PARTE 1
A.1 ESTRUCTURACION
A.1.6 COLUMNAS
A.1.10 ESCALERA
B) PARTE 2
PREDIMENSIONAMIENTO DE VIGAS
b= B/20=6/20 = 0.3 m
vp =0.65*0.3m
PREDIMENSIONAMIENTO DE COLUMNAS
P. columna : 60 kg/m2
A= (6+6)/2*(5+8)/2=39m2
P=980*39 =38220 kg
b*D=5338.64 m 2
b=D=73 C 1 0.7x0.7
A=(5+8 )/2*(6)/2=19.5m2
P =980*19.5 =19110kg
b*D=3640 m 2
h=L/22 =7.3/22=0.33m
ZAPATA
Viga C =8-0.7=7.3m
Viga 3 =6-0.7=5.3 m
8 pisos h=3-0.25=2.75m
p. Acabado 6*8*100=4800kg
Pp viga 3=0.3*0.65*2400*5.3=2480.4kg
Suma =27472.3kg
s/c = 7.3*5.3*250=9672.5kg
PD=8*27472.32=219778.4kg
PL =8*9672.5kg=77380kg
Pc=PD+PL =219778.4kg+77380kg=297158.4kg