Decommissioning &
Abandonment Summit
20-21 February 2018
Omni Hotel, Houston, Texas
Decommissioning &
Abandonment Summit
20-21 February 2018
Omni Hotel, Houston, Texas
Decommissioning, Abandonment
and Late-Life Asset Management
Conference
Decommissioning &
Abandonment Summit 2018
20-21 February Omni Hotel, Houston, Texas
Celebrating its 10th year of bringing together the most influential names in the industry, The Decommissioning
& Abandonment Summit 2018 will share a decades worth of decommissioning and well P&A data, recent
case study insight and lessons learned in an unrivalled learning experience.
As the worlds largest and most established late-life summit, no other meeting point is able to bring you the
quality of information and networking as The Decommissioning & Abandonment Summit 2018.
Just some of the thousands of attendees that have attended the Decommissioning & Abandonment
Summit over the last decade:
Decommissioning &
Abandonment Summit
20-21 February 2018
Omni Hotel, Houston, Texas
Want to join these industry leaders at the largest event of its kind?
Click here to pre-order
Sign upthe
by October 6 to get an extra $100 off your pass
conference brochure
simply quote REPORT when registering here