DIS. TRIB 1.

77
PREDIMENCIONAMIENTO
VIGAS H=L/11 0.395 0.40
B=H/2 0.20 0.25
LOSA H=L/25 0.17 0.20
DONDE L= LUZ LIBRE MAYOR

LUCES 2.82
METRADOS DE CARGAS

DATOS
LOSA
PESO PROPIO 300.00 KG/M2
ACABADOS 100.00 KG/M2
TABIQUERIA 100.00 KG/M2 PEOS DEL CONCRETO
D 500.00 KG/M2

METRADO DE VIGAS PRINCIPALES DONDE D


PESO PROPIO 240.00 KG/ML V
LOSA ALIGERADA 1564.75 KG/ML
D 1804.75 KG/ML V 782.5

COLUMNA
AT(M2) ATa(M2) R1(%)
EJE NIVEL
AZOTEA 5.54 5.54
3.00 5.54 11.08 8.86
1.00
2.00 5.54 16.62 13.30
1.00 5.54 22.16 17.73
AZOTEA 9.73 9.73
3.00 9.73 19.47 15.57
2.00
2.00 9.73 29.20 23.36
1.00 9.73 38.94 31.15
AZOTEA 12.14 12.14
3.00 12.14 24.29 19.43
3.00
2.00 12.14 36.43 29.15
1.00 12.14 48.58 38.86
AZOTEA 11.83 11.83
3.00 11.83 23.66 18.93
4.00
2.00 11.83 35.49 28.40
1.00 11.83 47.33 37.86
AZOTEA 11.77 11.77

5.00
3.00 11.77 23.54 18.83
5.00
2.00 11.77 35.31 28.25
1.00 11.77 47.08 37.66
AZOTEA 7.89 7.89
3.00 7.89 15.78 12.62
6.00
2.00 7.89 23.66 18.93
1.00 7.89 31.55 25.24

COLUMNA CARGA MUERTA


PPC PD TOTAL
EJE NIVEL KG
AZOTEA 3194.41 450.00 3644.41
3.00 3194.41 450.00 3644.41
1.00
2.00 3194.41 450.00 3644.41
1.00 3194.41 450.00 3644.41
AZOTEA 5612.77 450.00 6062.77
3.00 5612.77 450.00 6062.77
2.00
2.00 5612.77 450.00 6062.77
1.00 5612.77 450.00 6062.77
AZOTEA 7002.43 450.00 7452.43
3.00 7002.43 450.00 7452.43
3.00
2.00 7002.43 450.00 7452.43
1.00 7002.43 450.00 7452.43
AZOTEA 6821.96 450.00 7271.96
3.00 6821.96 450.00 7271.96
4.00
2.00 6821.96 450.00 7271.96
1.00 6821.96 450.00 7271.96
AZOTEA 6785.86 450.00 7235.86
3.00 6785.86 450.00 7235.86
5.00
2.00 6785.86 450.00 7235.86
1.00 6785.86 450.00 7235.86
AZOTEA 4547.97 450.00 4997.97
3.00 4547.97 450.00 4997.97
6.00
2.00 4547.97 450.00 4997.97
1.00 4547.97 450.00 4997.97

AREA DE COLUMNA
AC=0.00624CPU F'C=175KG/CM2 0.00624
AC=0.00544CPU F'C=210KG/CM2 0.00544

COLUMNA
PU C AREA CM2
EJE NIVEL
AZOTEA 7959.66 1.70 73.61
3.00 15698.33 1.70 145.18
1.00
1.00
2.00 23326.50 1.50 190.34
1.00 30844.18 1.50 251.69
AZOTEA 13474.59 1.30 95.29
3.00 26266.94 1.30 185.76
2.00
2.00 38718.16 1.30 273.81
1.00 50828.26 1.30 359.46
AZOTEA 16643.63 1.30 117.70
3.00 32225.35 1.30 227.90
3.00
2.00 47276.12 1.30 334.34
1.00 61795.94 1.30 437.02
AZOTEA 16232.06 1.30 114.79
3.00 31456.25 1.30 222.46
4.00
2.00 46176.51 1.30 326.56
1.00 60392.83 1.30 427.10
AZOTEA 16149.75 1.30 114.21
3.00 31302.27 1.30 221.37
5.00
2.00 45956.17 1.30 325.00
1.00 60111.45 1.30 425.11
AZOTEA 11046.38 1.70 102.16
3.00 21644.81 1.70 200.17
6.00
2.00 32019.27 1.50 261.28
1.00 42169.76 1.50 344.11

DATOS:
FC= 210.00 KG/CM2
Fy 4200.00 KG/CM2
b 25.00
d 31.87

METRADO DECARGAS
D 1804.75 KG/ML V 782.50

CARGA DE DISEO
W=1.4D+1.7L 3.86 TN/ML

CALCULOS DE MOMENTOS NEGATIVOS EN APOYOS

APOYO 1 3.07 T-M

APOYO 2 3.15 T-M

APOYO 3 5.07 T-M

APOYO 4 4.79 T-M


APOYO 5 4.74 T-M

APOYO 6 1.79 T-M

CALCULOS DE MOMENTOS POSITIVOS EN TRAMOS

TRAMO 1-2 1.92 T-M

TRAMO 2-3 2.03 T-M

TRAMO 3-4 4.56 T-M

TRAMO 4-5 1.76 T-M

TRAMO 5-6 4.48 T-M

ACEROS NEGATIVOS EN APOYOS


P min 0.003333
As mim 2.6560

APOYO 1
M= 3.07
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 2.494
TANTEO 1
AS= MX10^5 2.6495 ASUMIR MIN
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 2.4936 CM
.85*FC*b

APOYO 2
M= 3.15
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 2.568
TANTEO 1
AS= MX10^5 2.7285 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 2.5680 CM
.85*FC*b

APOYO 3
M= 5.07
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 4.5638
TANTEO 1
AS= MX10^5 4.5312 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 4.2646 CM
.85*FC*b

APOYO 4
M= 4.79
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 4.3048
TANTEO 1
AS= MX10^5 4.2659 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 4.0150 CM
.85*FC*b

APOYO 5
M= 4.74
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 3.9457
TANTEO 1
AS= MX10^5 4.1923 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 3.9457 CM
.85*FC*b

APOYO 6
M= 1.79
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 1.4314
TANTEO 1
AS= MX10^5 1.5209 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 1.4314 CM
.85*FC*b

ACEROS NEGATIVOS EN APOYOS


TRAMO 1-2
M= 1.92
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 1.5345
TANTEO 1
AS= MX10^5 1.6304 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 1.5345 CM
.85*FC*b

TRAMO 2-3
M= 2.03
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 1.6252
TANTEO 1
AS= MX10^5 1.7267 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 1.6252 CM
.85*FC*b

TRAMO 3-4
M= 4.56
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 4.2709
TANTEO 1
AS= MX10^5 4.0580 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 3.8193 CM
.85*FC*b

TRAMO 4-5
M= 1.76
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 1.4037
TANTEO 1
AS= MX10^5 1.4914 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 1.4037 CM
.85*FC*b
TRAMO 5-6
M= 4.48
FC= 210.00
Fy 4200.00
b 25.00
d 31.87
a 3.7146
TANTEO 1
AS= MX10^5 3.9468 CM2
.9*Fy*(D-a/2)

COMPROBACION
a= AS*Fy 3.7146 CM
.85*FC*b
3.11 3.88 3.78 3.76

2.90 4.35 2.70 4.31

2400.00 KG/M3

CARGA MUERTA
CARGA VIVA

KG/ML

R(%) R(%) F

1.00
60.00 9 0.91
60.00 13 0.87
60.00 18 0.82
1.00
60.00 16 0.84
60.00 23 0.77
60.00 31 0.69
1.00
60.00 19 0.81
60.00 29 0.71
60.00 39 0.61
1.00
60.00 19 0.81
60.00 28 0.72
60.00 38 0.62
1.00
60.00 19 0.81
60.00 28 0.72
60.00 38 0.62
1.00
60.00 13 0.87
60.00 19 0.81 PS= PD ACUML+ PL ACUML
60.00 25 0.75 PU= 1.5PD ACUML+ 1.8PL ACUML

PD ACUML CARGA VIVA F PL TOTAL PL ACUML PS

3644.41 1385 1.00 1385.03 1385.03 5029.43


7288.82 1385 0.91 1262.25 2647.28 9936.09
10933.22 1385 0.87 1200.87 3848.15 14781.37
14577.63 1385 0.82 1139.48 4987.63 19565.26
6062.77 2434 1.00 2433.58 2433.58 8496.35
12125.55 2434 0.84 2054.55 4488.12 16613.67
18188.32 2434 0.77 1865.04 6353.16 24541.48
24251.09 2434 0.69 1675.52 8028.68 32279.77
7452.43 3036 1.00 3036.10 3036.10 10488.53
14904.86 3036 0.81 2446.15 5482.25 20387.11
22357.29 3036 0.71 2151.18 7633.44 29990.73
29809.72 3036 0.61 1856.21 9489.64 39299.36
7271.96 2958 1.00 2957.85 2957.85 10229.81
14543.91 2958 0.81 2397.92 5355.77 19899.68
21815.87 2958 0.72 2117.96 7473.73 29289.59
29087.82 2958 0.62 1837.99 9311.72 38399.54
7235.86 2942 1.00 2942.20 2942.20 10178.06
14471.72 2942 0.81 2388.18 5330.38 19802.10
21707.58 2942 0.72 2111.17 7441.55 29149.13
28943.44 2942 0.62 1834.16 9275.72 38219.16
4997.97 1972 1.00 1971.90 1971.90 6969.87
9995.94 1972 0.87 1723.04 3694.94 13690.88
14993.91 1972 0.81 1598.61 5293.56 20287.47
19991.88 1972 0.75 1474.19 6767.74 26759.62

SECCION

25x25
25x25
25x25
25x25 5.03 11.40
25x25 1.91 20.40
25x25 3.72 0.00
25x25 5.48 0.00
25x25 7.19 0.00
25x25 2.35 0.00
25x25 4.56 0.00
25x25 6.69 0.00
25x25 750.00 11.25 11.88
25x25 2.30 0.00
25x25 4.45 0.00
25x25 6.53 0.00
25x25 750.00
25x25
25x25 9.38
25x25
25x25 625.00
25x25
25x25
25x25
25x25

KG/ML
2.656 CM2

3.00 1/2 N DIAM


AS UTILIZAR 3.87 OK 3 3/8 0.98
4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54
3.00 1/2 N DIAM
AS UTILIZAR 3.87 OK 3 3/8 0.98
4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54

3 1/2 N DIAM
AS UTILIZAR 1.00 5/8 3 3/8 0.98
5.8500 OK 4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54

3 1/2 N DIAM
AS UTILIZAR 1.00 5/8 3 3/8 0.98
5.85 OK 4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54
3 1/2 N DIAM
AS UTILIZAR 1.00 5/8 3 3/8 0.98
5.85 OK 4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54

3.00 1/2 N DIAM


AS UTILIZAR 3.87 OK 3 3/8 0.98
4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54

3.00 1/2 N DIAM


AS UTILIZAR 3.87 OK 3 3/8 0.98
4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54
3.00 1/2 N DIAM
AS UTILIZAR 3.87 OK 3 3/8 0.98
4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54

3 1/2 N DIAM
AS UTILIZAR 1.00 5/8 3 3/8 0.98
5.85 OK 4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54

3.00 1/2 N DIAM


AS UTILIZAR 3.87 OK 3 3/8 0.98
4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54

2 1/2 N DIAM
AS UTILIZAR 1.00 5/8 3 3/8 0.98
4.56 OK 4 1/2 1.27
5 5/8 1.58
6 3/4 1.98
7 1 2.54
2.52

3.13

4.31
+ 1.8PL ACUML

PU

7959.66
15698.33
23326.50
30844.18
13474.59
26266.94
38718.16
50828.26
16643.63
32225.35
47276.12
61795.94
16232.06
31456.25
46176.51
60392.83
16149.75
31302.27
45956.17
60111.45
11046.38
21644.81
32019.27
42169.76

N DIAM AREA
3 3/8 0.98 0.71
4 1/2 1.27 1.29
5 5/8 1.58 1.98
6 3/4 1.98 2.85
7 1 2.54 5.1
7.92
AREA
0.71
1.29
1.98
2.85
5.1
AREA
0.71
1.29
1.98
2.85
5.1

AREA
0.71
1.29
1.98
2.85
5.1

AREA
0.71
1.29
1.98
2.85
5.1
AREA
0.71
1.29
1.98
2.85
5.1

AREA
0.71
1.29
1.98
2.85
5.1

AREA
0.71
1.29
1.98
2.85
5.1
AREA
0.71
1.29
1.98
2.85
5.1

AREA
0.71
1.29
1.98
2.85
5.1

AREA
0.71
1.29
1.98
2.85
5.1

AREA
0.71
1.29
1.98
2.85
5.1
ZAPATA LATERAL
ZAPATAZ 1 PS= 19565.26

CALCULO DEL PESO PROPIO DE LA ZAPATA


Ppz= 4%PS 782.61 KG

AREA DE LA ZAPATA
Rt= 1 kg/cm2
AZ= PS+PPZ = 20347.8717 cm2
Rt

Rt= Resistencia del terreno

CALCULOS DE LADOS

LX=A/2 1.01
LY=2LX 2.02

ZAPATA CENTRAL
ZAPATAZ 2 PS= 32279.77

CALCULO DEL PESO PROPIO DE LA ZAPATA


Ppz= 4%PS 1291.19 KG

AREA DE LA ZAPATA
Rt= 1 kg/cm2
AZ= PS+PPZ = 33570.9621 cm2
Rt

Rt= Resistencia del terreno

CALCULOS DE LADOS

L=A 1.83

ZAPATA CENTRAL
ZAPATAZ 3 PS= 39299.36
CALCULO DEL PESO PROPIO DE LA ZAPATA
Ppz= 4%PS 1571.97 KG

AREA DE LA ZAPATA
Rt= 1 kg/cm2
AZ= PS+PPZ = 40871.3384
Rt

Rt= Resistencia del terreno

CALCULOS DE LADOS

L=A 2.02