Energy Integrated Systems Support and Services

A Power Utility Consulting and Engineering Services Company


INTERNAL PROGRESS REPORT
TOLEDO CHEMICAL CLEANING UNIT 2 INSTALLATION July 17, 2017

PLANT SITE: TVEP TOLEDO CEBU CITY SHIFT SCHEDULE


PROJECT: TVEP PRE-BOILER CHEMICAL CLEANING UNIT 2 0800H 1700H

I. DAILY ACTIVITY: Weather: Cloudy/Rainy


Description Assigned Status
1. Tool Box Meeting: 0830H Manny Merluza
1.1 Skid Assembly
1.2 Tie Ups
2. Safety Permits and Work Preparation AISSI
2.1 PTW and Hot Work Permits AISSI Ok
2.2 Other Safety Concerns AISSI/EISSS
3. Document Requirements AISSI/EISSS In Progress
4. Material Procurement Status AISSI
5. Equipment Status AISSSI/EISSS
6. Dosing System Skid Assembly AISSI/EISSS Motors are Plastic Covered
7. Circulating System Skid Assembly AISSI/EISSS Waiting for 12 Pipe
8. Auxiliary Boiler AISSI/EISSS Waiting for Electrical Testing
9. Piping and Tie ups Installation AISSI/EISSS In Progress
9.1 Feed water Tie Up AISSI/EISSS In Progress (65%)
4.2 Boiler Tie Up AISSI/EISSS TBS
10 Next Day Activities Manny Merluza Focus on RH Spray Tie up
Prepared by:
Louie Raymond A. Fernandez

11
Energy Integrated Systems Support and Services
A Power Utility Consulting and Engineering Services Company

3. Document Requirements
# Document Status Assigned Notes
1 Updated pre-Boiler P & ID Pre Boiler Chem Clean
. Finished Dave Cabral
2 Flow Simulation of Pre Boiler Chem Clean System To be Revised Leonardo Fuentes
3 Updated Project Schedule In Progress Arlee Dimaano
4 Flow Path of Pre Boiler Chem Clean System Finished Dave Cabral
5 Valve Isolation List Finished Dave Cabral

IX. TIE UPS INSTALLATION


4.1 Tie ups Feedwater
# Tasks Status Notes
1. HP Heater Tie Up In Progress
1.1 Piping In Progress
1.2 Tie Up In Progress
1.3 Hyrdrotest TBS (To be scheduled)
2. LP heater Tie up In Progress
2.1 Piping In Progress
2.2 Tie Up In Progress
2.3 Hyrdrotest TBS
3. BFP-A tie up In Progress
3.1 Piping In Progress
3.2 Tie ups (In/Out/RH) In Progress
3.3 Hydrotest TBS
4. BFP-B tie up In Progress
4.1 Piping In Progress
4.2 Tie ups (In/Out/RH) In Progress
4.3 Hydrotest TBS
5. BFP-C tie up In Progress
5.1 Piping In Progress
5.2 Tie ups (In/Out/RH) In Progress
5.3 Hydrotest TBS
6. Condensate Tie up TBS Waiting for activities inside STG Building
6.1 Piping In Progress to be finished in order to proceed.
6.2 Tie up In Progress
6.3 Hydrotest TBS
7. Deaerator Tie Up In Progress
6.1 Piping In Progress
6.2 Tie up In Progress
6.3 Hydrotest TBS
Energy Integrated Systems Support and Services
A Power Utility Consulting and Engineering Services Company

Economizer Tie Up Installation Deaerator Tie Up Installation

4.2 Tie Ups Boiler


# Tasks Status Notes
1.
Steam drum tie up* TBS
1.1 Li/Lx TBS
1.2 Orifice Plate TBS
1.3 Corrosion Coupon TBS
1.4 Camera TBS
Unit
2. 2 BFP A
DowncommerPiping and
Tie Tie
up* up Installation
TBS Unit 2 BFP B Piping and Tie up Installation
2.1 Piping TBS
2.2 Tie Up TBS
2.3 Hyrdrotest TBS
3. Economizer Tie up* TBS
3.1 Piping TBS
3.2 Tie Up TBS
3.3 HYRDROTEST TBS
4. Super Heater Backfill Tie Up TBS
4.1 Piping TBS
4.2 Tie Up TBS
4.3 Hyrdrotest TBS
5.
Demin tank Tie up Completed
5.1 Piping Completed
5.2 Tie Up Completed
5.3 Hyrdrotest Completed
Unit 2 BFP C Piping and Tie up Installation Down Commer Piping Installation
6. Sedimentation Pond Tie Up In Progress
6.1 Piping Completed
6.2 Tie Up Completed
6.3 Hyrdrotest Completed
6.4 Ip Camera TBS
Energy Integrated Systems Support and Services
A Power Utility Consulting and Engineering Services Company
Energy Integrated Systems Support and Services
A Power Utility Consulting and Engineering Services Company

Item # Equipment Remarks / Status


1 Circulation System
1.1 Wilo Pump Plastic Covered (Megger Tested. Each line is Approx. 15Mohm Insulation Resistance )
1.2 Grundfos Pump Plastic Covered (Megger Tested. Each line is Approx. 150Mohm Insulation Resistance )
2 Dosing System System
2.1 Grundfos Pump Plastic Covered (Megger Tested. Each line is Approx. 50Mohm Insulation Resistance )
2.2 Ebara Pump Plastic Covered (Megger Tested. Each line is Approx. 200Mohm Insulation Resistance )
3 Auxiliary Boiler
3.1 Old (500BHP) -Boiler Tubes being repaired
3.2 New -Not in operation, Standby
3.3 Fuel Oil
4 Power Supply
4.1 500KVA Diesel Gen -ETA July 18, 2017 (Tentative)
4.2 115KVA Diesel Gen -Diesel Genset in Operation
4.3 Fuel Oil -OK
5 Instrument/PPE
5.1 Radio - Radio pulled out of Site
5.2 Flow meters - Flow meters pulled out of Site
5.3 PLC/HMI - PLC/HMI Pulled out of site
5.4 LX and Camera - LX and Level indicator inside mobile office
5.5 PPE - Ok
V. EQUIPMENT STATUS