CALCULO DE ESTRUCTURAL RESERVORIO APOYADO 20M3

DATOS "CREACION DE LOS SERVICIOS DE INNOVACION TECNOLGICA EN ACUICULTURA EN PUERTO OCOPA, DISTRITO DE RIO TAMBO,
PROVINCIA DE SATIPO, REGION JUNIN"
UBICACIN: :PUERTO OCOPA ACERO MUROS
EXPEDIENTE : .. ACERO VERTICAL = 3/8 Pulg.
DIAMETRO = 0.953 Cms.
AREA = 0.713 Cms2.
FECHA : 29-Aug-17 PESO = 0.560 Kg/ml
ACERO HORIZONTAL = 3/8 Pulg.
DIAMETRO = 0.953 Cms.
CARACTERISTICAS GEOMETRICAS AREA = 0.713 Cms2.
VOLUMEN RESERVORIO = 20.00 m3 PESO = 0.560 Kg/ml

ALTURA UTIL RESERVORIO = 1.70 mts.


LADO UTIL RESERVORIO = 3.45 mts. ACERO LOSA DE TECHO
ESPECIFICACIONES ACERO HORIZONTAL = 3/8 Pulg.
CONCRETO f'c = 210 Kg/cm2 DIAMETRO = 0.953 Cms.
SOBRECARGA EN LOSA = 150 Kg/m2 AREA = 0.713 Cms2.
ACERO fy = 4,200 Kg/cm2 PESO = 0.560 Kg/ml
RESISTENCIA DEL SUELO = 1.00 Kg/cm2 ACERO LOSA DE FONDO
COEF. SISMICO = 0.12 ACERO HORIZONTAL = 3/8 Pulg.
RECUBRIMIENTO r = = 4.00 Cm DIAMETRO = 0.953 Cms.
fs = 2,100 Kg/cm2 AREA = 0.713 Cms2.
fc = 94.5 Kg/cm2 PESO = 0.560 Kg/ml

0.20 0.20 1.73

2.13

2.13

Sc Wc
SL
A' B'

WL NIVEL DE AGUA

S1

Ea

2.43 2.37 W1 0.567

1.30 Wa

A B

S2

0.15
C D

W2

0.30

1.07

1.27
LCULO DE ESTRUCTURAL RESERVORIO APOYADO 20M3

RVICIOS DE INNOVACION TECNOLGICA EN ACUICULTURA EN PUERTO OCOPA, DISTRITO DE RIO TAMBO,


PROVINCIA DE SATIPO, REGION JUNIN"

0.13

0.30
NIVEL DE AGUA

1.70

0.30
CALCULOS

W1= Pc x V1 960.00 Kg
W2 = Pc x V2 1533.60 Kg
Wa = Pa x Va 2941.00 Kg
WL = Pc x VL 602.16 Kg
Ws = Sc x A 289.50 Kg
S1 = 0,12 x W1 172.80 Kg
S2 = 0,12 x W2 276.05 Kg
SL = 0,12 x WL 108.39 Kg
Ss = 0,12 x Ws 62.53 Kg
Ea = 1,12 x 0,5 x Pa x H12 2427.60 Kg

VERIFICACION DEL ESFUERZO CORTANTE EN LA BASE AB

V = Fh / A 1.39 Kg/cm2

Vc = 0,29 ( f'c )^1/2 4.20 Kg/cm2

V= 1.39 Kg/cm2 < Vc = 4.20 Kg/cm2 BIEN !!

CALCULO DE LA ARMADURA

ACERO VERTICAL CARA B'-B

MOMENTO MAXIMO EN LA BASE A-B

Mu 1905.46 Kg-mts.
d = t1 - r - D/2 15.52 Cms.

AREA DE ACERO
As1 = 128.62 Cms2
As2 = 3.33 Cms2 SE ASUME : 3.33 Cms2

CUANTIA = As / t1 x b 0.00167

CUANTIA MINIMA POR FLEXION 0.0012 < 0.0017 BIEN!!

USAR : 1 3/8 @ 0.22 mts.

ACERO HORIZONTAL B'B

ASUMIR CUANTIA MINIMA PARA EL ACERO HORIZONTAL, CONSIDERANDO P = 0,0018

As = P x b x t1 3.60 Cms2

USAR : 1 3/8 @ 0.20 mts.

ACERO EN LA ZAPATA

ASUMIR EL AREA DE ACERO HALLADA PARA LA BASE DE MURO

USAR : 1 3/8 @ 0.22 mts.

ACERO EN LA LOSA DE FONDO

P1 6973.0128
P2 11116.8
P3 9964.80
P4 19599.41
P5 30527.58

LUEGO: WuD : 5247.23


WuL : 270.00

Wu : 5517.23
CALCULO DEL MOMENTO ULTIMO

Mu = 0,0513 * Wu * L2 4217.09 Kg--mts


d = t1 - r - D/2 25.52 Cms.
AREA DE ACERO
As1 = 212.49 Cms2
As2 = 4.46 Cms2 SE ASUME : 4.46 Cms2

CUANTIA = As / t1 x b 0.001488

CUANTIA MINIMA POR FLEXION 0.0012 < 0.0015 BIEN!!

USAR : 1 3/8 @ 0.16 mts.

ACERO EN LA LOSA DE TECHO

WuD = 2400 * t1 * 1,5 468


WuL = SC * 1,8 270
Wu = 738

CALCULO DEL MOMENTO ULTIMO

Mu = 0,0479 * Wu * L2 423.20 Kg--mts


d = t1 - r - D/2 8.72 Cms.
AREA DE ACERO
As1 = 72.81 Cms2
As2 = 1.31 Cms2 SE ASUME : 1.31 Cms2

CUANTIA = As / t1 x b 0.001005

CUANTIA MINIMA POR FLEXION 0.0012 > 0.0010 MAL!! SE ASUME CUANTIA MINIMA P= 0.0012

As = P * t1 * b 1.56 Cms2

USAR : 1 3/8 @ 0.25 mts


4.25

0.15 0.30

0.20 0.15

0.20

2.13

0.15

3.45

ESCALINES FG
VER DETALLE
DETALLE DE ESCALINES

BUZON 0,60 x 0,60 Mts.


TAPA SANITARIA METALICA

ESPECIFICACIONES TECNICAS
0.20 RESISTENCIA DEL CONCRETO f'c = 210

FLUENCIA DEL ACERO fy = 4200

0.20 TRASLAPE MINIMO DE VARILLAS = 30

0.20 0.20 3.45 0.20 0.20


TUB. FG 3/4"
@ 0,30 Mts.

UNIONES
ELECTROSOLDADAS

ESPECIFICACIONES TECNICAS
Kg/cm2

Kg/cm2

cm
TAPA SANITARIA METALICA 3/8 @ 0.25 TUBERIA DE VENTILACION FG 2"
0,60 x 0,60 mts.

0.13



0.30

NIVEL DE AGUA

3/8 @ 0.22

3/8 @ 0.20 TARRAJEO C / IMPERMEABILIZANTE 2.00


1.70

3/8 @ 0.22


3/8 @ 0.16 PENDIENTE DE FONDO 1%

3/8 @ 0.22



0.30


0.200

1.15 SOLADO DE CONCRETO

0.20 0.20 3.45 0.20 0.20

RESERVORIO APOYADO
RESERVORIO APOYADO 20 M3
3/8 @ 0.25

3.85

2 3/8

ESPECIFICACIONES TECNICAS
RESISTENCIA DEL CONCRETO f'c

FLUENCIA DEL ACERO fy

TRASLAPE MINIMO DE VARILLAS

3.85

RESERVORIO APOYADO
ESPECIFICACIONES TECNICAS
= 210 Kg/cm2

= 4200 Kg/cm2

= 30 cm

RESERVORIO APOYADO 20 M3
HOJA DE METRADOS DE RESERVORIO

CAPACIDAD :

"CREACION DE LOS SERVICIOS DE INNOVACION TECNOLGICA EN ACUICULTURA EN PUERTO OCOPA, DISTRITO DE RIO TAMBO, PROVINCIA DE SATI
PROYEC.:
REGION JUNIN"
FECHA:
PARTIDA DESCRIPCION VECES LONG. ANCHO ALTURA SUB-TOTAL
9.00 RESERVORIO 20.00 M3
9.01 TRAZO Y REPLANTEO 1.00 4.25 4.25 18.06
9.02 EXCAVACION MANUAL 1.00 4.25 4.25 0.80 14.45
9.03 SOLADO DE CONCRETO E= 0.05 Mts. 1.00 4.25 4.25 18.06
9.04 CONCRETO F'C= 175 KG/CM2 1.00 4.25 4.25 0.30 5.42
2.00 3.85 0.20 2.00 3.08
2.00 3.45 0.20 2.00 2.76
1.00 3.85 3.85 0.13 1.93
9.05 CONFOR. DE PENDIENTE DE FONDO C F'C= 175 KG/CM2 1.00 3.45 3.45 11.90
9.06 ENCOFRADO Y DESENCOFRADO 4.00 3.85 2.13 32.80
4.00 3.45 2.00 27.60
1.00 3.45 3.45 11.90
9.07 ACERO FY= 4,200 KG/CM2 1.00 278.75 278.75
9.08 ESCALINES DE FIERRO GALVANIZADO 2.00 2.73 5.46
6.00 0.30 1.80
9.09 TARRAJEO INTERIOR CON IMPERMEABILIZANTE 4.00 3.45 2.00 27.60
1.00 3.45 3.45 11.90
9.10 TARRAJEO EXTERIOR MEZCLA 1:5 4.00 3.85 2.13 32.80
1.00 3.85 3.85 14.82
9.11 TAPA SANITARIA METALICA 0,60 x 0,60 Mts. 1.00 1.00
9.12 TUBERIA DE VENTILACION FG D= 2" 1.00 1.00
9.13 PRUEBA HIDRAULICA Y DESINFEC. RESERVORIO 1.00 1.00
9.14 SUMINISTRO Y COLOCACION DE HIPOCLORADOR 1.00 1.00
9.15 PINTADO DE MUROS EXTERIORES 4.00 3.85 2.13 32.80
1.00 3.85 3.85 14.82
9.16 JUNTA WATER STOP 1.00 15.40 15.40

10.00 CAMARA DE VALVULAS


10.01 TRAZO Y REPLANTEO 1.00 1.50 1.25 1.88
10.02 EXCAVACION MANUAL 1.00 1.50 1.25 0.80 1.50
10.03 CONCRETO F'C= 175 KG/CM2 1.00 1.50 1.25 0.10 0.19
2.00 1.00 0.15 1.10 0.33
1.00 1.30 0.15 1.10 0.21
1.00 1.30 1.15 0.10 0.15
10.04 ENCOFRADO Y DESENCOFRADO 3.00 1.00 1.10 3.30
2.00 1.15 1.10 2.53
1.00 1.30 1.10 1.43
1.00 1.00 1.00 1.00
10.05 ACERO FY= 4,200 KG/CM2 0.00
FIERRO CORRUGADO D= 3/8" 16.00 1.45 0.56 12.99
6.50 1.55 0.56 5.64
10.00 1.55 0.56 8.68
6.00 4.05 0.56 13.61
13.00 1.50 0.56 10.92
10.06 TARRAJEO EXTERIOR MEZCLA 1:5 2.00 1.15 1.15 2.65
1.00 1.30 1.15 1.50
1.00 1.30 1.30 1.69
10.07 TAPA METALICA 1.00 1.00
10.08 SUMINISTRO DE ACCESORIOS
VALVULAS COMPUERTA D =1" 3.00 3.00
VALVULAS COMPUERTA D =2" 1.00 1.00
TRANSICION PVC-SAP D=1" 7.00 7.00
TRANSICION PVC-SAP D= 2" 2.00 2.00
UNION UNIVERSAL FG D= 1" 6.00 6.00
UNION UNIVERSAL FG D= 2" 2.00 2.00
NIPLE FG D= 1" x 4" 6.00 6.00
CODO PVC-SAP D= 2" x 90 2.00 2.00
CODO PVC-SAP D= 1" x 90 1.00 1.00
TEE PVC-SAP D= 2" x 90 1.00 1.00
TEE PVC-SAP D= 1" x 90 2.00 2.00
CANASTILLA DE BRONCE D= 1" 1.00 1.00
UNION PVC-SAP D= 1" 1.00 1.00
CONO DE REBOSE DE 6" a 2" 1.00 1.00
TUBERIA PVC-SAP D=1" 1.00 5.00 5.00
TUBERIA PVC-SAP D= 2" 1.00 5.00 5.00
10.09 PINTADO DE MUROS EXTERIORES 3.00 1.10 1.00 3.30
11.00 TRABAJOS DE PROTECCION DE RESERVORIO
11.06 CERCO PERIMETRICO C/DADOS C Y ALAMBRE PUAS 1.00 165.00 165.00
20 M3

DE RIO TAMBO, PROVINCIA DE SATIPO,

8/29/2017
TOTAL UNID.

18.06 m2
14.45 m3
18.06 m2
13.19 m3
m3
m3
m3
11.90 m2
72.30 m2
m2
m2
278.75 kg
7.26 ml

39.50 m2
m2
47.62 m2
m2
1.00 unid
1.00 unid
1.00 glb
1.00 unid
47.62 m2

15.40 ml

1.88 m2
1.50 m3
0.88 m3
m3
m3
m3
8.26 m2
m2
m2
m2
51.84 kg
kg
kg
kg
kg
kg
5.83 m2
m2
m2
1.00 unid

3.00 unid
1.00 unid
7.00 unid
2.00 unid
6.00 unid
2.00 unid
6.00 unid
2.00 unid
1.00 unid
1.00 unid
2.00 unid
1.00 unid
1.00 unid
1.00 unid
5.00 ml
5.00 ml
3.30 m2
165.00 ml
VOLUMEN ALTURA LADO INTER VOLUMEN ASUMIDO
3.00 1.25 1.55 20.00 M3
4.00 1.25 1.80
5.00 1.25 2.00 ALTURA LADO
6.00 1.25 2.20 1.70 3.45
7.00 1.25 2.40
8.00 1.30 2.50
9.00 1.30 2.65
10.00 1.35 2.75
11.00 1.40 2.85
12.00 1.45 2.90
13.00 1.50 2.95
14.00 1.55 3.05
15.00 1.55 3.15
16.00 1.60 3.20
17.00 1.65 3.25
18.00 1.65 3.35
19.00 1.70 3.35
20.00 1.70 3.45
21.00 1.75 3.50
22.00 1.75 3.55
23.00 1.80 3.60
24.00 1.85 3.65
25.00 1.85 3.70
26.00 1.85 3.75
27.00 1.90 3.80
28.00 1.90 3.85
29.00 1.95 3.90
30.00 1.95 3.95
31.00 2.00 3.95
32.00 2.00 4.00
33.00 2.05 4.05
34.00 2.05 4.10
35.00 2.05 4.15
36.00 2.10 4.15
37.00 2.10 4.20
38.00 2.15 4.25
39.00 2.15 4.30
40.00 2.15 4.35
41.00 2.20 4.35
42.00 2.20 4.40
43.00 2.20 4.45
44.00 2.25 4.45
45.00 2.25 4.50
46.00 2.25 4.55
47.00 2.30 4.55
48.00 2.30 4.60
49.00 2.30 4.65
50.00 2.35 4.65
51.00 2.35 4.70
52.00 2.45 4.65
53.00 2.40 4.70
54.00 2.40 4.75
55.00 2.40 4.80
56.00 2.40 4.85
57.00 2.45 4.85
58.00 2.45 4.90
59.00 2.55 4.85
60.00 2.45 4.95
PLANILLA DE ARMADURA DE RESERVORIO DE 3 M3

ARMADURA LOSA DE TECHO LONGITUD VECES LONG. POR EN ML.

1/4" 3/8" 1/2" 5/8"


2.26

0.07 1/2 2.40 16.00 38.40

2.26

3/8 2.40 4.00 9.60

0.07

0.50

1/2 0.57 32.00 18.24


0.07

0.10 3/8 3.00 1.00 3.00


0.7

0.7

ARMADURA LOSA DE FONDO LONGITUD VECES 1/4" 3/8" 1/2" 5/8"

2.55

1/2 2.55 22.00 56.10

0.1

1/2 1.07 24.00 25.68

0.97

ARMADURA DE MURO LONGITUD VECES 1/4" 3/8" 1/2" 5/8"


0.05

1.75
1/2 2.00 32.00 64.00

0.20

0.15
2.20 1/2 9.10 7.00 63.70

2.20

PESO POR / ML. 0.25 0.58 1.02 1.55

LONG. TOTAL POR 0.00 12.60 266.12 0.00

RESUMEN GENERAL PESO TOTAL POR 0.00 7.31 271.44 0.00

NUMERO VARILLAS POR 1.00 30.00 0.00

PESO TOTAL 278.75 Kg