FLUJO DE CAJA POR MES

marzo abril mayo junio julio agosto Total


CREACION DE COMPLEJO DEPORTIVO
OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD - GENERAL
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO
LIMPIEZA MANUAL DEL TERRENO S/. 130,389.56 S/. 130,389.56
TRAZOS NIVELES Y REPLANTEO
TRAZO Y REPLANTEO INICAL S/. 62,101.43 S/. 62,101.43
TRAZO Y REPLANTEO PRELIMINAR DURANTE EL PROCESO S/. 861,967.78 S/. 861,967.78
SEGURIDAD Y SALUD
EQUIPO DE PROTECCIN COLECTIVA S/. 404.16 S/. 404.16
SEALIZACIN TEMPORAL DE SEGURIDAD S/. 2,791.18 S/. 2,791.18
CERCO PERIMETRICO
ESTRUCTURAS - CERCO PERIMETRICO
OBRAS PRELIMINARES
CERCO PERIMETRICO PROVICIONAL S/. 86,393.13 S/. 86,393.13
MOVIMIENTO DE TIERRAS
EXCAVACIONES
EXCAVACION DE ZANJA PARA CIMIENTOS CORRIDOS S/. 842.76 S/. 912.98 S/. 1,755.74
RELLENO CON MATERIAL (CALICANTO NATURAL ZARANDEADO) S/. 295.45 S/. 295.45
RELLENOS
NIVELACION INTERIOR Y APISONADO S/. 786.92 S/. 196.73 S/. 983.65
ELIMINACIONES
ELIMINACION DE MATERIAL EXCEDENTE S/. 1,429.49 S/. 1,429.49
OBRAS DE CONCRETO SIMPLE
CIMIENTOS CORRIDOS
CONCRETO CICLOPEO DE CIMIENTOS CORRIDOS B1:10 + 30% PG S/. 24,191.20 S/. 24,191.20
SOBRECIMIENTOS
ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTO S/. 58,406.76 S/. 58,406.76
CONCRETO CICLOPEO PARA SOBRECIMIENTO, 1:8 + 25% PM S/. 19,832.94 S/. 19,832.94
OBRAS DE CONCRETO ARMADO
COLUMNAS
COLUMNAS ACERO FY= 4200 kg/cm2 GRADO 60 S/. 11,004.66 S/. 11,004.66
CONCRETO COLUMNAS f'c=210 kg/cm2 S/. 11,676.54 S/. 11,676.54
ENCOFRADO DE COLUMNAS S/. 6,028.07 S/. 6,028.07
DESENCOFRADO DE COLUMNAS S/. 5,722.00 S/. 5,722.00
VIGAS
ENCOFRADO DE VIGAS S/. 2,443.95 S/. 977.58 S/. 3,421.53
VIGAS ACERO FY= 4200 kg/cm2 S/. 3,990.89 S/. 3,990.89
CONCRETO PARA VIGAS F'C=210 KG/CM2 S/. 6,353.95 S/. 6,353.95
DESENCOFRADO DE VIGAS S/. 3,227.71 S/. 3,227.71
ARQUITECTURA
MUROS Y TABIQUES DE ALBALILERA
MURO LADRILLO SOGA MMEZC C:A 1:4 JUNTA 1.5 cm. S/. 15,710.01 S/. 62,840.04 S/. 78,550.05
REVOQUES, ENLUCIDOS Y MOLDURAS
TARRAJEOS
TARRAJEO EN SOBRECIMIENTOS S/. 11,682.07 S/. 46,728.28 S/. 58,410.35
TARRAJEO COLUMNAS S/. 9,522.63 S/. 1,904.53 S/. 11,427.16
TARRAJEO DE VIGAS S/. 6,044.02 S/. 6,044.02
CARPINTERIA METALICA
REJAS CARP BCO S/. 7,112.10 S/. 3,556.05 S/. 10,668.15
PINTURAS
PINTURA ANTICORROSIVA EN REJA METALICA TIPO 1 INC S/. 1,433.70 S/. 1,433.70
VARIOS
JUNTA CON TECKNOPORT e=1" S/. 559.52 S/. 559.52
CAMPO DEPORTIVO
ESTRUCTURAS
MOVIMIENTO DE TIERRAS
EXCAVACION
EXCAVACION MASIVA CON EQUIPO PESADO S/. 6,729.58 S/. 6,729.58
ELIMINACION DE MATERIAL EXCEDENTE
ELIMINACION DE MATERIAL EXCEDENTE , INCLUYE ACARREO INTERNO DE MATERIAL S/. 3,569.72 S/. 3,569.72
NIVELACION S/. 8,187.31 S/. 8,187.31
APISONADO MANUAL S/. 18,285.14 S/. 8,126.73 S/. 26,411.87
OBRAS DE CONCRETO SIMPLE
CONCRETO 1:10, PARA SOLADOS Y DADOS S/. 30,991.89 S/. 30,991.89
VARIOS
SUMINISTRO E INSTALACION DE GRASS SINTTICO
SUMINISTRO E INSTALACION DE GRAS SINTETICO S/. 37,147.50 S/. 37,147.50
ARQUITECTURA
PISOS Y PAVIMENTOS
ENCOFRADO DE SARDINELES S/. 1,176.59 S/. 1,176.59
CONCRETO PARA SARDINELES FC=140KG/CM2 S/. 592.21 S/. 592.21
DESENCOFRADO DE SARDINELES S/. 980.68 S/. 980.68

Pgina 1
FLUJO DE CAJA POR MES

marzo abril mayo junio julio agosto Total


ESTRUCTURA PARA COBERTURAS
MOVIMIENTO DE TIERRAS
EXCAVACION
EXCAVACION MANUAL DE ZANJAS PARA ZAPATAS S/. 24,827.26 S/. 24,827.26
RELLENO CON MATERIAL (CALICANTO NATURAL ZARANDEADO) S/. 10,962.90 S/. 10,962.90
NIVELACION Y COMPACTACION
NIVELACION Y COMPACTADO TERRENO NORMAL (CON PLANCHA) S/. 1,119.00 S/. 1,119.00
OBRAS DE CONCRETO SIMPLE
SOLADOS
SOLADOS PARA ZAPATAS C:H 1:12 e=4" S/. 464.00 S/. 464.00
ELIMINACION DE MATERIAL EXCEDENTE S/. 2,255.05 S/. 2,255.05
COBERTURAS
SUMINISTRO E INSTALACION DE COBERTURA
SUMINISTRO E INSTALACION DE COBERTURA METALICA S/. 66,807.13 S/. 66,807.13
OBRAS DE CONCRETO ARMADO
ZAPATAS
CONCRETO PARA ZAPATASF'C=210KG/CM2 S/. 32,000.83 S/. 32,000.83
ACERO CORRUGADO D=5/8" FY= 4200 kg/cm2 GRADO 60 S/. 8,353.37 S/. 8,353.37
INSTALACIONES SANITARIAS
SISTEMA DE DRENAJE PLUVIAL - COBERTURA
CANALETAS PLUVIAL SEMICIRCULAR 6" INCLUYE ACCESORIOS S/. 5,770.47 S/. 5,770.47
SUMINISTRO E INSTALACION DE TUBERIA PVC - SAL DE 4" S/. 5,797.44 S/. 5,797.44
CODO PVC SAL 4"X 90D S/. 72.00 S/. 72.00
CODO PVC SAL 4"X22.5 S/. 33.92 S/. 33.92
CODO PVC SAL DE 4"X11.25 S/. 33.92 S/. 33.92
ABRAZADERA DE FO. GDO. DE 4" S/. 1,326.24 S/. 1,326.24
SISTEMA DE DRENAJE PLUVIAL
REJILLA METALICA PARA CANALETA PLUVIAL S/. 6,282.64 S/. 6,282.64
CAJA DE REGISTRO 12"X24" TAPA DE CONCRETO S/. 425.48 S/. 425.48
SERVICIOS HIGIENICOS
ESTRUCTURAS
MOVIMIENTO DE TIERRAS
EXCAVACIONES
EXCAVACION MANUAL DE ZANJAS H=0.60M MATERIAL SUELTO S/. 414.16 S/. 414.16
ELIMINACIONES
ELIMINACION DE MATERIAL EXCEDENTE S/. 43.86 S/. 43.86
RELLENOS
RELLENO COMPACTADO CON MATERIAL PROPIO S/. 75.50 S/. 75.50
OBRAS DE CONCRETO SIMPLE
CIMIENTOS CORRIDOS
CONCRETO PARA CIMIENTOS CORRIDOS F'C=140KG/CM2 + 30% PG S/. 1,099.24 S/. 1,099.24
SOBRECIMIENTO
ACERO DE REFUERZO fy=4,200 kg/cm2 S/. 800.68 S/. 800.68
ENCOFRADO DE SOBRECIMIENTO h=0.50 M.CON PLANChA METALICA 0.60x1.20 m. S/. 1,227.13 S/. 1,227.13
CONCRETO ARMADO
COLUMNA DE AMARRE
CONCRETO FC=175 KG/CM2 PARA SOBRECIMIENTOS S/. 508.54 S/. 508.54
ENCOFRADO Y DESENCOFRADO DE COLUMNETAS S/. 507.82 S/. 507.82
DESENCOFRADO PARA SOBRECIMIENTO REFORZADO S/. 676.88 S/. 676.88
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/. 148.29 S/. 148.29
VIGUETAS
ENCOFRADO Y DESENCOFRADO EN VIGUETAS S/. 1,200.16 S/. 1,200.16
CONCRETO PARA COLUMNETAS F'C=175 KG/CM2 S/. 79.49 S/. 79.49
CONCRETO PARA VIGUETAS F'C=175 KG/CM2 S/. 218.50 S/. 218.50
ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 S/. 246.62 S/. 246.62
ARQUITECTURA
MUROS Y TABIQUES DE ALBALILERA
MUROS DE LADRILLO KK 18 HUECOS DE SOGA, C:A 1:4 S/. 4,093.66 S/. 4,093.66
REVOQUES, ENLUCIDOS Y MOLDURAS
TARRAJEO DE MUROS CON ADITIVO IMPERMEABILIZANTE S/. 2,673.42 S/. 2,673.42
TARRAJEO EN VIGUETAS S/. 520.52 S/. 520.52
VESTIDURA DE DERRAMES A=0.15, MORTERO 1:5 S/. 528.71 S/. 528.71 S/. 1,057.42
TARRAJEO EN COLUMNETAS S/. 253.25 S/. 253.25
COBERTURAS
COBERTURA OPACA ONDA 100 DE FIBRA VEGETAL DE 2.00x1.20 S/. 12,959.11 S/. 12,959.11
SUMINISTRO E INSTALACION DE VIGAS DE MADERA DE 3"x2" S/. 871.64 S/. 871.64
SUMINISTRO E INSTALACION DE ARRIOSTRES DE MADERA DE 2"x2" S/. 657.88 S/. 657.88
SUMINISTRO E INSTALACION DE TABLA MACHIEMBRADA QUINILLA S/. 52.03 S/. 52.03
CARPINTERIA DE MADERA
SUMINISTRO E INSTALACION DE CORREAJES DE MADERA DE 2"x2" S/. 1,376.78 S/. 1,376.78
SUMINISTRO E INSTALACION DE PUERTA 0.75X1.95 M - INC. MARCO S/. 1,398.68 S/. 1,398.68
SUMINISTRO E INSTALACION DE VENTANA DE MADERA DE 0.35X0.75 M - INC. MARCO S/. 791.04 S/. 791.04
CERRAJERIA

Pgina 2
FLUJO DE CAJA POR MES

marzo abril mayo junio julio agosto Total


SUMINISTRO E INSTALACION DE VENTANA DE MADERA DE 0.35X1.15 M - INC. MARCO S/. 912.58 S/. 912.58
SUMINISTRO E INSTALACION DE CERRADURA TIPO PERILLA S/. 25.92 S/. 25.92
SUMINISTRO E INSTALACION DE BISAGRA ALUMINIZADO DE 4"X4" S/. 29.94 S/. 29.94
ZOCALOS Y CONTRAZOCALOS
CONTRAZOCALO DE CEMENTO SEMIPULIDO E=1.5CM S/. 373.01 S/. 373.01
PISOS
PISO DE CEMENTO PULIDO E=1" S/. 1,052.73 S/. 1,052.73
PINTURAS
PINTURA DE MUROS Y COLUMNAS EXTERIORES, LATEX 02 MANOS, INCUYE IMPRIMANTE S/. 2,134.13 S/. 2,134.13
INSTALACIONES SANITARIAS
APARATOS SANITARIOS Y ACCESORIOS
SUMINISTRO E INSTALACION DE APARATOS SANITARIOS S/. 2,700.00 S/. 2,700.00
SUMINISTRO E INSTALACION DE ACCESORIOS S/. 96.00 S/. 96.00
FIN DE OBRA
Total S/. 1,200,700.05 S/. 265,942.86 S/. 172,721.99 S/. 140,753.18 S/. 12,938.30 S/. 1,793,056.38