Programacion de Obra
Programacion de Obra
PROYECTO: MEJORAMIENTO DE VIAS URBANAS EN LAS AVENIDAS DE PUNO Y TACNA EN LA LOCALIDAD DE KELLUYO,
DISTRITO DE KELLUYO - CHUCUITO - PUNO
MADERA TORNILLO INCLUYE CORTE PARA ENCOFRADO p2 4245.71 4.50 19105.70 0.00 326.36 10200.00 8579.34 19105.70
FIERRO LISO m3 3864.50 4.20 16230.90 0.00 0.00 0.00 16230.90 16230.90
CEMENTO Bls 17715.84 24.00 425180.25 764.34 15775.54 135790.31 272850.06 425180.25
ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 2451.58 3.30 8090.21 4054.77 4035.44 0.00 0.00 8090.21
ARENA GRUESA m3 994.40 50.00 49720.20 234.51 7654.32 13637.02 28194.35 49720.20
PIEDRA ZARANDEADA m3 1090.75 50.00 54537.70 0.00 21708.34 21666.85 11162.50 54537.70
AGUA m3 1135.69 2.12 2406.12 0.00 1062.58 1062.18 281.37 2406.13
CLAVOS DE 3" Kg 339.99 4.50 1529.97 213.40 91.01 768.34 456.35 1529.10
TOTAL DE COSTO DIRECTO 142.62 576801.04 5267.02 50653.59 183124.70 337754.87 576801.04
0.91% 8.78% 31.75% 58.56%