Contract Duration :
Sub-Total P 50,000.00
B. LABOR COST QUANTITY NO. OF DAYS COST PER DAY
None - - - 0.00
Sub-Total P 0.00
C. EQUIPMENT COST QUANTITY NO. OF DAYS COST PER DAY
None - - - 0.00
Sub-Total P 0.00
Sub-Total P 3,328,650.00
B. LABOR COST QUANTITY NO. OF DAYS COST PER DAY
Project Engineer 1.00 7.00 600.00 4,200.00
Construction Leadman 1.00 7.00 500.00 3,500.00
Skilled Workers 10.00 7.00 400.00 28,000.00
Labor 10.00 7.00 300.00 21,000.00
Sub-Total P 56,700.00
C. EQUIPMENT COST QUANTITY NO. OF DAYS COST PER HOUR
None - - - 0.00
Sub-Total P 0.00
Sub-Total P 62,500.00
B. LABOR COST QUANTITY NO. OF DAYS COST PER DAY
Project Engineer 1.00 7.00 600.00 4,200.00
Construction Leadman 1.00 7.00 500.00 3,500.00
Skilled Workers 10.00 7.00 400.00 28,000.00
Labor 10.00 7.00 350.00 24,500.00
Sub-Total P 60,200.00
C. EQUIPMENT COST QUANTITY NO. OF DAYS COST PER HOUR
None - - - 0.00
Sub-Total P 0.00
ITEM III: TOTAL COST of ROAD PAVEMENT, PATHWALK/SIDEWALK & CURB & GUTTER 6,998,080.00