PLAN DE LLENADO

Noviembre 2016 Junio 2017


PAD UTUNSA

Planeamiento Lima
Octubre - 2016
PLAN DE MINADO PRELIMINAR:

Plan 2016 Plan 2017


Unidad sep-16 oct-16 nov-16 dic-16 ene-17 feb-17 mar-17 abr-17 may-17 jun-17 jul-17 ago-17 sep-17 oct-17 nov-17 dic-17

total
Mineral t 0 0 248,000 540,000 375,000 465,000 420,000 465,000 450,000 465,000 450,000 465,000 465,000 450,000 465,000 540,000
Desmonte t 171,988 1,350,000 1,264,800 1,296,000 825,000 1,023,000 924,000 1,116,000 675,000 465,000 225,000 232,500 139,500 135,000 93,000 108,000
SR 5.1 2.4 2.2 2.2 2.2 2.4 1.5 1.0 0.5 0.5 0.3 0.3 0.2 0.2
Ley de Au g/t 0.44 0.48 0.50 0.51 0.52 0.50 0.50 0.50 0.58 0.58 0.58 0.58 0.58 0.58
Au Depositado oz 0 0 3,484 8,264 6,064 7,625 6,981 7,512 7,270 7,483 8,391 8,671 8,671 8,391 8,671 10,070
Rec Au % % 56% 57% 58% 58% 58% 58% 58% 58% 58% 58% 58% 58% 58% 58%
Au Producido teorico oz 0 0 1,968 4,710 3,517 4,422 4,049 4,357 4,217 4,340 4,867 5,029 5,029 4,867 5,029 5,840

Mineral t/dia 0 0 8,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000
Desmonte t/dia 5,548 45,000 40,800 36,000 33,000 33,000 33,000 36,000 22,500 15,000 7,500 7,500 4,500 4,500 3,000 3,000
ESTATUS DE PAD UTUNSA:

Sector 01

Sector 03

Sector 02

Sector con lamina de Geomenbrana

Sector con trabajos avanzados (7 Ha aprox.)

Sectores Pad
Geomenbrana
Etapa 01 2016
PLAN DE LLENADO PAD UTUNSA: Nov Dic 2016

FASE 01

FASE 03
FASE 02

Sector con lamina de Geomenbrana

FASE F_INICIO F_FINAL TM LIFT


FASE 01 1-nov. 17-nov. 132,751 01 Sectores Pad
FASE 02 17-nov. 30-nov. 99,559 02 Geomenbrana
FASE 03 30-nov. 5-dic. 70,849 03 Etapa 01 2016
PLAN DE LLENADO PAD UTUNSA: Dic 2016 Ene 2017

FASE 06
FASE 05

FASE 04

FASE F_INICIO F_FINAL TM LIFT


FASE 04 5-dic. 22-dic. 194,495 01 Sectores Pad
FASE 05 22-dic. 5-ene. 220,049 02 Geomenbrana
FASE 06 5-ene. 13-ene. 117,070 03 Etapa 01 2016
PLAN DE LLENADO PAD UTUNSA: Ene Feb 2017

FASE 07

FASE 08

FASE 09

FASE F_INICIO F_FINAL TM LIFT


FASE 07 13-ene. 20-ene. 97,232 02 Sectores Pad
FASE 08 20-ene. 29-ene. 138,928 02 Geomenbrana
FASE 09 29-ene. 5-feb. 104,431 03 Etapa 01 2016
PLAN DE LLENADO PAD UTUNSA: Feb Mar 2017

FASE 12

FASE 11
FASE 10

FASE F_INICIO F_FINAL TM LIFT


FASE 10 5-feb. 16-feb. 174,078 03 Sectores Pad
FASE 11 16-feb. 11-mar. 343,054 02 Geomenbrana
FASE 12 11-mar. 29-mar. 261,201 03 Etapa 01 2016
PLAN DE LLENADO PAD UTUNSA: Mar May 2017

FASE 14

FASE 13
FASE 15

FASE F_INICIO F_FINAL TM LIFT


FASE 13 29-mar. 4-abr. 97,178 03 Sectores Pad
FASE 14 4-abr. 18-abr. 202,599 03 Geomenbrana
FASE 15 18-abr. 2-may. 220,906 04 Etapa 01 2016
PLAN DE LLENADO PAD UTUNSA: May Jun 2017

FASE 18

FASE 17

FASE 16

FASE F_INICIO F_FINAL TM LIFT


FASE 16 2-may. 25-may. 336,434 04 Sectores Pad
FASE 17 25-may. 19-jun. 384,276 03 Geomenbrana
FASE 18 19-jun. 28-jun. 126,002 04 Etapa 01 2016
CONSTRUCCION DE PAD UTUNSA 2016:

Sector 01

Sector 03

Sector 02

Sectores y fecha de Entrega:


Sector 01 : 6.5 Ha Noviembre 2016
Sector 02 : 4.5 Ha Octubre 2016
Sector 03 : 3.0 Ha Diciembre 2016

Sectores Pad
Geomenbrana
Etapa 01 2016
CAPACIDAD DE PAD: 14 Ha ( 4300,000 m3)

FASE 18

Capacidad: 6800,000 t
Volumen: 4300,000 m3
FASE 17

FASE 16

Sectores Pad
Geomenbrana
Etapa 01 2016