PRESUPUESTO BASE VALORIZACION ANTERIOR

DESCRIPCION METRADO PARCIAL ACUMULADA


UNID. CANT. P.U. COSTO METRADO
PISTAS 1,281,175.10
OBRAS PROVISIONALES
CARTEL DE DE OBRA DE 7.20 x 6.00 M u 2.00 1,850.00 3,700.00 2.00
OFICINA, ALMACEN Y CASETA DE GUARDIANIA glb 1.00 2,067.07 2,067.07 1.00
TRABAJOS PRELIMINARES 0.00
ESMOVILIZACION DE EQUIPOS, MAQUINARIAS Y HERRAMIENTAS glb 1.00 4,000.00 4,000.00 1.00
TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 17,079.75 1.66 28,352.39 17,079.75
LIMPIEZA MANUAL DE TERRENO m2 17,079.75 0.46 7,856.69 17,079.75
E CARPETA ASFALTICA EXISTENTE DETERIORADO E=2" m2 5,644.29 1.79 10,103.28 5,644.29
NIMIENTO DE TRANSITO TEMPORAL Y SEGURIDAD VIAL glb 1.00 2,545.06 2,545.06 1.00
TRAZO DE SIMBOLOS Y LETRAS m2 767.80 1.91 1,466.50 767.80
RAZO DE LINEAS CONTINUAS Y DISCONTINUAS m 5,490.05 0.78 4,282.24 5,490.05
MOVIMIENTO DE TIERRAS 0.00
EN TERRENO NORMAL HASTA NIVEL DE SUBRSASANTE m3 9,136.35 6.13 56,005.83 9,136.35
CONFORMACION DE SUBRASANTE m2 13,893.99 2.45 34,040.28 13,893.99
NACION DE MATERIAL EXCEDENTE CON MAQUINARIA m3 11,330.50 14.93 169,164.37 11,330.50
PAVIMENTO 0.00
SUB BASE GRANULAR E=30CM m2 13,893.99 15.58 216,468.36 13,893.99
BASE GRANULAR E=20CM m2 13,893.99 10.81 150,194.03 13,893.99
IMPRIMACION ASFALTICA CON MC - 30 m2 13,893.99 5.12 71,137.23 13,893.99
RIEGO EN LIGA CON MC - 30 m2 3,185.76 4.21 13,412.05 3,185.76
TA ASFALTICA EN CALIENTE DE 1" (RECAPA ASFALTICA) m2 3,185.76 18.85 60,051.58 3,185.76
CARPETA ASFALTICA EN CALIENTE DE 2" m2 13,893.99 30.12 418,486.98 13,893.99
SEALIZACION DE TRANSITO 0.00
DO DE PAVIMENTO (LINEA CONTINUA Y DISCONTINUA) m 5,490.05 1.81 9,936.99 5,490.05
E PAVIMENTO (SIMBOLOS PEATONALES Y DIRECCIONALES) m2 767.80 16.01 12,292.48 767.80
VARIOS 0.00
Y/O ENCIMADO DE CUERPO DE BUZONES EXISTENTES und 7.00 183.28 1,282.96 7.00
AMBIO DE TECHOS DE CAMARA DE INSPECCION und 7.00 618.39 4,328.73 7.00

VEREDAS 227,663.06
TRABAJOS PRELIMINARES
TRAZO, NIVELES Y REPLAN m2 2,256.12 1.66 3,745.16 2,256.12
DEMOLICION DE VEREDAS m2 643.65 18.15 11,682.25 643.65
LIMPIEZA MANUAL DE TER m2 2,256.12 0.46 1,037.82 2,256.12
MOVIMIENTO DE TIERRAS 0.00
CORTE SUPERFICIAL MANU m3 451.22 28.15 12,701.84 451.22
NIVELACION Y COMPACTAC m2 2,256.12 4.40 9,926.93 2,256.12
AFIRMADO DE 4" PARA VER m2 2,256.12 11.59 26,148.43 2,256.12
ELIMINACION DE MATERIA m3 618.71 16.33 10,103.53 618.71
CONCRETO SIMPLE 0.00
CONCRETO EN SARDINEL D m3 86.85 318.56 27,666.94 86.85
CONCRETO EN VEREDAS FC= m3 2,256.12 42.22 95,253.39 2,256.12
ENCOFRADO Y DESENCOF m2 651.37 33.04 21,521.26 651.37
OTROS 0.00
JUNTA DE DILATACION ASF m 758.00 2.80 2,122.40 758.00
CURADO DE VEREDAS (INC m2 2,256.12 2.55 5,753.11 2,256.12

SARDINELES Y AREAS VERDES 360281.92


TRABAJOS PRELIMINARES
TRAZO, NIVELES Y REPLAN m2 5459.92 1.66 9063.47 5,459.92
LIMPIEZA DE TERRENO MAUm2 5459.92 0.46 2511.56 5,459.92
DEMOLICION Y ELIMINACION glb 1 3437.28 3437.28 1.00
SARDINELES 0.00
EXCAVACION MANUAL DE Z m3 159.71 31.09 4965.38 159.71
ELIMINACION DE MATERIA m3 191.65 16.33 3129.64 191.65
CONCRETO FC=175 K/CM2 m3 159.71 401.05 64051.7 159.71
ENCOFRADO Y DESENCOFRm2 1950.41 35.26 68771.46 1,950.41
ACERO DE REFUERZO FY=4kg 4986.8 4.95 24684.66 4,986.80
TARRAJEO DE SUPERFICIE ENm2 466.43 24.06 11222.31 466.43
PINTURA DE TRAFICO EN BO m2 134.31 14.42 1936.75 134.31
JUNTA DE DILATACION E=1" m2 41.88 12.9 540.25 41.88
AREAS VERDES 0.00
TRASNPORTE DE PLANTAS glb 1 537.37 537.37 0.00
CORTE SUPERFICIAL MANUAm3 1091.98 28.15 30739.24 1,091.98
ELIMINACION DE MATERIA m3 1310.38 16.33 21398.51 1,310.38
MEJORAMIENTO DE TERRE m2 5459.92 5.98 32650.32 0.00
PREPARACION DE TERREN m2 5459.92 2.58 14086.59 0.00
SEMBRADO DE GRAS EN C m2 5459.92 11.75 64154.06 0.00
CONSERVACION Y RIEGO D glb 1 2401.37 2401.37 0.00
VALORIZACION ANTERIOR
VALORIZACION ACTUAL VALORIZACION ACUM.
ACUMULADA
PARCIAL METRADO PARCIAL METRADO PARCIAL
1,281,175.10 - 1,281,175.10

3,700.00 0.00 0.00 2.00 3,700.00


2,067.07 0.00 0.00 1.00 2,067.07

4,000.00 0.00 0.00 1.00 4,000.00


28,352.39 0.00 0.00 17,079.75 28,352.39
7,856.69 0.00 0.00 17,079.75 7,856.69
10,103.28 0.00 0.00 5,644.29 10,103.28
2,545.06 0.00 0.00 1.00 2,545.06
1,466.50 0.00 0.00 767.80 1,466.50
4,282.24 0.00 0.00 5,490.05 4,282.24

56,005.83 0.00 0.00 9,136.35 56,005.83


34,040.28 0.00 0.00 13,893.99 34,040.28
169,164.37 0.00 0.00 11,330.50 169,164.37

216,468.36 0.00 0.00 13,893.99 216,468.36


150,194.03 0.00 0.00 13,893.99 150,194.03
71,137.23 0.00 0.00 13,893.99 71,137.23
13,412.05 0.00 0.00 3,185.76 13,412.05
60,051.58 0.00 0.00 3,185.76 60,051.58
418,486.98 0.00 0.00 13,893.99 418,486.98

9,936.99 0.00 0.00 5,490.05 9,936.99


12,292.48 0.00 0.00 767.80 12,292.48

1,282.96 0.00 0.00 7.00 1,282.96


4,328.73 0.00 0.00 7.00 4,328.73

227,663.06 - 227,663.06 227,663.06

3,745.16 0.00 0.00 2,256.12 3,745.16


11,682.25 0.00 0.00 643.65 11,682.25
1,037.82 0.00 0.00 2,256.12 1,037.82
16,465.23
12,701.84 0.00 0.00 451.22 12,701.84
9,926.93 0.00 0.00 2,256.12 9,926.93
26,148.43 0.00 0.00 2,256.12 26,148.43
10,103.53 0.00 0.00 618.71 10,103.53
58,880.73
27,666.94 0.00 0.00 86.85 27,666.94
95,253.39 0.00 0.00 2,256.12 95,253.39
21,521.26 0.00 0.00 651.37 21,521.26
144,441.59
2,122.40 0.00 0.00 758.00 2,122.40
5,753.11 0.00 0.00 2,256.12 5,753.11
7,875.51
246452.21 113,829.72 360,281.92

9,063.47 0.00 0.00 5,459.92 9,063.47 1,869,120.08


2,511.56 0.00 0.00 5,459.92 2,511.56
3,437.28 0.00 0.00 1.00 3,437.28

4,965.38 0.00 0.00 159.71 4,965.38


3,129.64 0.00 0.00 191.65 3,129.64
64,051.70 0.00 0.00 159.71 64,051.70
68,771.46 0.00 0.00 1,950.41 68,771.46
24,684.66 0.00 0.00 4,986.80 24,684.66
11,222.31 0.00 0.00 466.43 11,222.31
1,936.75 0.00 0.00 134.31 1,936.75
540.25 0.00 0.00 41.88 540.25

0.00 1.00 537.37 1.00 537.37


30,739.24 0.00 0.00 1,091.98 30,739.24
21,398.51 0.00 0.00 1,310.38 21,398.51
0.00 5,459.9200 32,650.32 5,459.92 32,650.32
0.00 5,459.92 14,086.59 5,459.92 14,086.59
0.00 5,459.92 64,154.06 5,459.92 64,154.06
0.00 1.00 2,401.37 1.00 2,401.37
CLCULOS DE INCIDENCIA DENTRO DEL PROYECTO
Inc
Incidencia de Sub-Presupuestos

Item Partida Monto (S/.) Incidencia 19


1 PISTAS 1,281,175.10 68.54%
2 VEREDAS 227663.06 12.18% 12.18%
3 SARDINELES Y AREAS VERDES 360281.92 19.28%
COSTO DIRECTO sin (IGV) = 1,869,120.08 100%

Incidencia en pistas

Item Partida Monto (S/.) Incidencia


1.01 OBRAS PROVISIONALES 5,767.07 0.45%
1.02 TRABAJOS PRELIMINARES 58,606.16 4.57%
1.03 MOVIMIENTO DE TIERRAS 259,210.48 20.23%
1.04 PAVIMENTO 929,750.23 72.57% 1.7
1.05 SEALIZACION DE TRANSITO 22,229.47 1.74%
1.06 VARIOS 5,611.69 0.44%
COSTO DIRECTO sin (IGV) = 1,281,175.10 100%

72.5

Incidencia en veredas

Item Partida Monto (S/.) Incidencia


2.01 TRABAJOS PRELIMINARES 16,465.23 7.23%
2.02 MOVIMIENTO DE TIERRAS 58,880.73 25.86%
2.03 CONCRETO SIMPLE 144,441.59 63.45%
2.04 OTROS 7,875.51 3.46%
COSTO DIRECTO sin (IGV) = 227,663.06 100%

63.45%
63.45%

Incidencia en sardineles y areas verdes

Item Partida Monto (S/.) Incidencia Incid


3.01 TRABAJOS PRELIMINARES 15,012.31 4.17%
3.02 SARDINELES 179,302.15 49.77%
3.03 AREAS VERDES 165,967.46 46.07%
COSTO DIRECTO sin (IGV) = 360,281.92 100% 46.07%
Incidencia de Sub - Presupuestos

19.28%

PISTAS
12.18% VEREDAS
SARDINELES Y AREAS VERDES

68.54%

Incidencia en Pistas

OBRAS PROVISIONALES
1.74% 0.44% 0.45%4.57%
20.23% TRABAJOS PRELIMINARES
MOVIMIENTO DE TIERRAS
PAVIMENTO
SEALIZACION DE TRANSITO
VARIOS
72.57%

Incidencia en Veredas

3.46% 7.23%
25.86% TRABAJOS PRELIMINARES
MOVIMIENTO DE TIERRAS
CONCRETO SIMPLE
OTROS

63.45%
63.45%

Incidencia en Sardineles y Arreas verdes

4.17%

46.07% TRABAJOS PRELIMINARES


SARDINELES
AREAS VERDES
49.77%
AVANCE VALORIZADO

Avance Programado Avance Real


Periodo N de Porcentaje N de
valorizacin Parcial Acumulado valorizacin
Mar-16 1 31.31% 31.31% 1
Apr-16 2 25.74% 57.05% 2
May-16 3 28.82% 85.87% 3

MONTO REAL EJECUTADO MONTO PROGRAMADO % AVANCE REAL EJECUTADO


PERIODO
PARCIAL ACUMULADO PARCIAL ACUMULADO PARCIAL

NOVIEMBRE 1,339,880.32 1,339,880.32 1,023,859.54 1,023,859.54 54.73%


DICIEMBRE 959,198.99 2,299,079.31 617,167.39 1,641,026.93 39.18%
ENERO 149,094.17 2,448,173.48 620,208.90 2,261,235.83 6.09%
FEBRERO 0.00 2,448,173.48 186,937.65 2,448,173.48 0.00%
TOTAL 2,448,173.48 2,448,173.48 100.00%

MONTO REAL EJECUTADO MONTO PROGRAMADO 100.00%


PERIODO 90.00%
80.00%
PARCIAL ACUMULADO PARCIAL ACUMULADO
70.00% 54.73%
60.00%
41
50.00%
NOVIEMBRE 1,339,880.32 1,339,880.32 1,023,859.54 1,023,859.54 40.00%
30.00%
DICIEMBRE 959,198.99 2,299,079.31 617,167.39 1,641,026.93
20.00%
ENERO 149,094.17 2,448,173.48 620,208.90 2,261,235.83 10.00%
FEBRERO 0.00 2,448,173.48 186,937.65 2,448,173.48 0.00%
TOTAL 2,448,173.48 2,448,173.48 NOVIEMBR

% AVANCE REAL EJECUTADO % AVANCE PROGRAMADO SITUACION


PERIODO DE LA OBRA
PARCIAL ACUMULADO PARCIAL ACUMULADO POR MES

NOVIEMBRE 54.73% 54.73% 41.82% 41.82% ADELANTADO


DICIEMBRE 39.18% 93.91% 25.21% 67.03% ADELANTADO
ENERO 6.09% 100.00% 25.33% 92.36% ATRASADO
FEBRERO 0.00% 100.00% 7.64% 100.00%
TOTAL 100.00% 100.00%
E VALORIZADO

Avance Real Situacin de


Situacin de
Porcentaje obra
obra total
Parcial Acumulado mensual
58.32% 58.32% adelantada adelantada
25.84% 84.16% adelantada adelantada
6.68% 90.83% atrasada adelantada

VANCE REAL EJECUTADO % AVANCE PROGRAMADO SITUACION SITUACION


DE LA OBRA DE LA OBRA
ACUMULADO PARCIAL ACUMULADO POR MES TOTAL

54.73% 41.82% 41.82% ADELANTADO ADELANTADO


93.91% 25.21% 67.03% ADELANTADO ADELANTADO
100.00% 25.33% 92.36% ATRASADO ADELANTADO
100.00% 7.64% 100.00%
100.00%
Valorizaciones Mensuales
100.00% 100.00%
93.91% 92.36%
100.00%
90.00%
80.00% 67.03%
70.00% 54.73%
60.00%
41.82%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
NOVIEMBRE DICIEMBRE ENERO FEBRERO
% AVANCE REAL EJECUTADO % AVANCE PROGRAMADO

SITUACION
DE LA OBRA
TOTAL

Curva "S" de Avance de Obra


ADELANTADO
120.00%
100.00%
100.00% 93.91% 100.00%
92.36%
80.00%
Curva "S" de Avance de Obra
120.00%
ADELANTADO
ADELANTADO 100.00%
100.00% 93.91% 100.00%
92.36%
80.00%
67.03%
54.73%
60.00%

40.00% 41.82%

20.00%

0.00%
NOVIEMBRE DICIEMBRE ENERO FEBRERO
Avance Real Avance Programado