Documentos de Académico
Documentos de Profesional
Documentos de Cultura
(PHASES 9&10)
Inspection & Test Plan for
Atmospheric Tank Work
GS / OIEC/ IOEC
CONSORTIUM Doc. No. : ONS-09-0-PR-5254 Rev. No. : 3 Class : 1
CONTENTS
Page
1. PURPOSE 4
2. TERMS AND DEFINITIONS 4
3. REFERENCES 4
4. RESPONSIBILITY 5
5. ATTACHMENTS 5
1. PURPOSE
The purpose of this Inspection & Test Plan (ITP) is to describe the methods and establish the Quality
Plan for the Inspection & Test Plan for Atmospheric Tank Work Activities for South Pars 9&10 Project.
CONTRACTOR: The party (GS/OIEC/IOEC CONSORTIUM) which entered under Contract Agreement
with COMPANY for the Design, Engineering, Procurement and Construction of the Onshore and
Offshore Facilities regarding the South Pars Field Development Project 9&10.
SUBCONTRACTOR: shall mean any company, firm or person with whom CONTRACTOR enters into
a subcontract.
TPA (Third Party Authorities): any inspection service person or company who is independent from
COMPANY, CONTRACTOR AND SUBCONTRACTOR.
SITE: The location for installation of the facilities at ASSALUYEH or the vicinity thereof in the IRAN.
3. REFERENCES
3.1 Specification & Procedure
RP-6340S-999-6600-001 Shop and Field Painting Specification
RP-6340S-999-2500-001 Cylindrical Storage Tanks Small and Medium Size
RP-6340S-999-6300-0001 Welding of Pressure Containing Piping and Equipment
RP-6340S-999-P332-003 Field Erection Pressure Testing
COM-07-0-PR-0002 Field Material Control Procedure
ONS-09-0-PR-5300 Work Instruction for Material Receiving
ONS-09-0-PR-5400 Material Control Procedure
ONS-09-0-PR-4505 Flushing Procedure
ONS-09-0-PR-5208 Work Procedure for Welder and Welding Operator Qualification
ONS-09-0-PR-5210 Work Procedure for Welding Qualification
ONS-09-0-PR-4600 Work Procedure for Blasting & painting Application
ONS-09-0-PR-5200,1,2,3,4,7 NDT Procedures
ONS-09-0-PR-5211 PWHT Procedure
ONS-09-0-PR-5252 Inspection & Test Plan for Tank Lining Work
ONS-09-0-PR-4503 Work Procedure for Pressure Test
ONS-O9-0-PR-4506 Welding Consumable Control Procedure
3.2 Standards
API 650 Welded Steel Tanks for Oil Storage
API 620 Design and Construction of Large, Welded Low-Pressure
Storage Tanks
API 2000 Venting Atmospheric and Low-Pressure Storage Tanks
4. RESPONSIBILITIES
4.1 SUBCONTRACTOR Field QA/QC Manager is responsible for Quality Control for all kinds of
Equipment Installation Work Activities.
c) Comply with any instructions or comments by the COMPANYs Mechanical Supervisor and
Field Inspector/CONTRACTORs field inspector and Issue all field inspection reports to the
COMPANY/CONTRACTOR for review/information.
d) Maintain regular contact with the COMPANY/CONTRACTOR, including reporting all field
inspection activities.
g) Request the inspection & witness to COMPANYs Mechanical Supervisor and Field Inspector
/CONTRACTORs field inspector as per the ITP required for inspection on witness and hold
point(At least one day in advance).
h) Perform Inspection.
5. ATTACHMENTS
A MATERIAL VERIFICATION
Related Drawing
1 Verify the material condition before installation , & Vendor Manual & Material MRI-001/EQP- X W SW
Welding Consumable Control Control Procedure 016