Documentos de Académico
Documentos de Profesional
Documentos de Cultura
I O N A L
O F E S S T
SERIE
P R O P M E N
L
S
D E V E
SPONSORED BY
AIA Provider
No. 70118112
PROFESSIONAL DEVELOPMENT SERIES
change, then the results of the test could be altered decreased by approximately 49% at 120 degrees,
significantly. as compared to the laboratory-tested value.
The difference between laboratory conditions Corrugated polypropylene had similar results,
and field conditions can yield significantly differ- where the ring stiffness decreased by approxi-
ent results. For instance, the pipes to be tested per mately 46% at 120 degrees, compared to the
D2412 are to be conditioned in an environment with laboratory-tested value. The PVC pipe decreased
a temperature of 73 degrees Fahrenheit +/- 4 degrees by approximately 23%. Because steel has a signifi-
and tested in a laboratory at the same temperature. cantly higher melt temperature, as compared to
However, look at how the measured pipe stiffness of thermoplastic products, the corrugated steel pipe
various pipe types varies with temperature: only lost about 5.5% of its stiffness, and the steel-
As the chart below shows, pipes made with reinforced HDPE pipe was in between, with a loss
different materials react differently when tested of ring stiffness of about 18.4%. This is significant
at higher temperatures than those used in the given that pipe walls can reach 140 degrees or more
laboratory. The polyethylene pipes ring stiffness in the direct sun.
Development Series
Short- vs. Long-Term Deflections the soil mass around the pipe as well as the ring
For flexible pipes, short-term deflections are stiffness of the pipe itself. However, contribu-
largely induced during the installation process. tions in stiffness between the two elements
Flexible pipes can be deformed by a number of generally are far from equal. In flexible pipe
different activities during the installation process. design, the stiffness of the soil embankment
surrounding the pipe is far more important in
Pipe sections are typically bundled and shipped
controlling long-term deflections than the stiff-
over long distances to get to the jobsite. They then
ness of the pipe itself.
are lifted off the trucks and generally stored some-
To illustrate this, a widely accepted method-
where onsite, where they are commonly lifted and
ology for predicting long-term pipe deflections
handled several more times before they reach the
is the Iowa formula. The basis of the formula
location where they are to be placed.
is the fairly straightforward approach that pipe
Although normal lifting and handling doesnt
deflections could be estimated by the following
result in pipe deformations, due to the size and
mathematical approach:
power of the construction equipment used on
pipe installationsunintended deformations to
load on the pipe
the pipes can occur. In addition, after the pipes pipe deflection = X 100
pipe stiffness factor + soil stiffness factor
are placed in their final location, the backfill-
ing process begins. During this process, backfill
material is routinely dropped on top of the
A modified version of the Iowa formula was
largely unsupported pipes during the process.
developed by the U.S. Bureau of Reclamation.
The backfill then is typically shoveled and spread
This modified formula appears as follows:
into place so compaction can begin. Compaction
of backfill adjacent to and over pipes can result
Tf0.07h + 10WL
in significant loads that the pipe has to resist. Y(%) =
EI
+ 0.061FdE
Finally, even after the pipe is backfilled, it is r3
operate over the pipes before the final cover or Y(%) = percent vertical deflection
pavement is installed. It is routine that the loads Tf = time-lag factor, dimensionless
exerted by construction vehicles during site con- 0.07 = combination of conversion factors and bedding constant, square
feet per square inch ft2/in2 per linear inch (ft2/in2 per linear
struction exceed the loads the pipes experience inch)
during the rest of their service life. = backfill unit weight, pounds per cubic feet (lb/ft3)
The resistance to deflection during handling h = depth of cover, feet (feet)
WL = live load, pounds per square inch (lb/in2)
and installation is where the ring stiffness of E = modulus of soil reaction, lb/in2
the product plays the largest role in controlling Fd = design factor, dimansionless
pipe deflections. Until the pipe is supported by EI/r3 = pipe stiffness factor, lb/in2 per linear inch
the backfill envelope around it, the ring stiffness
of the pipe is the primary means for mitigating From the denominator of the equation, you
pipe deflections. can see that pipe stiffness is dictated primarily by
The other significant contributor to short-term the stiffness of the pipe wall (EI). The modulus
flexible pipe deflections is the consolidation of of elasticity (E) is dependent upon the material
the soil envelope directly around the pipe. Even that the pipe is produced from (HDPE, steel, etc.).
compacted backfill materials typically experience The moment of inertia (I) is dependent on the
some consolidation within the first few weeks pipe wall geometry. The soil stiffness is primarily
after construction. Flexible pipes simply reflect controlled by the modulus of soil reaction (E) of
this consolidation through pipe deflection. In the backfill that surrounds the pipe. This modulus
other words, if the soils directly adjacent to a describes how the soil responds under load. The
flexible pipe move either through elastic defor- higher the E value, the more support the soil
mation of the soil mass or consolidation of the provides to the pipe to resist deflection. A repre-
backfill, the pipe will mirror this movement by sentative range of E values for backfill materials
deflecting an equal amount. is shown in Figure 2.
Using this methodology, it is possible to cre-
ate a comparison of estimated long-term pipe
Influence of Pipe Stiffness on deflections for pipes with various pipe stiffnesses.
Long-Term Deflections Most flexible drainage pipe products have pipe
The resistance to long-term deflections in a stiffnesses between 5 and 75, generally varying by
flexible pipe is a function of both the stiffness of diameter and pipe material/construction. A
The chart in Figure 3 illustrates the comparison of long-term pipe deflections with varying pipe stiffnesses.
comparison of estimated long-term pipe deflections 90% or greater, even a much higher pipe-stiffness
based on a range of pipe-stiffness values is as shown pipe doesnt have a significant performance dif-
in the following chart: ference when it comes to controlling long-term
As the chart above illustrates (Figure 3), pipe deflections.
stiffness has greater impact on low-modulus soils
than it does on relatively high-modulus soils.
For a backfill material with a relatively moder-
AUTHOR
Darrell Sanders, P.E., is Chief Engineer for
ate modulus of 2,000 psi, even a 15x increase in
Contech Engineered Solutions. Darrell holds a B.S.
stiffness from 5 to 75 only increases the long-term
degree in Civil Engineering from the University
pipe deflection by approximately 1%. For a 36-inch
of Cincinnati and an M.B.A. from the University
diameter pipe, thats slightly less than 3/8 inch.
of Dayton and holds a Professional Engineering
Even for a very-low-modulus soil, a 3x increase in
license in several states. He also is a member of
pipe stiffness results in just more than the same
several industry committees, including NCSPA,
1% increase in pipe deflection.
AASHTO, ASTM and CSA. Darrell can be reached
Figure 3 shows that soil stiffness is the largest
at dsanders@conteches.com.
factor in controlling long-term pipe deflections. A
pipe with a pipe stiffness of 5 will perform simi-
larly to a pipe with a pipe stiffness of 75 in a sand REFERENCES
backfill if the density requirements are increased Fuerst, R.P., 2013. Method for Prediction of
from 90% to 95%. With the use of high-quality Flexible Pipe Deflection, U.S. Department of
fills, the influence of pipe stiffness is almost mean- the Interior Bureau of Reclamation, M-25 Second
ingless, because the difference in performance is Edition.
similar between all the pipes.
Pipe stiffness is a trait to consider when
selecting a flexible pipe. The pipe needs to have
enough stiffness to withstand the handling and
construction loads that it will be subjected to
during installation. In poorer grades of backfill,
it can have some impact on the long-term deflec-
tions of the installation. However, with the use of
quality backfill materials at compaction levels of
1) T rue or False: In a D2412 pipe stiffness test, a pipe is 6) T rue or False: The more support the soil provides, the
generally deflected to 95% of its original height. greater likelihood for pipe deflection.
A. True A. True
B. False B. False
2) T rue or False: Temperature has little to no impact on 7) T rue or False: Pipe stiffness has greater impact on
pipe stiffness. low-modulus soils than it does on relatively high-modulus
A. True soils.
B. False A. True
B. False
the following:
A. Moment of Inertia (I) 10) W
hen compaction levels of 90% or greater are achieved,
B. Modulus of Soil Reaction (E) is the performance of significant high pipe stiffness still
C. Stiffness of the Pipe Wall (EI)
a major factor in design?
D. Modulus of Elasticity (E)
A.
Yes
E. None of the above
B.
No
Superior drainage
and Storm Sewer
Products
CONTECH PROVIDES
INDUSTRY LEADING
PERFORMANCE.
www.ContechES.com/storm-sewer | 800-338-1122