DISEO DE PAVIMENTO

TIPO DE VEH L M M J V S D TOTAL


AUTOS 1 1 1 0 2 2 1 8
C2 1 0 0 0 0 0 0 1
T3S2 0 0 1 0 0 0 0 1
C4 0 0 0 0 0 0 0 0
TOTAL 2 1 2 0 2 2 1

CALCULO DEL IMDA

TIPO VEH TOTAL SEMANA IMDA S FCM IMDA %


AUTOS 8 1.1428571429 1.1002 1.2573714 81.00725
C2 1 0.1428571429 1.0318 0.1474 9.496374
T3S2 1 0.1428571429 1.0318 0.1474 9.496374
C4 0 0 1.0318 0 0
TOTAL 2 100

CBR = 6.55 %
TASA DE CRECI = 1.1 %
PERIODO DE DISE = 10 AOS
NUMER CARRILES = 1
IMDA = 2 VEH

SI CBR 7.2 >7.220 >20


MR 6000 3003.3928 3772.0599
CBR subras 6.55 % log CBR = 0.8162413
IMD 1 Veh
Periodo de dis = n 10 aos
(1+r)^n = 1.1156078
Tasa de crec = r 1.1 %
n de carriles 1
Factor de crec 10.51
CLCULO DE EALS O rep EE8.2Tn.

FACTOR DE
FACTOR
PRESIN FACTOR
TIPO DE VEH IMDa Fc EE DIRECCION
DE CARRIL Fact.
AL
LLANTAS Crecimie
EE dia carril nto
C2 1 3.68 1 3.68 0.5 1 1.84 10.51
T3S2 0 4.552 1 0 0.5 1 0 10.51
TOTAL
Nrep/120=
Espesor del afirmado log(Nrep/120)=
e= 151.15 mm
e= 15.11 cm
"e" adoptado 15.00 cm
N rep. EE
7058.516
0.000
7058.516
58.820967
1.7695322