Está en la página 1de 3

CALCULO DE FLETE

PROYECTO: MANTENIMIENTO DEL SISTEMA DE DESAGUE EN EL CASERIO DE GONTZAJIRCA, DISTRITO DE


SAN LUIS, PROVINCIA DE CARLOS FERMIN FITZCARRALD - ANCASH

1) DATOS GENERALES DE CARGA


A) POR PESO

Descripcin Und. Cantidad Peso Unitario (kg) Peso Parcial (kg)

LUBRICANTE PARA TUBERIA PVC UF gal 0 3.50 0.00


ALAMBRE NEGRO RECOCIDO # 16 kg 39 1.00 39.00
ALAMBRE NEGRO RECOCIDO # 8 kg 0 1.00 0.00
CLAVOS PARA MADERA CON CABEZA DE 3" kg 23 1.00 23.00
CLAVOS PARA MADERA CON CABEZA DE 4" kg 0 1.00 0.00
CLAVOS PARA MADERA SIN CABEZA DE 3" kg 15 1.00 15.00
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 1259.7 1.00 1,259.70
ARENA FINA m3 0 0.00 0.00
PIEDRA CHANCADA DE 1/2" (PUESTO EN OBRA) m3 0 0.00 0.00
ARENA GRUESA m3 0 0.00 0.00
PIEDRA ZARANDEADA DE 1/2" A 3/4" m3 0 0.00 0.00
MATERIAL SELECIONADO PARA CAMA DE APOYO m3 0 0.00 0.00
CEMENTO PORTLAND TIPO I (42.5 kg) bls 318 42.50 13,515.00
ACCESORIOS DIVERSOS u 2500 1.00 2,500.00
PEGAMENTO PARA PVC AGUA FORDUIT gal 5 3.50 17.50
TAPA DE CONCRETO ARMADO PARA BUZON D=0.60M u 0 30.00 0.00
FLETE TERRESTRE glb 1 0.00 0.00
FLETE RURAL glb 1 0.00 0.00
MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTA glb 1 0.00 0.00
HORMIGON (PUESTO EN OBRA) m3 0 0.00 0.00
AGUA m3 0 0.00 0.00
CARTEL DE OBRA PREFABRICADO DE 3.60 X 2.40M u 1 10.00 10.00
MADERA TORNILLO p2 0 1.50 0.00
MADERA TORNILLO 2" X 3" X 10' u 0 5.00 0.00
MADERA EUCALIPTO ROLLIZO 4" X 4 m u 0 5.00 0.00
MADERA EUCALIPTO ROLLIZO 3" X 2.50 m u 0 7.00 0.00
ESTACA DE MADERA EUCALIPTO u 0 0.30 0.00
MADERA TORNILLO INCLUYE CORTE PARA ENCOFRADO p2 0 1.50 0.00
TAPA CON MARCO FIERRO FUNDIDO DE DESAGUE 12" X 24" pza 0 10.00 0.00
PETROLEO gal 0 3.50 0.00
PINTURA ESMALTE gal 0 3.50 0.00
CALAMINA 1.20 X 2.40 m u 0 5.00 0.00
CACHIMBA DE 45 PVC 110mmx110mm UF u 0 1.00 0.00
CACHIMBA DE 45 PVC 110mmx160mm UF u 0 1.00 0.00
ANILLO DE JEBE DE 110MM u 0 0.20 0.00
ANILLO DE JEBE DE 160MM u 0 0.20 0.00
TUBERIA PVC- ISO 4435, UF 110mm S-25 (INC. ANILLO) m 0 0.00 0.00
TUBERIA PVC- ISO 4435, UF 160mm S-25 (INCLUYE ANILLO) m 0 0.00 0.00
TOTAL 17,379.20
B) TUBERIA POR VOLUMEN

Descripcin Und. Cantidad Cap (U/Viaje) N Viajes

TUBERIA PVC- ISO 4435, UF 160mm S-25 (INCLUYE ANILLO) m 1,269.0000 250 0.8460
TUBERIA PVC- ISO 4435, UF 110mm S-25 (INC. ANILLO) m 346.0000 200 0.2883
NUMERO TOTAL DE VIAJES 2.00

2) FLETE TERRESTRE

Descripcin Und. Cantidad P. U. (S/.) Cap (U/Viaje)

MATERIALES kg 17,379.20 0.22 3,823.42


AGREGADOS M3 0.0000 0.00 0.00
TUBOS Viaje 1.00 1,500.00 1,500.00
TOTAL 5,323.42

3) FLETE RURAL

Descripcin Und. Cantidad P. U. (S/.) PARCIAL


CEMENTO PORTLAND TIPO I (42.5KG) BOL 0.0000 5.00 0.00
MATERIALES SIN CEMENTO kg 0.00 0.50 0.00
AGREGADOS Lata (*) 0.00 2.00 0.00
TUBOS und 0.00 1.00 0.00
TOTAL 0.00

4) RESUMEN DEL FLETE

Descripcin Monto (S/.) Monto sin IGV (S/.

FLETE RURAL 0.00 0.00


FLETE TERRESTRE 5,323.42 4,511.38
TOTAL 5,323.42 4,511.38