Documentos de Académico
Documentos de Profesional
Documentos de Cultura
665
1 (Retd.) Secretary to Government of the Punjab, Irrigation and Power Department, 77-Shah
Jamal Colony, Ichhra, Lahore.
176 Chohan
1.3 Balloki Headworks had originally been constructed for withdrawal of 6900
cusecs into the Lower Bari Doab Canal having a gross command area (GCA)
of 1.822 million acres and culturable command area (CCA) of 1.47 million
acres. With the partitioning of the sub-continent into Indo Pak segments in
the year 1947, the flow of river Sutlej was blocked by India. This deprived
irrigation and drinking water facility in the areas dependent on that source
of Pakistan side. Balloki Sulemanki Link off-taking from the left bank of this
headworks had therefore to be constructed in haste with a discharge of
15,182 cusecs in the year 1954 to provide water in the Sutlej river for feeding
the canals of Pakistan previously dependent on that source. This link was
also made to provide on its way, the irrigation water to the lower channels of
Depalpur Canal System, which hitherto were getting water from Ferozepur
Headworks of Sutlej river now under Indian control. The link canal has thus
saved from devastation a GCA of 0.654 or CCA of 0.615 million acres of the
10 direct off-takes of Lower Depalpur Canal System and a GCA of 3.366 or
CCA of 2.444 million acres of Forwah, Eastern Sadiqia and Pakpattan Canals
off-taking from Sulemanki Headworks. The total area benefited from Balloki
Headworks works out to GCA 5.842 or CCA of 4.729 million acres which is
about 23% of the total CCA of the Punjab Province.
1.4 River Ravi brings down very nominal flow below the first headworks on it
namely Madhopur in India. On this account it has a characteristic of taking
sharp loops which bring under attack even the distant abadies along its
route. This behaviour is observed close to the headworks also and
consequently a large number of river training works have been put on ground
to tame the river and ward off attack at the marginal bunds. At present apart
from the Pitched Island and Guide Banks there exist a battery of 11 spurs on
the upstream and 3 spur on the downstream sides of the headworks. Location
of the Barrage, ancillary structures and the layout of the training works are
shown at Figure-1.
1.5 Layout of the Barrage and Head Regulators are shown on Figure-2 with
salient features as under:-
The effect of the Thein Dam with storage capacity of 1.9 MAF constructed on
river Ravi in 2001 by India some distance upstream of Madhupur Headworks
was not taken into account in this analysis because of its short duration data
and also being too far away from Balloki Barrage.
4.2 The observed annual peak discharges and the result of three studies were
plotted on the probability paper and the one more consistent with the
observed data had been selected for the purpose of adoption at the site. In the
present case Log Pearson-III provided more appropriate resemblance with
the observed data and its computation for 100 years return period of 3.797 lac
cusecs would be a desirable selection. Incidentally this figure is very close to
the historic flood discharge of 3.893 lac cusecs reported during the year 1988
at Balloki which indicates reliability of the selected option.
4.3 Nespak conducted a study in the year 1987-88 and by applying Gumbel
method analysis alone calculated a discharge of 2.82 lac cusecs for 100 years
return period. This analysis did not include the historic high flood discharge
of 3.893 cusecs reported in the year 1988. Another study was made by
Nespak Harza group in the year 1996-97 and by using again the Gumbel
distribution system derived a value of 3.10 lac cusecs for 100 years return
period. Since Pearson and Log Pearson are the latest versions and equally
recognized international techniques for such analysis, their derivations
should not be ignored. Log Pearson-III analysis gives results best fit with
182 Chohan
actual data. Its derivation of 3.797 lac cusecs for 100 years return period
would therefore be a more reliable option to adopt at this site.
5. FLOOD MANAGEMENT
5.1 Design discharge of 3.797 (say 3.8) lac cusecs has been derived to hold good
for 100 years return period. The barrage with all bays in operation is
presently designed for 2.25 lac cusecs with upstream high flood level limit of
638.00. The balance discharge of 3.8 2.25 = 1.55 lac cusecs, if pushed
through designated breaching sites in the right marginal bund (R.D. 12 to
R.D. 49) as presently being practiced will be catastrophic for the area that
would get inundated (being thickly populated and cultivated by rains,
tubewells and canals Figure-6). Arrangement should therefore be devised to
handle the derivated flow to a maximum extent through the barrage gates
without impairing the safety of the structure and also from the right
marginal bund side by minimizing the damage of inundation by floodwater.
Various options to handle this situation are discussed in the paragraphs to
follow:-
A. Improving The Barrage Capacity
5.2 It is desirable to pass maximum flood discharge through the barrage by
incorporating feasible amendments/modifications in it. It is visualized that
the combined effect of the total discharge of 3.8 lac cusecs passing across the
structure through barrage and breaches would generate a flood water level of
637.00 on the downstream side of the headworks (a level attained during
super high flood of 3.90 lac cusecs in the year 1988). In this situation the
barrage in its present form of upstream designed HFL 638.0 with two bays
blocked by Pitched Island and adjoining two bays practically non-functional,
will not be able to pass a discharge more than 2.0 lac cusecs as against the
designed capacity of 2.25 lac cusecs.
5.3 To maximize the barrage capacity, a modular operation of the structure
would be desirable to maintain. This would become feasible by raising the
high flood limit upstream, say by one foot i.e. upto R.L.639.00. By so doing
the discharge capacity of the barrage would increase to about 2.30 lac cusecs.
If the earthen shank of the pitched island is replaced by a masonry/concrete
wall, the two totally and adjoining partially masked bays can be made fully
operational and in that situation the maximum discharge through the
barrage would increase to about 2.60 lac cusecs. To confirm this derivation,
the testing of such position was done on the comprehensive physical and
sectional model of the weir, by the Irrigation Research Institute which
established a discharge of 2.57 lac cusecs. This provision still leaves a gap
of 3.8 2.57 = 1.23 lac cusecs to be catered for through some other
feasible arrangement.
5.4 On raising the high flood level limit upstream by one foot, the flow through
the Barrage Works out to 2.57 lac cusecs against existing capacity of 2.25 lac
Pakistan Engineering Congress, 70th Annual Session Proceedings 183
cusecs. The intensity of flow over the structure thus increases by about 14%,
which remains within safe limits of the existing weir section as tested on the
model for energy dissipation. The raising of flood limit on upstream of the
barrage from R.L.638.00 to R.L.639.00 is therefore advisable to maximize
flow through the Barrage without impairing its safety. Corresponding raising
of the upstream training works will however need to be done depending upon
higher flood levels that might be generated against them.
B. Breaching Section Option to Pass Surplus Discharge
Change in Current Practice
5.5 There are two designated breaching sites on the right side. The site between
R.D 48,000 48,500 Madhodas bund (Figure-6) near end point of right
marginal bund is called as site No. 1 and between R.D 12,500 13,000 of the
marginal bund as site No. 2. Another suitable breaching site can be
incorporated between R.D 8,500 9,000 which being near the barrage will
perhaps be more suitable in providing immediate relief to the structure.
5.6 The breach site at Madhodas bund is too far off and does not provide
immediate relief at barrage. Addedly its flow inundates a vast belt of
developed cultivated area. It would be desirable to abandon this site and
replace this site with the one newly proposed between R.D 8,500 9,000 right
marginal bund and thus confine the inundation area limit within the riverian
zone upto the left side of abandoned Upper Chenab Canal (UCC). The ground
levels on the right of this abandoned canal are higher and majority of
inundated water from the breach of Madhudas bund even otherwise comes
towards the above riverian belt via a causeway in the metalled road near the
police check post at a distance of 12,500 ft. from the Barrage.
5.7 The area from headworks upto police check post is low lying. The metalled
road in this reach is about 4 to 10 ft higher than the adjoining ground.
Further away the metalled road is virtually at ground level. The water from
breaches at present goes to river by overtopping the road and causing
breaches in this reach of the road upto Police Post.
A big depression with pool of deep water exists even today at a distance of
2,400 ft from the headworks where the road is made to breach first on
making cuts in the right marginal bund. To pass the floodwater of breaches
hitting the metalled road (upto Police checkpost), it would be desirable to
construct 2 bridges of appropriate size on the depression sites at a distance of
2,400 ft; and 6,000 ft from the headworks to avoid road traffic disruption.
General scheme of this flood routing is shown in red color at Figure-6.
C. Annexe Weir
5.8 M/s Nespak Harza carried out study in the year 1996-97 under Flood Sector
Project which derived a discharge of 3.10 lac cusecs for 100 year return period
by Gumbel Distribution technique and proposed construction of an Annexe
Weir of 8 bays with lower crest of 2 ft on the right flank to pass a balance
184 Chohan
discharge of 3.10 2.25 = 0.85 lac cusecs through it (location at Figure-12 and
layout at Figure-13). With the expected water levels 637.0 to be generated on
the downstream and raised flood level limit of 639.0 on the upstream of
barrage, the annexe weir of lower crest will be able to handle an additional
discharge of about 0.68 lac cusecs. In this way, the barrage with annexe weir
provision will take a maximum discharge of 2.57+0.68 = 3.25 lac cusecs. A
balance of 3.8 3.25 = 0.55 lac cusecs would still remains to be
catered for via breaches in the right marginal bund or through some type of
an overflow spillway placed at a suitable location.
5.9 Provision of an Annexe Weir on the right flank will tantamount to increasing
the barrage length from existing of 1,646.50 ft to about 2,067 ft. The flow of
river at Balloki for nearly 10 months in a year hardly meet canals water
requirement off-taking on left flank and no escapage across the barrage takes
place. With this flow pattern, the right half of the barrage remains liable to
silt deposition and growth of bela in close vicinity of the structure tending to
block the floodwater passage in that part. The Annexe Weir will also be prone
to such adversaries and at times this part may not take its contemplated
share of discharge to pass it lower down. The provision of Annexe Weir will
encounter these snags, may be to a greater extent being further on the right
side of barrage; more so if ample surplus flows during the dry spells of a few
years do not become available for flushing/keep clear the approach channel of
river leading upto Annexe.
D. Overflow Spillway
5.10 The flood water from breaches of the right marginal bund causes lot of
damages to vast agriculturally developed and thickly populated area by
inundation/ submergence. Property loss, damage to infrastructure and
disruption of traffic over long period disturbs public life and generate strong
resentment from the direct affectees. With the passage of time, pressure on
land is bound to increase and the practice of making breaches in the marginal
bund may no longer remain workable.
5.11 Constructing an overflow spillway of adequate capacity at a suitable location
is a workable alternative to escape the excessive river flow for releasing
pressure on barrage. It is felt that an overflow spillway constructed at a short
distance upstream from the headworks between spur No. 10 and spur No. 3
may be desirable to incorporate in the system. The operation of this spillway
has been tested on a comprehensive physical model at Nandipur and
suggested mode gives satisfactory performance.
D-I Spillway with Provision of Annexe Weir
5.12 The provision of Annexe Weir at the right flank of barrage leaves a balance
discharge of 0.55 lac cusecs (derived in para 5.5) to be catered for by the
spillway. If the crest of this structure is kept one foot above the proposed
optimum raised pond R.L. 634.0 for canal withdrawals at the barrage, the
spillway shall begin to operate when flow in the river upto the high flood
Pakistan Engineering Congress, 70th Annual Session Proceedings 185
stage limit can be made to pass through the barrage at that pond level (1.30
lac cusecs designated capacity of high flood stage flow) and thus provides
simultaneous relief to be barrage structure matching with the rising river
flood water.
5.13 The discharge capacity of this spillway will depend upon the width of its crest
and the flood heights that would be generated by the rising flood. A spillway
width of 800 ft with crest at R.L. 635.0 and HFL 642.0 expected at this site
corresponding to 3.80 lac cusecs (para 4.2), a discharge of 55,000 cusecs to
60,000 cusecs (derived at para 5.8) would be escaping from this structure.
The location of the spillway and its geometrical configuration are shown at
Figure-7 and Figure-8.
5.14 The flood flow from the spillway in this arrangement is planned to be kept
within the limits of newly proposed tie bunds upto the junction of Balloki-
More Khunda road where a wide bridge would need to be constructed at
location shown in Figure-7 and geometrical details at Figure-9 to avoid public
property damage. Lower down a natural depression already exists to lead the
water on to the river channel about a mile downstream of the barrage.
E. Preferable Choice
5.17 Various options to handle the incoming floodwater of over and above
indicated higher discharge capacity of existing barrage (2.57 lac cusecs para
5.3) i.e. balance of 1.23 lac cusecs flow have been narrated in para 5.5 to para
5.16. The best choice seems in constructing an overflow spillway of low crest
for passing a discharge of 1.23 lac cusecs as narrated in para 5.15 and is
therefore recommended for adoption. The precise location, shape, layout and
operational performance may however be tested again on the physical model
depending upon river approach conditions prevailing at the time of project
execution.
F. Masking on Right Upstream of Barrage
5.18 With the transfer control of 3 Eastern rivers (Sutlej, Beas and Ravi) to India,
practically no flow is coming into Pakistan from these rivers even during the
monsoon season and due to construction by India of Bhakra and Pong Dams
on Sutlej/Beas rivers and Thein dam on river Ravi upstream Madhopur
Headworks. The canal systems of the country on these rivers are now being
fed by transferring water from western rivers via link canals and storage
water of dams. This has resulted in the formation of almost dry river zones
below the headworks of Sulemanki and Islam on Sutlej; below Balloki and
Sidhnai on Ravi, below Qadirabad on Chenab and below Rasul on Jhelum
(due to Mangla storage). Heavy bela formation is taking place on the
upstream of all these structures with pronounced masking opposite the right
bays as all withdrawals on these barrages are from the left flank. Vegetation
grow on these belas and their washing had become almost impossible, more
so, because sizeable surplus flow is often not available to pass lower down
even during the flood period of July to August. This phenomena has in turn
been adversely affecting the discharging capability of the bays on the right
side of Balloki Barrage apart from causing of parallel flow conditions from
left to right side close to the structure. This state of affairs made liable to
damage the upstream floor/loose stone protection of the barrage in the event
of high floods and seriously impaired the discharging capacity of the
structure as a whole.
5.19 Efforts made in the past to reduce development of belas/masking on the right
and to make the affected bays of the structures fully operational by way of
leading cuts has failed completely. A pitched Island of about 1,500 ft length
with stone pitched semi circular end nose (upstream of bay 19 and bay 20)
was constructed in the year 1956-57 to feed the right side of barrage from its
upstream but the same also did not help much to keep the bela growth under
check. Foreign experts suggest provision of dredgers at such sites which
would be a very expensive prescription apart from their operational
problems. Our experience of keeping dredgers for desilting of canals at
Qadirabad and Trimmu has been a complete failure and the equipment had
ultimately to be disposed off as scrap. Nespak-Harza in their report of 1996-
97 on Balloki suggested keeping a dredger at site for maintaining a direct
Pakistan Engineering Congress, 70th Annual Session Proceedings 187
approach channel of the river on the right side for keeping that part of the
weir fully operational. This provision neither suited the environments of this
country nor a situation of having a direct approach channel of the river arm
on that side is feasible to create at site.
G. Dividing Walls
5.20 A practical and natural solution of the problem is to keep the bela formation
tendency at some distance from the structure so that the right bays may
remain fully open/operational to handle their share of discharge when
required. At Balloki, it is suggested to form compartments of flow by putting
Dividing Walls on the upstream side. These walls may be approximately 400
ft straight in length with slope ends of 69 ft and should be constructed after
every six bays commencing from right and going upto about the middle of the
structure i.e. 3 dividing walls opposite piers of bays between 17-18, 23-24 and
29-30 (Figure-7 & 12). The extreme left wall at pier No. 17 will be about 900
ft in length so as to keep flow currents of right side compartments away from
the zone of canal head regulators for silt control. These walls will also need
extension on the downstream floor of the barrage upto the baffle wall block to
streamline the exit flow conditions. This provision will enable passing the
incoming surplus/low flood flow through these compartments turn by turn
and flush down deposited silt of each zone by generating silt eroding velocity
of water in them. Approach of water to these compartments will in this
situation be at a safe distance upstream of the barrage structure and that
would obviate chances of any damage to the structure by parallel flow
phenomena. The bela formation in this way will shift fairly upstream of the
barrage and would thus not hamper the overall discharging efficacy of the
barrage structure. Similar effect will be achieved on the Annexe Weir (if that
is introduced in the system) by restricting dividing groyne/wall to a narrow
width of nearly 50 ft and keeping its length as for other dividing walls. The
working of the dividing walls and annexe weir in the stated position has on the
comprehensive physical model testing been found to be effective in achieving
the desired objectives and their indicated precise layout is as optimized on the
model by the Irrigation Research Institute at Nandipur (Figure-12).
H. Removal of Pitched Island
5.21 With the provision of 3 dividing walls as proposed in para 5.20, the existence
of Pitched Island Shank (originally 1,300 ft long and a round semi circular
mole head which got punctured during the floods of 1988 and is now in a
straight length of about 900 ft) will become redundant and would need
removal. By doing so the 2 blocked bays of the barrage will become clear to
take their share of discharge. Its semi circular stone pitched mole head nose
of 400 ft diameter in the proposed scheme of work is likely to create shoaling
at its back too close to the weir (as also indicated on the model). The nose
part of the pitched island which has already lost its identity during flood
damages of over last 17 years would thus require demolition by salvaging its
stone to the extent feasible.
188 Chohan
6. BARRAGE SAFETY
6.1 Soundness of Structure and Substrata
To evaluate the present condition of the structure and sub-surface strata,
non-destructive testing techniques as well as other field and laboratory tests
were got carried out by Central Materials Testing Laboratory (CMTL)
WAPDA as listed below:
(a) Seismic Refraction: The system determines the compressional wave
velocities of the materials from the surface to a specified depth. In this
technique seismic (sound) velocities are generated and their arrival
time through geophones is recorded via sensors and cables to the
seismic recorder. The seismogram data is then transferred to the
computer where it is deciphered on a special software to compute
velocities of different layers. On the basis of velocities, the
interpretation of each layer is made to differentiate between
satisfactory and grey areas.
(b) Electrical Resistivity: This system is based on the measurement of
vertical changes in the electrical properties of the surface & sub-
surface materials. The equipment consists of a current transmitter, a
receiver to measure the resultant potential and a set of current and
potential electrodes. The results are then analysed on a computer
programme to ascertain quality of various strata.
(c) Conventional Gravity: This is a geophysical method that measures
minute changes in the force of earth gravity. The equipment measures
gravity changes of the underlying geological structure to understand
the ground beneath and detecting underground cavities.
Some of the non-destructive tests indicated above were made at a number of
locations on the downstream side of the barrage floor. These tests are
indicative in nature, but their results are supportive of each other to justify
reliance on the derived conclusions. These tests have revealed:
(i) The stone masonry and concrete of floor to be intact at all locations
except some weakness in bay No. 9 which might be due to opened up
joints visible in the upper layer of the stone masonry.
(ii) The sub-strata are uniform in character with no evidence of cavities,
voids, runnels or segregation.
(d) Concrete Core: Samples were extracted at 5 locations and their
compressive strength varied from 4000 to 7000 lbs per square inch
which is more than the expected limit.
(e) PUNDIT & Schmidt Hammer Tests: The result of 12 tests showed a
uniform stone/concrete mass without cracks/ voids or segregation and
strength to be more than 4000 ft.
Pakistan Engineering Congress, 70th Annual Session Proceedings 189
6.2.3 The minimum downstream water level at present remains about 2.0 ft. above
the barrage floor end. The retrogressionary trend is very mild and in the
current situation it is not likely to aggravate to a situation of any alarm.
There is still a margin of 2 ft. to cater for any such eventuality for long time
to come. It is thus concluded that there is no cause of anxiety to the
structural stability of the barrage as far as the retrogressive/ accretionary
trends on the downstream of the barrage are concerned.
6.3 Exit Gradient
With nil flow condition below i.e. with minimum water at R.L. 615.5 or dry
floor downstream which may be case in future times and ponded condition
upto RL 635.0 on the upstream, the barrage in its present form is safe
against exit gradient as its value remains within the safety factor of 7
normally taken for fine sand sub-strata.
6.4 Uplift Pressures and Floor Thickness Downstream
The floor thicknesses of the existing structure are safe upto upstream ponded
water at R.L. 634.0 with nil flow or dry floor condition downstream. With
pond level raised to R.L. 634.5 the middle portion of downstream floor is
deficient in thickness by a meager value of 3 inches while at RL 635.0, this
shortfall increases to 6 inches only which is not of much significance.
Thickening of floor for added safety if resorted to would make the
downstream slope more flat and crest part wider. In this position, the
formation of hydraulic jump tends to shift much lower down and turbulent
flow of severe nature goes beyond the limit of pucca floor to damage the loose
protection works, as also tested on the model. The idea of thickening the
downstream floor thus gets totally ruled out. It is therefore concluded that in
a given situation, normal operative upstream pond for canals operation
should not be raised above RL 634.0 so that at no stage the head across the
barrage get exceeded beyond a limit of 634.0 615.5 = 18.5 ft. With some
leakage of water from the barrage gates, the pond level can however be raised
upto RL 635.0 by keeping a watch that the head across the structure does not
exceed the limit of 18.5 ft.
6.5 Floor Length Downstream
To aim at formation of hydraulic jump and proper dissipation of energy,
adequate length of downstream floor is required to be provided. The structure
is presently designed to pass a flood discharge of 2.25 Lac cusecs with
upstream HFL 638.0 and downstream HFL 635.0 (i.e. by modular operation).
If the structure is made to pass a higher discharge of 2.57 Lac cusecs as
derived theoretically and also confirmed by the model studies corresponding
to raised HFL 639.0 and downstream flood water at R.L. 637.0 (discussed in
para-5.A) the intensity of flow per foot run across the weir crest comes to 184
cusec. Analysis show that the available length of floor beyond the range of
hydraulic jump formation is adequate and no extension of floor is required on
that account.
Pakistan Engineering Congress, 70th Annual Session Proceedings 191
7. CANAL CAPACITIES
7.1 Two canals take off on left side of Barrage. Lower Bari Doab Canal is being
remodeled to take a discharge of 9841 cusecs which can be drawn from its
Head Regulator by maintaining the existing pond of R.L. 633.0 at the
barrage. The head regulator has ample waterway and to meet even any
future enhancement of discharge for withdrawal upto 12,500 cusecs raising of
the pond to R.L. 634.0 is only needed. This level retains modular operation of
the head regulator as water level then required in the canal would be about
R.L. 632.5. These withdrawals are feasible without impairing the structural
stability of the head regulator or the barrage weir.
7.2 Balloki Sulemanki Link is presently designed for a discharge of 22,000 cusecs
and it is in the process of remodeling to take enhanced flow of 24,500 cusecs.
The existing discharge can be handled by maintaining a pond of R.L. 634.0,
but for a higher discharge of 24,500 cusecs, pond at R.L. 634.7 will be
required.
7.3 The demand of water for canals off-taking directly from the link canal and
those at Sulemanki Headworks is mounting every day. If a very modest
flexibility of 10% is incorporated in the discharging capability of the Head
Regulator, the structure is required to be made fit for passing a discharge of
27000 cusecs. For this quantum a pond R.L. 635.4 is required to be
maintained. With breast wall bottom of the head regulator at R.L. 633.0,
water level in the canal is not to exceed RL 632.5 to maintain modular under
short flow which corresponds to a canal discharge of 28,000 cusecs. For
passing this discharge pond R.L. 635.7 would require to be maintained.
Further attempt to push more discharge into the link canal by any means or
through any alternate source will make the canal water to rise to a situation
of submerging the gate openings with consequential effect of reducing its
discharge co-efficient. It is thus concluded that to draw a discharge of more
than 22,000 cusecs from the existing head regulator, a pond higher than R.L.
634.0 will have to be maintained which has serious implication of barrage
safety against excessive uplift pressures (para 6.4) as well as causing large
scale submergence of private lands beyond the pond area acquired limits
(Figure-16).
7.4 Regarding inundation of the upstream area, limiting pond level position
occurs at R.L. 634.5 under a situation of low flow in the river or nil release
lower down the barrage. At higher river flows with somewhat steeper water
slope, inundation effect will be more pronounced indicating desirability of not
exceeding the pond R.L. 634.0 from canals operation viewpoint. For forming a
higher pond upto R.L. 635.5, the backwater effect would travel much
upwards and cause submergence in the privately owned area of about 1100
acres (Table-2 & Figure-16). This area comprises developed cultivated land
and has numerous hutments in the riverian belt. Acquisition of this area
would pose socio-political/ environmental problems apart from being cost
Pakistan Engineering Congress, 70th Annual Session Proceedings 193
intensive. It is thus not advisable that the pond level on upstream of the
barrage from canals operation view be allowed to exceed R.L. 634.0.
7.5 New 2nd B.S. Link Head Regulator
By limiting the pond level at R.L 634.0, a discharge of 22,000 cusecs can be
passed through the existing B.S. Link Head Regulator under free flow
condition i.e. without submergence of gates or its breast wall bottom.
Alternative arrangement to push the additional discharge are therefore
required to be devised. For this purpose a Second Head Regulator of 8 bays
matching with the existing structure i.e. crest R.L. 624.84, breast wall bottom
R.L. 633.0 and 24 ft clear width of each bay will require to be constructed.
This arrangement with canal water at RL 632.5 below the structure will
withdraw discharge of 28,000 cusecs through the two head regulators
working non modularly at Pond R.L. 634.0 i.e. getting a flexibility of 14% over
and above the presently planned withdrawal of 24,500 cusecs. If by
remodelling the link canal, its water level at head can be lowered to a stage of
regulators working modularly, the two head regulators would be capable of
delivering much higher discharge to meet all time future needs of the
dependent canal systems.
The second head regulator being a new construction should be constructed
matching with proposed new environments i.e. high flood limit on upstream
of barrage raised from R.L. 638.0 to R.L. 639.0. This head regulator is
planned to be located alongside the existing regulator and at a minimum
distance from it by keeping in view that its operational capability is not
hampered during construction stage. It is also planned to be located at an
angle of 11 with the existing structure for achieving better upstream water
approach condition and also for smooth flow of the road traffic on its deck.
This arrangement has been tested on model and found to be smoothy
workable. Relative location of the new head regulator and its typical section
are shown at Figure-12 and Figure-17 & 18.
7.6 Existing B.S. Link Head Regulator
The existing regulator is safe against exit gradient for pond RL 634.5 while
the crest and glacis parts are short in thickness by about 1.5 ft. To make the
existing head regulator safe against exit gradient corresponding to higher
HFL 639.0 and nil flow in the link canal, a deeper end cut off is required
which will be possible by providing a row of sheet pile line in the proposed
downstream extension portion of the existing floor. The deficiency of
downstream floor thickness at that level can be overcome by constructing a
4.0 ft. high baffle wall above the newly placed end pile line for maintaining a
matching depth of water over the floor. The deficiency in floor thickness of
over 3 ft at crest and glacis can be met with by extensive grouting the sub-
strata of this part with cement to create a thick cement sand mass and
anchoring the same suitably with the existing floor. This part is resting
between the deep foundation of the bridge/ overhead deck of the regulator
194 Chohan
gates and it is hoped that a confined zone of cement grout in between will
make the sub-strata solid enough in a desirable depth for safety against the
effect of uplift pressure there. The proposed modification of the existing head
regulator and the cross-section of the structure are shown on Figure-17 & 18.
8.0 RIVER TRAINING WORKS
8.1 General
The behaviour of river Ravi is characteristics of making sharp loops which
quite often cannot be anticipated much in advance. This phenomenon brings
under attack the abadies enroute at short notice. Consequently a large
number of river training works in the form of spurs have been constructed all
along the river course from its entry point from India at Nainankot to
Sidhnai. This trend has been creating problems close to the headworks also.
To ward off attack at the marginal bunds and for having favourable river
approach towards the barrage, a large number of spurs have therefore been
put on ground as shown at Figure-1.
8.2 Dividing Walls
Something is required to be done to make the right side of the barrage fully
operational by controlling the tendency of shoal formation in the immediate
vicinity of the structure. For this purpose, model studies were got conducted
at Nandipur Research Station which supported the idea of constructing three
Dividing Walls; two of them 469 ft long in line with barrage piers No. 23 and
29 and the third 869 ft in length at pier No. 17 as discussed in para-5.20 and
shown at Figure-12. With this provision, the existence of Pitched Island
becomes redundant and would need removal as also indicated by model
studies and discussed in para 5.21.
8.3 Spurs
The prevailing river position do not warrant construction of any additional
spur at the present. The provision of Annexe Weir on the right side of the
barrage for passage of additional flood discharge across the structure (as
discussed under para-5.8) however, places the nose of Spur No. 10 in direct
passage of the river flow towards the Annexe. This nose will require removal
and constructed in a retarded position as shown at Figure-7, if the need for
constructing the Annexe Weir crystallizes at any stage. If the proposal of
providing spillway of adequate capacity as discussed at para 5.15 is
implemented, the nose of spur No. 10 will stay in position as existing at
present.
8.4 Bunds Strengthening
The training works on the upstream side of the barrage were repaired in the
recent past and strengthened corresponding to flood heights generated by the
historic flood of the year 1988, when the designed HFL 638.0 on the upstream
of the barrage had been attained. With the proposal to raise HFL limit by one
foot to RL 639.0 at the barrage and escapage of surplus floodwater through
Pakistan Engineering Congress, 70th Annual Session Proceedings 195
11. ACKNOWLEDGEMENTS
Pakistan Engineering Congress, 70th Annual Session Proceedings 197
The author expresses his deep gratitude to Mr. Muhammad Akhtar Rana
Ex Secretary I&P Deptt; Mr. Ahsan Hassan Zaidi Ex Chief Engineer I&P
Deptt and Mr. Muhammad Ashraf Khokhar Ex Superintending Engineer
I&P Deptt for their candid help in technical dialogues. Thanks are due to Mr.
Javaid Iqbal Awan, Senior Mechanical Engineer; Mr. Muhammad Aslam
Bhatti, Principal Geo-Tech Engineer; and Mr. Shakil Ahmad, Senior
Hydrologist of ACE in providing guidance of their fields. The author is highly
appreciative of the support given by Central Monitoring Testing Laboratory
(CMTL) WAPDA and Irrigation Research Institute (IRI) Lahore for
conducting tests of great value. Above all author is grateful to Mr.
Muhammad Fiaz Khan, CAD Operator of ACE for his willing help in
preparing the sketch drawings and type work.
198 Chohan
Table 1: Annual Peak Discharges of River Ravi below Balloki Headworks (Data Year 1922 to Year
2003)
Discharge Total Discharge Total Discharge Total
Breaches/ Annual Breaches/ Annual Breaches/ Annual
Year Year Year
Barrage Canals Peak Barrage Canals Peak Barrage Canals Peak
(Estimated) Discharge (Estimated) Discharge (Estimated) Discharge
1922 45,354 45,354 1950 225,540 50,000 275,540 1978 91,536 91,536
1923 60,180 60,180 1951 52,190 52,190 1979 81,720 81,720
1924 61,300 61,300 1952 61,370 61,370 1980 153,810 153,810
1925 96,155 96,155 1953 87,000 87,000 1981 93,698 93,698
1926 64,476 64,476 1954 175,000 175,000 1982 42,815 42,815
1927 49,137 49,137 1955 144,360 60,000 204,360 1983 65,182 65,182
1928 71,000 71,000 1956 74,774 74,774 1984 53,368 53,368
1929 41,500 41,500 1957 168,700 168,700 1985 75,586 75,586
1930 39,150 39,150 1958 116,339 116,339 1986 54,590 54,590
1931 51,935 51,935 1959 133,516 133,516 1987 14,135 14,135
1932 44,280 44,280 1960 38,515 38,515 1988 240,845 148,500 389,345
1933 37,310 37,310 1961 100,912 100,912 1989 114,070 114,070
1934 76,279 76,279 1962 118,180 118,180 1990 73,900 73,900
1935 150,707 150,707 1963 41,831 41,831 1991 68,190 68,190
1936 128,100 128,100 1964 83,000 83,000 1992 102,157 102,157
1937 60,260 60,260 1965 35,985 35,985 1993 119,792 119,792
1938 35,565 35,565 1966 131,000 131,000 1994 95,335 95,335
1939 38,163 38,163 1967 131,801 131,801 1995 222,800 222,800
1940 51,913 51,913 1968 76,265 76,265 1996 220,000 220,000
1941 38,162 38,162 1969 57,230 57,230 1997 156,950 156,950
1942 133,000 133,000 1970 46,360 46,360 1998 68,470 68,470
1943 36,500 36,500 1971 104,200 104,200 1999 43,980 43,980
1944 53,300 53,300 1972 40,730 40,730 2000 46,530 46,530
1945 61,000 61,000 1973 183,000 115,000 298,000 2001 76,240 76,240
1946 61,000 61,000 1974 46,360 46,360 2002 57,710 57,710
1947 153,820 153,820 1975 180,208 180,208 2003 44,700 44,700
1948 100,840 100,840 1976 234,474 21,500 255,974 2004 40,425 40,425
Pakistan Engineering Congress, 70th Annual Session Proceedings 199
17,500 637.0
634.81 636.31 36.81 37.81 Private Cultivated
22,500 638.0 Area Requiring
Acquisition
22,500 638.0
635.25 636.75 37.25 38.25 No
27,500 639.0 Private
Inundation No
Cultivated
27,500 639.0 Inundation
Area
636.08 637.58 38.08 39.08 No Inundation
32,500 640.0
32,500 640.0
636.91 638.41 38.91 39.91
37,500 642.0
Figure 4
BALLOKI BARRAGE