1. PURPOSE
To provide assurance that critical controls relating to fatal hazards and management plans
are being effectively managed.
To outline the process at Glendell Mine for fatal hazard assurance monitoring and reporting
to Coal Assets Australia Glencore (CAAG), consistent with XCN SD PRO 0004 Core Hazard
Assurance Monitoring.
2. MAJOR HAZARDS
Ineffective management of fatal hazards and/or management plans leading to failure in
critical controls.
3. REQUIREMENTS
GLD SD PRES 0032 Fatal Hazard Critical Control Assurance Monitoring;
GLD SD TRN 0444 Fatal Hazard Critical Control Assurance Monitoring Competency
Assessment;
XstraSafe user profile;
GLD SD REG 0027 Fatal Hazard Critical Control Schedule;
GLD SD FRM 0027 Fatal Hazard Critical Control Specification Sheet Owners;
GLD Fatal Hazard Critical Control Specification Sheets.
4. PROCEDURE
4.1 Fatal Hazard Spec Sheet Process
1. Coal Assets Australia Glencore (CAAG) is responsible for the development of the Fatal
Hazard Critical Control Schedule. Glendell will review the schedule to determine:
> Applicability of Fatal Hazards;
> Critical control sheet owners;
> Managers responsible for control sheet completion, as per GLD SD FRM 0027 Fatal
Hazard Specification Sheet Owners.
GLD SD REG 0027 Fatal Hazard Critical Control Schedule will be updated to reflect the
requirement of XCN SD POL 0023 XCN Fatal Hazard Critical Control Schedule.
2. At the beginning of every month the HS & HR Administration Assistant will review GLD
SD REG 0027 Fatal Hazard Critical Control Schedule and download the appropriate Fatal
Hazard Critical Control Specification Sheets from the Glendell Intranet.
3. Specification sheets are then forwarded to fatal hazard owners via email stating the date
to be completed. Fatal Hazard Spec Sheet Owners and Managers are determined by GLD
SD FRM 0027 Fatal Hazard Critical Control Specification Sheet Owners.
General Manager
Operations Manager reports to General Manager
on a monthly basis
Operations Manager
Department Manager
Time Period: Select Time Period that sheet is completed in e.g. May 2011;
Operation Name: Change to Glendell Mine;
Area Owner / Person Responsible for Completion of Critical Control Sheet:
Name of person who completed spec sheet;
Fatal Hazard: Fatal Hazard the spec sheet relates to;
Fatal Hazard Critical Controls: The relevant number and name of spec sheet;
Any Significant changes to work methods or environment since last review: Yes
/ No. Alternatively copy response from control sheet
Note: Each Fatal Hazard Critical Control Specification Sheet question must be entered
separately by selecting .
.
NOTE: A corrective action must be assigned to any question that is ranked as being either
Red or Amber.
Do you agree to sign off: The manager selects Yes if they agree with the Fatal Hazard
Spec Sheet information.
Is a second level of sign off required?: Select Yes for each completed sheet.
Name of person for 2nd level sign off: Select the Operations Manager from the drop
down selection list.
The Operations Manager receives an email that there is a Fatal Hazard Critical Control
Specification Sheet that requires review and sign off.
Do you agree to sign off: Operations Manager selects Yes.
Note: The Email option is the preferred method of report generation making it easier to
forward onto the General Manager.
5. DEFINITIONS
Term Definition
Critical Control The process employed by the site to keep the core hazard in control
e.g. Regular roof bolt anchorage checks to check that roof bolts are
effective.
Fatal Hazard The basic hazard which is present in the mining environment which
may potential cause a Catastrophic or High Risk outcome e.g. Strata
Failure.
Fatal Hazard An auditing document containing a list of items to check to confirm
Critical Control that critical controls are occurring to a quality and schedule as
Specification planned.
Sheets
Term Definition
6. ACCOUNTABILITIES
Property Value
Approved by Health and Safety Manager
Keywords Core Hazard, Assurance Monitoring, Fatal Hazard Critical Control Monitoring
For a complete list of document properties, select View Properties from the documents
context menu on the intranet.
8.2 Revisions
Initial Issue;