Documentos de Académico
Documentos de Profesional
Documentos de Cultura
programming to management
accounting
In the previous chapters we have seen that there be scarce. The opportunity costs of these scarce
is an opportunity cost for scarce resources that resources can be determined by the use of linear
should be included in the relevant cost programming techniques. Our objective in this
calculation for decision-making and variance chapter is to examine linear programming
calculations. Our previous discussions, however, techniques and to consider how they can be
have assumed that output is limited by one scarce applied to some specific types of decisions that a
resource, but in practice several resources may firm may have to make.
Product Y () () Product Z () ()
Standard selling price 38 Standard selling price 42
Less Standard cost: Less Standard cost:
Materials {8 units at 1) 8 Materials (4 units at 1) 4
Labour (6 hours at 2) 12 Labour {8 hours at 2) 16
Variable overhead Variable overhead
(4 machine hours at 1) 4 (6 machine hours at 1) 6
24 26
Contribution 14 Contribution 16
During the next accounting period, it is expected that the availability of labour hours will be
restricted to 2880 hours. The remaining production inputs are not scarce, but the marketing manager
estimates that the maximum sales potential for product Y is 420 units. There is no sales limitation for
product Z.
()
420 units of Y at a contribution of 14 per unit 5880
45 units of Z at a contribution of 16 per unit 720
6600
Where more than one scarce resource exists, the optimum production programme
Two-resource cannot easily be established by the process previously outlined. Consider the situ-
ation in Exhibit 24.1, where there is an additional scarce resource besides labour. Let
constraints us assume that both products Y and Z use a common item of material and that the
supply of this material in the next accounting period is restricted to 3440 units.
There are now two scarce resources - labour and materials. If we apply the proce-
dure outlined above, the contributions per unit of scarce resource would be as
follows:
Product Y Product Z
Labour 2.33 2.00
Material 1. 75 (14/8) 4.00 (16/4)
This analysis shows that product Y yields the largest contribution per labour hour,
and product Z yields the largest contribution per unit of scarce materials, but there
is no clear indication of how the quantity of scarce resources should be allocated to
each product. In such circumstances there is a need to resort to higher-powered
mathematical techniques to establish the optimal output programme.