Está en la página 1de 4

OBRA: MEGA PLAZA -HUARAL

CLIENTE: INVERSIONES LENDIPO SAC

DOCUM. : METRADO DE CONCRETO DE ZAPATAS CONTRATISTA: H y HE

RESIDENTE. : ING. ROBERTO OPORTO FECHA: 6/2/2016

ELABORADO POR : BACH. HAROLD PAUCAR ESCALANTE.

DIMENSIONES SUBTOTAL
ITEM ELEMENTO DESCRIP. EJES CANT.
(m3)
LONG. ANCHO PERALTE
TIENDA POR DEPARTAMENTO
1 VIGA VC-01 EJE 01/E-F 1.00 7.92 0.30 0.60 1.43
2 VIGA VC-01 EJE 01/D-E 1.00 7.92 0.30 0.60 1.43
3 VIGA VC-01 EJE 01/C-D 1.00 7.92 0.30 0.60 1.43
4 VIGA VC-01 EJE 01/A-B 1.00 6.99 0.30 0.60 1.26
5 VIGA VC-01 EJE A/01-02 1.00 7.83 0.30 0.80 1.88
6 VIGA VC-02 EJE 02/A-B 1.00 4.54 0.30 0.00 1.36
7 VIGA VC-02 EJE 03/A-B 1.00 4.54 0.30 0.00 1.36
8 VIGA VC-02 EJE 04/A-B 1.00 4.54 0.30 0.00 1.36
9 VIGA VC-02A EJE 05/A-B 1.00 6.99 0.30 1.20 2.52
10 VIGA VC-01 EJE A/02-03 1.00 3.28 0.30 0.60 0.59
11 VIGA VC-01 EJE A/03-04 1.00 7.78 0.30 0.60 1.40
12 VIGA VC-01 EJE A/04-05 1.00 2.78 0.30 0.60 0.50
13 VIGA VC-01 EJE A/05-06 1.00 7.83 0.30 0.60 1.41
14 VIGA VC-01 EJE A/06-07 1.00 3.21 0.30 0.60 0.58
15 VIGA VC-01 EJE A/07-08 1.00 7.48 0.30 0.60 1.35
16 VIGA VC-03 EJE 06/A-B 1.00 6.99 0.30 1.00 2.10
17 VIGA VC-04 EJE 07/A-B 1.00 6.94 0.30 0.70 1.46
18 VIGA VC-04 EJE 08/A-B 1.00 6.94 0.30 0.70 1.46
19 VIGA VC-01A EJE 06/B-C 1.00 7.91 0.30 0.60 1.42
20 VIGA VC-01 EJE C/06-07 1.00 7.54 0.30 0.60 1.36
21 VIGA VC-01 EJE C/07-08 1.00 7.48 0.30 0.60 1.35
22 VIGA VC-01 EJE 08/B-C 1.00 2.82 0.30 0.60 0.51
23 VIGA VC-01 EJE 06/C-D 1.00 3.66 0.30 0.60 0.66
24 VIGA VC-01 EJE 06/F-G 1.00 9.72 0.30 0.60 1.75
25 VIGA VC-01 EJE 06/G-H 1.00 6.32 0.30 0.60 1.14
26 VIGA VC-01 EJE H/05-06 1.00 3.76 0.30 0.60 0.68

TOTAL = 33.71
OBRA: MEGA PLAZA -HUARAL

CLIENTE: INVERSIONES LENDIPO SAC

DOCUM. : METRADO DE CURADO DE ZAPATAS CONTRATISTA: H y HE

RESIDENTE. : ING. ROBERTO OPORTO FECHA: 6/2/2016

ELABORADO POR : BACH. HAROLD PAUCAR ESCALANTE.

DIMENSIONES SUBTOTAL
ITEM ELEMENTO DESCRIP. EJES CANT. (m2)
LONG. ANCHO PERALTE
TIENDA POR DEPARTAMENTO
1 VIGA VC-01 EJE 01/E-F 2.00 7.92 0.60 9.50
2 VIGA VC-01 EJE 01/D-E 2.00 7.92 0.60 9.50
3 VIGA VC-01 EJE 01/C-D 2.00 7.92 0.60 9.50
4 VIGA VC-01 EJE 01/A-B 2.00 6.99 0.60 8.39
5 VIGA VC-01 EJE A/01-02 2.00 7.83 0.80 12.53
6 VIGA VC-02 EJE 02/A-B 2.00 4.54 0.00 0.00
7 VIGA VC-02 EJE 03/A-B 2.00 4.54 0.00 0.00
8 VIGA VC-02 EJE 04/A-B 2.00 4.54 0.00 0.00
9 VIGA VC-02 EJE 05/A-B 2.00 6.99 1.20 16.78
10 VIGA VC-01 EJE A/02-03 2.00 3.28 0.60 3.94
11 VIGA VC-01 EJE A/03-04 2.00 7.78 0.60 9.34
12 VIGA VC-01 EJE A/04-05 2.00 2.78 0.60 3.34
13 VIGA VC-01 EJE A/05-06 2.00 7.83 0.60 9.40
14 VIGA VC-01 EJE A/06-07 2.00 3.21 0.60 3.85
15 VIGA VC-01 EJE A/07-08 2.00 7.48 0.60 8.98
16 VIGA VC-03 EJE 06/A-B 2.00 6.99 1.00 13.98
17 VIGA VC-04 EJE 07/A-B 2.00 6.94 0.70 9.72
18 VIGA VC-04 EJE 08/A-B 2.00 6.94 0.70 9.72
19 VIGA VC-01A EJE 06/B-C 2.00 7.91 0.60 9.49
20 VIGA VC-01 EJE C/06-07 2.00 7.54 0.60 9.05
21 VIGA VC-01 EJE C/07-08 2.00 7.48 0.60 8.98
22 VIGA VC-01 EJE 08/B-C 2.00 2.82 0.60 3.38
23 VIGA VC-01 EJE 06/C-D 2.00 3.66 0.60 4.39
24 VIGA VC-01 EJE 06/F-G 2.00 9.72 0.60 11.66
25 VIGA VC-01 EJE 06/G-H 2.00 6.32 0.60 7.58
26 VIGA VC-01 EJE H/05-06 2.00 3.76 0.60 4.51

TOTAL = 197.50
OBRA: MEGA PLAZA -HUARAL

CLIENTE: INVERSIONES LENDIPO SAC

DOCUM. : METRADO DE ENCOFRADO DE ZAPATAS CONTRATISTA: H y HE

RESIDENTE. : ING. ROBERTO OPORTO FECHA: 6/2/2016

ELABORADO POR : BACH. HAROLD PAUCAR ESCALANTE.

DIMENSIONES SUBTOTAL
ITEM ELEMENTO DESCRIP. EJES CANT. (m2)
LONG. ANCHO PERALTE
TIENDA POR DEPARTAMENTO
1 VIGA VC-01 EJE 01/E-F 2.00 7.92 0.60 9.50
2 VIGA VC-01 EJE 01/D-E 2.00 7.92 0.60 9.50
3 VIGA VC-01 EJE 01/C-D 2.00 7.92 0.60 9.50
4 VIGA VC-01 EJE 01/A-B 2.00 6.99 0.60 8.39
5 VIGA VC-01 EJE A/01-02 2.00 7.83 0.80 12.53
6 VIGA VC-02 EJE 02/A-B 2.00 4.54 0.00 0.00
7 VIGA VC-02 EJE 03/A-B 2.00 4.54 0.00 0.00
8 VIGA VC-02 EJE 04/A-B 2.00 4.54 0.00 0.00
9 VIGA VC-02 EJE 05/A-B 2.00 6.99 1.20 16.78
10 VIGA VC-01 EJE A/02-03 2.00 3.28 0.60 3.94
11 VIGA VC-01 EJE A/03-04 2.00 7.78 0.60 9.34
12 VIGA VC-01 EJE A/04-05 2.00 2.78 0.60 3.34
13 VIGA VC-01 EJE A/05-06 2.00 7.83 0.60 9.40
14 VIGA VC-01 EJE A/06-07 2.00 3.21 0.60 3.85
15 VIGA VC-01 EJE A/07-08 2.00 7.48 0.60 8.98
16 VIGA VC-03 EJE 06/A-B 2.00 6.99 1.00 13.98
17 VIGA VC-04 EJE 07/A-B 2.00 6.94 0.70 9.72
18 VIGA VC-04 EJE 08/A-B 2.00 6.94 0.70 9.72
19 VIGA VC-01A EJE 06/B-C 2.00 7.91 0.60 9.49
20 VIGA VC-01 EJE C/06-07 2.00 7.54 0.60 9.05
21 VIGA VC-01 EJE C/07-08 2.00 7.48 0.60 8.98
22 VIGA VC-01 EJE 08/B-C 2.00 2.82 0.60 3.38
23 VIGA VC-01 EJE 06/C-D 2.00 3.66 0.60 4.39
24 VIGA VC-01 EJE 06/F-G 2.00 9.72 0.60 11.66
25 VIGA VC-01 EJE 06/G-H 2.00 6.32 0.60 7.58
26 VIGA VC-01 EJE H/05-06 2.00 3.76 0.60 4.51

TOTAL = 197.50
METRADO DE ACERO
Obra:MP HUARAL FASE 1
Clie MEGA PLAZA
Fecha:
13/03/16 Hecho por :Roberto Oporto

2 8mm 3 4 5 6 8 9 10 11
N de N Pzs/ Long (ml) 1/4" 8mm 3/8" 1/2" 5/8" 3/4" 1" 1 1/8" 1 1/4" 1 3/8"
ITEM Descrip. # TOTAL (Kg)
veces Elmto 0.249 0.395 0.560 0.994 1.552 2.235 3.973 5.034 6.215 7.520
### 01 ZAPATAS TXD
### 1.01 TXD
### 1.01 ZAPATAS
### 1.01 EJE 01/E-F, 01/D-E, EJE 01/C-D
LONGITUDINALES 8 1" 3 6 1 8.52 609.30
TRANSVERSALES 3 3/8" 3 1 32 2 107.52

### 1.02 EJE 01/A-B


LONGITUDINALES 8 1" 1 6 1 7.59 180.93
TRANSVERSALES 3 3/8" 1 1 28 2 31.36

### 1.03 EJE A/01-02


LONGITUDINALES 8 1" 1 6 1 8.43 200.95
TRANSVERSALES 3 3/8" 1 1 31 2 34.72

### 1.04 EJE 02/A-B, 03/A-B, 04/A-B


LONGITUDINALES SUPERIOR 8 1" 3 3 1 8.77 313.59
LONGITUDINALES INFERIOR 8 1" 3 3 1 8.98
TRANSVERSALES 3 3/8" 3 1 31 2.66 138.53
### REFUERZO 1 5 5/8" 3 1 2 2.66 24.77
REFUERZO 2 8 1" 3 1 3 5.59 199.88
REFUERZO 3 8 1" 3 1 3 5.69 203.46
### 1.05 EJE 05/A-B
LONGITUDINALES SUPERIOR 8 1" 1 1 3 8.98 107.03
LONGITUDINALES INFERIOR 6 3/4" 1 1 3 8.41
### TRANSVERSALES 3 3/8" 1 1 27 3.52 53.22
REFUERZO 8 1" 1 1 3 5.59 66.63
### 1.08 EJE A/02-03
LONGITUDINALES 8 1" 1 6 1 4.84 115.38
TRANSVERSALES 3 3/8" 1 1 13 2 14.56

### 1.09 EJE A/03-04


LONGITUDINALES 8 1" 1 6 1 9.34 222.65
TRANSVERSALES 3 3/8" 1 1 31 1.8 31.25

### 1.10 EJE A/04-05


LONGITUDINALES 8 1" 1 6 1 4.34 103.46
TRANSVERSALES 3 3/8" 1 1 11 1.8 11.09

### 1.11 EJE A/05-06


LONGITUDINALES 8 1" 1 6 1 9.39 223.84
TRANSVERSALES 3 3/8" 1 1 31 1.8 31.25

### 1.12 EJE A/06-07


LONGITUDINALES 8 1" 1 6 1 4.77 113.71
TRANSVERSALES 3 3/8" 1 1 13 1.8 13.10

### 1.13 EJE A/07-08


LONGITUDINALES 8 1" 1 6 1 9.04 215.50
TRANSVERSALES 3 3/8" 1 1 30 1.8 30.24

### 1.14 EJE 06/A-B


LONGITUDINALES SUPERIOR 8 1" 1 4 1 8.98 142.71
LONGITUDINALES INFERIOR 6 3/4" 1 4 1 8.98 80.28
TRANSVERSALES 3 3/8" 1 1 28 3.52 55.19
REFUERZO 8 1" 1 1 2 5.59 44.42

### 1.15 EJE 07/A-B


LONGITUDINALES SUPERIOR 8 1" 1 4 1 8.93 141.92
LONGITUDINALES INFERIOR 6 3/4" 1 4 1 8.93 79.83
TRANSVERSALES 3 3/8" 1 1 28 4.12 64.60
### 1.16 REFUERZO 7 3/4" 1 1 2 5.59

### 1.17 EJE 08/A-B


LONGITUDINALES SUPERIOR 8 1" 1 4 1 8.93 141.92
LONGITUDINALES INFERIOR 6 3/4" 1 4 1 8.93 79.83
TRANSVERSALES 3 3/8" 1 1 28 4.12 64.60
### REFUERZO 8 1" 1 1 2 5.59 44.42

### 1.19 EJE 06/B-C


LONGITUDINALES 8 1" 1 6 1 9.47 225.75
TRANSVERSALES 3 3/8" 1 1 32 2 35.84

### 1.20 EJE C/06-07


LONGITUDINALES 8 1" 1 6 1 9.1 216.93
TRANSVERSALES 3 3/8" 1 1 30 2 33.60

### 1.21 EJE C/07-08


LONGITUDINALES 8 1" 1 6 1 9.04 215.50
TRANSVERSALES 3 3/8" 1 1 30 2 33.60

1.01.0 EJE C-D/07-08


LONGITUDINALES 8 1" 1 6 1 4.69 111.80
TRANSVERSALES 3 3/8" 1 1 15 2 16.80

EJE F-G/06
LONGITUDINALES 8 1" 3 6 1 10.32 738.02
TRANSVERSALES 3 3/8" 3 1 39 2 131.04

EJE F-G/06
LONGITUDINALES 8 1" 3 6 1 8.92 637.90
TRANSVERSALES 3 3/8" 3 1 33 2 110.88

Total Long (Ml) 0.00 0.00 1862.50 0.00 15.96 107.36 1393.80 0.00 0.00 0.00
% De Desperdicio 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
# Varillas 0 0 207 0 2 12 155 0 0 0
Peso Parcial (Kg) 0.00 0.00 1043.00 0.00 24.77 239.95 5537.57 0.00 0.00 0.00 6,845.29