HOJA DE METRADO

PROYECTO: "CONSTRUCCION DE INFRAESTRUCTURA I.E. NIVEL INICIAL


LUGAR : ALLPACHACA - LIRCAY - ANGARAES

N DIMENSIONES
ITEM PARTIDA UNID PARCIAL
VEC. LARGO ANCHO ALTO

01.00 ESTRUCTURAS
01.01 OBRAS PROVICIONALES
01.01.01 CARTEL DE IDENTIFICACION DE LA OBRA 3.60X 2.40 mts Und 1 1.00
01.01.02 ALMACEN Y GUARDIANIA Und 1 1.00
01.02 OBRAS PRELIMINARES
01.02.01 LIMPIEZA DE TERRENO MANUAL m2 1 18.00 18.00 324.00
01.02.02 TRAZO Y REPLANTEO m2 1 18.00 18.00 324.00
01.03 MOVIMIENTO DE TIERRAS
01.03.01 CORTE DE TERRENO NATURAL H=20cm m2 1 18 18 324
01.03.02 EXCAVACION DE ZANJAS PARA ZAPATAS m3
Z-1 16 AREA= 1.095 1.35 23.652
Z-2 7 1 0.8 1.2 6.72
01.03.03 EXCAVACION DE ZANJAS PARA CIMIENTOS m3
EJE D,A,A',D',4-4,7-7 8 1.63 0.4 0.7 3.6512
Ejes Muro diagonal de las aulas 8 1.63 0.4 0.7 3.6512
EJE H,G ENTRE EJES 1-1,2 2 1.90 0.40 0.50 0.7584
EJE F ENTE EJES 1-2, 3-3 1 2.90 0.40 0.70 0.81088
EJE MURO INTERIOR SS.HH ENTE EJES H,G,1,2 1 2.30 0.40 0.50 0.4592
EJE 1-1,3-3 ENTE EJES G,F 2 4.15 0.40 0.70 2.324
EJE 1,2 ENTRE EJES H,G 2 1.81 0.40 0.50 0.7244
EJE G ENTRE EJES 2,3-3 1 0.20 0.40 0.70 0.056
01.03.04 RELLENO CON MATERIAL PROPIO m3
Z-1 16 1.02 0.20 3.258
Z-2 7 0.46 0.10 0.322
EJE D,A,A',D',7-7 12 1.63 0.13 0.10 0.245
EJE 4-4 1 1.63 0.40 0.10 0.065
Ejes Muro diagonal de las aulas 16 1.63 0.13 0.10 0.326
EJE H,G ENTRE EJES 1-1,2 4 1.90 0.13 0.10 0.095
EJE F ENTE EJES 1-2, 3-3 2 2.90 0.13 0.10 0.072
EJE MURO INTERIOR SS.HH ENTE EJES H,G,1,2 2 2.30 0.13 0.10 0.057
EJE 1-1,3-3 ENTE EJES G,F 4 4.15 0.13 0.10 0.208
EJE 1 ENTRE EJES H,G 2 1.81 0.13 0.10 0.045
EJE 2 ENTRE EJES H,G 1 1.81 0.40 0.10 0.072
EJE G ENTRE EJES 2,3-3 1 0.20 0.13 0.10 0.003
01.03.05 NIVELACION INTERIOR Y APISONADO m2
AREA AULAS 2 41.46 82.91
En area de SS.HH. 2 2.40 1.31 6.28
Area direccion 1 5.00 3.55 17.75
01.03.06 ELIMINACION DE MATERIAL EXCEDENTE + EL 20% DE ESPONJAMIENTO m3 1 102.84 1.2 123.41

01.04 OBRAS DE CONCRETO SIMPLE


01.04.01 SOLADO PARA ZAPATAS DE 4" MEZCLA 1:12 CEMENTO-HORMIGON m2
Z- 1 16 1.09 17.44
Z-2 7 1.00 0.80 5.60
01.04.02 CONCRETO 1:10 + 30% P.G. PARA CIMIENTOS CORRIDOS m3
Eje A,A',D,D',4,7 8 1.63 0.40 0.60 3.13
Ejes Muro diagonal de lasl aulas 8 1.63 0.40 0.60 3.13
EJE H,G ENTRE EJES 1-1,2 2 1.90 0.40 0.40 0.61
EJE F ENTE EJES 1-2, 3-3 1 2.90 0.40 0.60 0.70
EJE MURO INTERIOR SS.HH ENTE EJES H,G,1,2 1 2.30 0.40 0.50 0.46
EJE 1-1,3-3 ENTE EJES G,F 2 4.15 0.40 0.60 1.99
EJE 1,2 ENTRE EJES H,G 2 1.81 0.40 0.40 0.58
EJE G ENTRE EJES 2,3-3 1 0.20 0.40 0.60 0.048

01.04.03 ENCOFRADO Y DESENCOF. SOBRECIMIENTO m2


EJE D,A,A,D,7-7 6 2.36 0.60 8.50
EJE 4-4 1 1.36 0.60 0.82
Ejes Muro diagonal de las aulas 8 2.36 0.60 11.33
EJE H,G ENTRE EJES 1-1,2 2 2.31 0.60 2.77
EJE F ENTE EJES 1-2, 3-3 1 3.39 0.60 2.03
EJE 1,2 ENTRE EJES H,G 2 2.39 0.60 2.87
EJE G ENTRE EJES 2,3-3 1 0.85 0.60 0.51
EJE INTERIOR SS.HH 1 2.55 0.60 1.53
EJE 1-1ENTE EJES G,F 1 4.90 0.60 2.94
EJE 3-3 ENTE EJES G,F 1 4.00 0.60 2.40
01.04.04 CONCRETO 1.8 +25% PM PARA SOBRECIMIENTO m3
EJE D,A,A,D,7-7 6 2.36 0.15 0.30 0.64
EJE 4-4 1 1.36 0.15 0.30 0.06
Ejes Muro diagonal de las aulas 8 2.36 0.15 0.30 0.85
EJE H,G ENTRE EJES 1-1,2 2 2.31 0.15 0.30 0.21
EJE F ENTE EJES 1-2, 3-3 1 3.39 0.15 0.30 0.15
EJE 1,2 ENTRE EJES H,G 2 2.39 0.15 0.30 0.22
EJE G ENTRE EJES 2,3-3 1 0.85 0.15 0.30 0.04
EJE INTERIOR SS.HH 1 2.55 0.15 0.30 0.11
EJE 1-1ENTE EJES G,F 1 4.90 0.15 0.30 0.22
EJE 3-3 ENTE EJES G,F 1 4.00 0.15 0.30 0.18

01.04.05 FALSO PISO DE H=4" DE CONCRETO 1:12 , C:H m2


En area de SS.HH. 2 2.55 1.31 6.68
Area Direccion 1 5.15 3.55 18.28
En area de Aula 2 41.46 82.92

01.04.06 CONCRETO EN VEREDA DE 4" m2


Vereda En general 1 145.27 145.27

01.05 OBRAS DE CONCRETO ARMADO


01.05.01 ZAPATAS
01.05.01.01 ACERO EN ZAPATAS FY=4200 kg/cm2 kg
01.05.01.02 CONCRETO EN ZAPATAS F'C= 175 Kg/cm2 m3
Z-1 16 1.10 0.45 7.88
Z-2 7 1.00 0.80 0.40 2.24
01.05.02 COLUMNAS
01.05.02.01 ACERO EN COLUMNAS FY=4200 kg/cm2 kg 1 1010.31
01.05.02.02 ENCOFRADO Y DESENCOFRADO EN COLUMNA m2
C1 16 4.34 2.30 159.71
C2 7 0.80 2.20 12.32
01.05.02.03 CONCRETO EN COLUMNAS F'C= 210 KG/CM2 m3
C1 16 1.50 2.30 55.20
C2 7 0.25 0.15 2.20 0.58
01.05.03 VIGAS
01.05.03.01 ACERO EN VIGAS FY=4200 kg/cm2 kg 1 1.00
01.05.03.02 ENCOFRADO Y DESENCOFRADO EN VIGAS m2
VC - 1 1 15.77 0.25 3.94
VC - 2 16 2.96 0.30 14.21
VC - 3 2 10.10 0.25 5.05
01.05.03.03 CONCRETO EN VIGAS F'C= 210 KG/CM2 m3
VC - 1 1 15.77 0.15 0.25 0.59
VC - 2 16 2.96 0.25 0.30 3.55
VC - 3 10.1 2.35 0.15 0.25 0.89
TOTAL

1.00
1.00

324.00
324.00

324
30.37

12.44

4.77

106.94

123.41
23.04

10.64

30.35

2.68

24.96

145.27

223.09
10.12
1818.55
172.03

55.78

580.41
23.20

5.03